Control, Measurement & Energy · Course

Finding a Step and a Drift

Lesson 6 of 10 23 min read
Found this useful?

A pipe that leaks one cubic metre an hour loses 720 cubic metres in a month, and every one of them was pumped and paid for. A pump that needs a little more energy for each cubic metre every week is never “broken” on any single day, so nobody reports it until the bill is a tenth higher. In both cases the readings held the answer for weeks. After “has something changed?” comes “since when?”, because the date tells you what was lost. This lesson shows how to date a sudden step with a cumulative sum, and how to measure a slow drift with a slope and an honest range. #CUSUM #ChangeDetection #LeakDetection

Learning Objectives

By the end of this lesson, you will be able to:

  1. Distinguish a step from a drift in a series of readings
  2. Plot the cumulative sum of deviations and read the date of a change from its turn
  3. Run a tabular CUSUM and estimate when a step began and how large it is
  4. Calculate a regression slope with its 95 percent confidence interval
  5. Predict the date on which a drifting value reaches a limit, with a range

Real-World System Problem: A borehole that pumps more water than people use



A borehole pump supplies a small estate. A flow meter and a power meter are read every hour for 60 days. In the day the users draw about 4.6 m³/h. At night, between 22:00 and 06:00, they draw about 0.6 m³/h. The operator has two questions about these 60 days.

The first: the monthly volume has risen, and nobody on the estate reports using more water. Is there a leak, since which day, and how much water has it cost? A leak flows at every hour. In the day it hides inside a demand that moves by half a cubic metre an hour from one hour to the next; at night the demand is small and steady, which is why water engineers watch the night flow.

The second: the pump is some years old. Is the energy used for each cubic metre rising, how fast, and when will it reach the level at which the pump is taken out for overhaul?

The first change happened on one date. The second has no date at all, only a rate. They need different tools.

PumpEstatesupplyflow(P)(F)power metermeterday4.6m³/hboreholeleaknight 0.6 m³/h(every hour)
The borehole, its two meters and the leak

Fundamental Theory: One date or one rate



A step and a drift

A step is a change of the mean at one time, with one mean before it and another after: a pipe breaks, a valve is left open, a sensor is replaced. The questions are when, and how large.

A drift is a change that grows a little in every period: a pump impeller wears, a condenser collects dust, a sensor ages. The question is how fast.

StepDriftone dateandasizea rate, no date
Two kinds of change

The cumulative sum of deviations

Choose a reference mean from a period that you believe was normal. For each reading , take its deviation from the reference, and add the deviations as you go:

is the cumulative sum. While the process mean equals , the positive and negative deviations cancel, and wanders near a level line. If the mean rises by an amount , every new reading adds about , and climbs along a straight line with a slope of for each reading.

Reading a cumulative sum plot

The slope of over any period is the mean of that period minus . The slope changes on the day the process mean changes. The turn in the plot marks the date, and the new slope is the size of the step.

Only the slope carries meaning, not the height of on a given day. The plot adds small deviations that no single reading shows, so a step of half a standard deviation becomes plain after a few weeks. It is like a running account balance: an overspend too small to notice on any one day shows as a balance that falls steadily. (Unlike a real balance, the height itself means nothing here.)

Readings●●●●●●new mean●●●●●●●●●reference meanCumulative sum of deviationsslope = size of stepthe turn marks the date
The cumulative sum turns where the mean changes

The tabular CUSUM

The plot is read by eye. To give an alarm by rule, the tabular CUSUM is used. For an upward change it keeps one number:

Two things differ from the plain cumulative sum: a reference value is subtracted from each deviation, so ordinary small deviations pull the statistic down, and the statistic never goes below zero, so a good period cannot delay a later alarm. A signal is given when passes a decision interval . A downward change is watched with a second statistic, .

Both and are set in units of the standard deviation of the readings. Common choices are and . With the chart is at its best for a step of about one standard deviation. With and both statistics running, independent normal readings give a false alarm about once in 465 points (the value tabulated by Montgomery). The upper statistic alone, which is all a leak needs, gives one about once in 930 points. After a step of one standard deviation it signals after about 10 points on average, and after a step of half a standard deviation after about 38. An individuals chart needs 44 and 155 points for the same steps.

When did it begin, and how large is it?

The tabular CUSUM also dates the change. Count , the number of successive periods for which has been above zero.

Dating and sizing a step

The change is estimated to have begun in the first period after the last time the statistic was zero before the signal. At the signal, the size of the step is estimated as

Once the date is known, a better estimate of the size is the mean of all readings after the date minus , because it uses more data.

A drift is measured with a slope

For a drift, fit a straight line to the daily values against the day number by least squares: . The slope is the drift for each day. A slope calculated from noisy data is never exactly zero, so the slope alone proves nothing. It needs its standard error.

Confidence interval of a slope

is the root mean square error of the line, is the fitted value, and is the t value for 95 percent with degrees of freedom (about 2.00 for 60 days). If the interval does not contain zero, the drift is real at that level of confidence.

A slope is well known when the scatter is small and is large. Doubling the length of a daily record makes eight times larger and the standard error almost three times smaller.

The interval is honest only if the residuals of the line are close to independent and the drift really is a straight line. Autocorrelated residuals make the true uncertainty larger than the formula says.

The date a drift reaches a limit

If the line continues, it reaches a limit on day . For the range, remember that a fitted line always passes through the point , and the uncertainty of the slope turns the line about that point. So use each end of the slope interval from there:

This range assumes that the wear continues at the same rate. That is an assumption about the machine, not a result of the statistics.

Which tool, and what to do when both are present

Each tool gives a wrong but confident answer on the other kind of change. A line fitted through a step reports a “drift” that does not exist. A CUSUM run on a drift signals correctly that the mean has moved, but its start date has no meaning, because a drift has no start inside the record. When a series has both, date the step with the CUSUM, then fit one model with a slope term and a step term (0 before the date, 1 from it), and read each coefficient with its own interval.

Application 1: The day a leak began, from the night flow



Step 1: Night flow and the reference

Click to reveal the reference values
  1. Night flow of each day. The mean of the eight night hours gives 60 values. Days 33 to 36 are 0.621, 0.554, 1.513 and 1.486 m³/h. ✅

  2. Reference mean. The mean of days 0 to 19 is . ✅

  3. Reference standard deviation. The sample standard deviation of the same 20 values is . Each night flow is a mean of eight hourly readings, which is why it is so steady. ✅

Step 2: The cumulative sum plot

Click to reveal the plot values
  1. Level part. is 0.000 on day 19 (it must be, because is the mean of those 20 days) and only 0.085 on day 34. For 35 days the plot is level. ✅

  2. Rising part. On day 59, . The plot turns between day 34 and day 35. ✅

  3. Slope after the turn.

    The mean night flow of days 35 to 59 is 0.901 m³/h above the reference. ✅

Step 3: The tabular CUSUM

Click to reveal the signal, the date and the size
  1. Settings. and . ✅

  2. Before day 35. The largest value of in days 0 to 34 is 0.086, on day 26. It never reaches , and it is back at zero on day 34. ✅

  3. Day 35.

    This is above . The CUSUM signals on day 35. ✅

  4. Date. The statistic was last zero on day 34 and . The leak is estimated to have begun on day 35. ✅

  5. Size at the signal. , from one day. ✅

  6. Size from all days after the date. The mean night flow of days 35 to 59 is 1.4989, so the step is . ✅

Step 4: Water lost

Click to reveal the loss
  1. Each day. a day. ✅

  2. To the end of the record. Days 35 to 59 are 25 days: (from the unrounded step). ✅

Step 5: Check with a much smaller leak

This leak is 33 times the standard deviation of the night flow, so any method finds it on the first day. The check asks what the same method does with a leak of 0.03 m³/h (1.1 standard deviations), made by subtracting 0.87 m³/h from the night flow of days 35 to 59.

Click to reveal the small-leak check
  1. Single readings. The first night flow above arrives on day 48, 13 days late. ✅

  2. Tabular CUSUM. It signals on day 40, with . The statistic was last zero on day 34, so the estimated start is day , the true day. ✅

  3. Size. against a true 0.030. An estimate made at the moment of the signal is usually somewhat high. ✅

  4. Check it on site. A method that has never seen a known leak is not yet proven. Open a hose at night with a flow measured by a bucket and a stopwatch, for example 0.10 m³/h for three nights, and confirm that the night flow rises by that amount and the CUSUM signals. Some flow meters do not register flow below a starting value, and a leak smaller than that never reaches the data; the hose test shows this too. ✅

Application 2: The drift of energy for each cubic metre



Step 1: The daily values and the line

Click to reveal the fit
  1. Daily values. On day 0 the pump used 31.81 kWh for 76.75 m³, which is 0.4144 kWh per m³. On day 59 the value is 0.4602. ✅

  2. Sums. With : , , and . ✅

  3. Slope.

    The specific energy rises by about 0.00065 kWh per m³ each day. ✅

  4. Intercept. . ✅

Step 2: The confidence interval of the slope

Click to reveal the interval
  1. Scatter about the line. kWh per m³, with in the denominator. ✅

  2. Standard error of the slope.

    The slope is known to about 4 percent of its value. ✅

  3. Interval. The t value for 95 percent and 58 degrees of freedom is 2.002.

    The interval is far from zero (the slope is 27 standard errors). The drift is real. ✅

  4. In plain terms. Over the 60 days the fitted value rose by kWh per m³, which is 9.3 percent of the starting value. ✅

  5. Compare with the truth. This data set was generated with a drift of exactly 0.0006 a day. The interval, 0.000604 to 0.000699, just misses it. That is not an error in the calculation. A 95 percent interval misses the true value for about one data set in twenty, and this is one of them. ✅

Step 3: The day the line reaches the limit

Click to reveal the date and its range
  1. Best estimate.

    The line reaches 0.50 kWh per m³ during day 124, which is 3 July 2026. ✅

  2. Earliest, with the upper end of the slope interval.

    Day 118 is 27 June 2026. ✅

  3. Latest, with the lower end.

    Day 132 is 11 July 2026. ✅

  4. The honest statement. “At the present rate the pump reaches 0.50 kWh per m³ about day 125, with a range of day 118 to day 132, if the wear continues in a straight line.” The true line of the generator reaches the limit on day 133, just outside this range, for the reason given in Step 2. The prediction also lies 65 days beyond the last reading, more than the length of the record itself. ✅

  5. Check the range a second way. The shortcut above turns the line about and ignores the small uncertainty of itself. The exact method finds the days on which the 95 percent confidence band of the line, , reaches 0.50. It gives day 118.0 to day 132.3, the same range. ✅

Step 4: Check a second way, and try each tool on the wrong job

Click to reveal the checks
  1. Library check. scipy.stats.linregress returns a slope of 0.000652 and a standard error of 0.0000239, the same as the hand formulas. ✅

  2. Check without regression. The mean of the last 10 days is 0.4542 and the mean of the first 10 days is 0.4220. Their centres are 50 days apart, so the rate is a day, inside the interval. ✅

  3. Independence. The lag-1 autocorrelation of the residuals is , close to zero, so the formula for the standard error can be trusted here. ✅

  4. A line through the night flow. It gives a slope of 0.0218 m³/h a day with . It looks convincing and it is false: the night flow did not rise day by day, it rose once. ✅

  5. A CUSUM on the specific energy. With days 0 to 19 as reference it signals on day 24 and reports a start on day 15. The signal is correct, the date is meaningless: the wear began before the record did. ✅

  6. Both terms together. A model of the night flow with a slope and a step at day 35 gives a slope of m³/h a day, which includes zero, and a step of m³/h. The model correctly reports a step and no drift. ✅

Verify It in Python



The script generates the borehole data, forms the night flow, runs both forms of the CUSUM, then fits the drift of the specific energy and its interval. It saves one plot with the night flow, the two CUSUM curves and the fitted line.

step_and_drift.py
"""A step found with a CUSUM and a drift found with a regression slope (borehole pump)."""
import datetime
import numpy as np
from scipy import stats
import matplotlib.pyplot as plt
def borehole_hourly(seed=37, days=60):
rng = np.random.default_rng(seed)
h = np.arange(days * 24); hour = h % 24
demand = np.where((hour >= 6) & (hour < 22), 4.6, 0.6) # m3/h drawn by users
demand = demand * (1.0 + rng.normal(0, 0.12, h.size))
leak = np.where(h >= 35 * 24, 0.9, 0.0) # a leak starts on day 35
flow = np.clip(demand + leak, 0, None) # m3/h
kwh_per_m3 = 0.42 + 0.0006 * (h / 24.0) # slow wear: rising
power = flow * kwh_per_m3 * (1.0 + rng.normal(0, 0.03, h.size)) # kW
return h, flow, power
def tabular_cusum(x, mu0, k, h):
"""Upper tabular CUSUM. Returns C, the count N since the last zero, first signal index."""
c = np.zeros(x.size)
n = np.zeros(x.size, dtype=int)
prev, count, signal = 0.0, 0, None
for i, v in enumerate(x):
prev = max(0.0, prev + v - mu0 - k)
count = count + 1 if prev > 0.0 else 0
c[i], n[i] = prev, count
if signal is None and prev > h:
signal = i
return c, n, signal
h_idx, flow, power = borehole_hourly()
flow_d = flow.reshape(60, 24) # row = day, column = hour of the day
power_d = power.reshape(60, 24)
days = np.arange(60)
# ---------- Application 1: night flow and the leak ----------
NIGHT = [0, 1, 2, 3, 4, 5, 22, 23] # the eight night hours of one calendar day
night = flow_d[:, NIGHT].mean(axis=1)
mu0 = night[:20].mean()
sigma = night[:20].std(ddof=1)
print("Application 1: mean night flow of each day (m3/h)")
print(f" reference, days 0 to 19: mean {mu0:.4f}, s {sigma:.4f}")
print(f" days 33 to 36: " + " ".join(f"{v:.3f}" for v in night[33:37]))
S = np.cumsum(night - mu0)
print(f" cumulative sum: day 19 {S[19]:.3f}, day 34 {S[34]:.3f}, day 59 {S[59]:.3f}")
print(f" slope of the cumulative sum, days 35 to 59: {(S[59] - S[34]) / 25:.4f} m3/h")
k, h = 0.5 * sigma, 5.0 * sigma
C, N, sig = tabular_cusum(night, mu0, k, h)
start = sig - N[sig] + 1
print(f" tabular CUSUM: k {k:.4f}, h {h:.4f}")
print(f" largest C before day 35: {C[:35].max():.4f} on day {int(C[:35].argmax())}")
print(f" signal on day {sig}: C {C[sig]:.4f}, N {N[sig]}, estimated start day {start}")
print(f" step from the CUSUM, k + C/N: {k + C[sig] / N[sig]:.3f} m3/h")
step = night[start:].mean() - mu0
print(f" mean night flow from day {start}: {night[start:].mean():.4f}, step {step:.4f} m3/h")
left = 60 - start
print(f" water lost: {step * 24:.1f} m3 a day, {step * 24 * left:.0f} m3 in {left} days")
# the same data with a leak of 0.03 m3/h (the clip in the generator is never active)
small = night.copy()
small[35:] -= 0.9 - 0.03
C2, N2, sig2 = tabular_cusum(small, mu0, k, h)
beyond = np.where(small > mu0 + 3.0 * sigma)[0]
print(f" leak of 0.03 m3/h: CUSUM signal day {sig2}, N {N2[sig2]}, start day "
f"{sig2 - N2[sig2] + 1}, step {k + C2[sig2] / N2[sig2]:.3f} m3/h")
print(f" leak of 0.03 m3/h: first single day above mean + 3 s: day {beyond[0]}")
# ---------- Application 2: drift of the specific energy ----------
energy = power_d.sum(axis=1) * 1.0 # kWh a day (hourly kW x 1 h)
volume = flow_d.sum(axis=1) * 1.0 # m3 a day
y = energy / volume # kWh per m3
x = days.astype(float)
n = x.size
print("Application 2: daily kWh per m3")
print(f" day 0: {energy[0]:.2f} kWh / {volume[0]:.2f} m3 = {y[0]:.4f}; day 59: {y[59]:.4f}")
x_bar, y_bar = x.mean(), y.mean()
Sxx = ((x - x_bar) ** 2).sum()
b1 = ((x - x_bar) * (y - y_bar)).sum() / Sxx
b0 = y_bar - b1 * x_bar
res = y - (b0 + b1 * x)
s_e = np.sqrt((res ** 2).sum() / (n - 2))
se_b1 = s_e / np.sqrt(Sxx)
t = stats.t.ppf(0.975, n - 2)
lo, hi = b1 - t * se_b1, b1 + t * se_b1
print(f" x mean {x_bar:.1f}, y mean {y_bar:.5f}, Sxx {Sxx:.0f}, Sxy {b1 * Sxx:.3f}")
print(f" line: {b0:.5f} + {b1:.7f} day, RMSE {s_e:.5f}")
print(f" SE of slope {se_b1:.7f}, t {t:.3f}, 95 % interval {lo:.7f} to {hi:.7f}")
print(f" slope / SE = {b1 / se_b1:.1f}; rise over 60 days {100 * b1 * 60 / b0:.1f} %")
r1 = np.corrcoef(res[1:], res[:-1])[0, 1]
print(f" lag-1 autocorrelation of the residuals {r1:.2f}")
chk = stats.linregress(x, y)
print(f" scipy linregress: slope {chk.slope:.6f}, SE {chk.stderr:.7f}")
print(f" last 10 days minus first 10 days, over 50 days: "
f"{(y[-10:].mean() - y[:10].mean()) / 50:.6f}")
LIMIT = 0.50
cross = (LIMIT - b0) / b1
early = x_bar + (LIMIT - y_bar) / hi
late = x_bar + (LIMIT - y_bar) / lo
print(f" line reaches {LIMIT:.2f} on day {cross:.1f} (range {early:.1f} to {late:.1f})")
day0 = datetime.date(2026, 3, 1) # an example start date for day 0
for label, v in (("best", cross), ("early", early), ("late", late)):
print(f" {label}: {day0 + datetime.timedelta(days=int(v))}")
# the wrong tool for each job
wrong = stats.linregress(x, night)
print(f" a line through the night flow: slope {wrong.slope:.4f} m3/h a day, "
f"R2 {wrong.rvalue ** 2:.2f}")
A = np.column_stack([np.ones(n), x, (x >= start).astype(float)])
coef, *_ = np.linalg.lstsq(A, night, rcond=None)
r3 = night - A @ coef
se3 = np.sqrt(np.diag((r3 ** 2).sum() / (n - 3) * np.linalg.inv(A.T @ A)))
t3 = stats.t.ppf(0.975, n - 3)
print(f" line plus a step at day {start}: slope {coef[1]:.4f} +/- {t3 * se3[1]:.4f}, "
f"step {coef[2]:.3f} +/- {t3 * se3[2]:.3f} m3/h")
mu_y, s_y = y[:20].mean(), y[:20].std(ddof=1)
C3, N3, sig3 = tabular_cusum(y, mu_y, 0.5 * s_y, 5.0 * s_y)
print(f" a CUSUM on kWh per m3: signal day {sig3}, 'start' day {sig3 - N3[sig3] + 1}")
# ---------- Plot ----------
fig, ax = plt.subplots(3, 1, figsize=(8, 10))
ax[0].plot(days, night, "o-", markersize=3)
ax[0].axhline(mu0, color="gray", linewidth=0.8, linestyle="--")
ax[0].set_ylabel("night flow (m3/h)")
ax[0].set_title("Mean night flow of each day")
ax[1].plot(days, S, label="cumulative sum of deviations")
ax[1].plot(days, C, label="tabular CUSUM")
ax[1].axhline(h, color="gray", linewidth=0.8, linestyle="--")
ax[1].set_ylabel("m3/h")
ax[1].set_title("Both forms of the CUSUM")
ax[1].legend()
ax[2].plot(days, y, ".", label="daily value")
ax[2].plot(days, b0 + b1 * x, label="fitted line")
ax[2].set_xlabel("day")
ax[2].set_ylabel("kWh per m3")
ax[2].set_title("Drift of the specific energy")
ax[2].legend()
fig.tight_layout()
fig.savefig("step_and_drift.png", dpi=120)
print("Saved step_and_drift.png")

Expected output

Application 1: mean night flow of each day (m3/h)
reference, days 0 to 19: mean 0.5977, s 0.0269
days 33 to 36: 0.621 0.554 1.513 1.486
cumulative sum: day 19 0.000, day 34 0.085, day 59 22.614
slope of the cumulative sum, days 35 to 59: 0.9012 m3/h
tabular CUSUM: k 0.0134, h 0.1345
largest C before day 35: 0.0861 on day 26
signal on day 35: C 0.9020, N 1, estimated start day 35
step from the CUSUM, k + C/N: 0.915 m3/h
mean night flow from day 35: 1.4989, step 0.9012 m3/h
water lost: 21.6 m3 a day, 541 m3 in 25 days
leak of 0.03 m3/h: CUSUM signal day 40, N 6, start day 35, step 0.040 m3/h
leak of 0.03 m3/h: first single day above mean + 3 s: day 48
Application 2: daily kWh per m3
day 0: 31.81 kWh / 76.75 m3 = 0.4144; day 59: 0.4602
x mean 29.5, y mean 0.43799, Sxx 17995, Sxy 11.726
line: 0.41877 + 0.0006516 day, RMSE 0.00320
SE of slope 0.0000239, t 2.002, 95 % interval 0.0006038 to 0.0006994
slope / SE = 27.3; rise over 60 days 9.3 %
lag-1 autocorrelation of the residuals -0.06
scipy linregress: slope 0.000652, SE 0.0000239
last 10 days minus first 10 days, over 50 days: 0.000644
line reaches 0.50 on day 124.7 (range 118.1 to 132.2)
best: 2026-07-03
early: 2026-06-27
late: 2026-07-11
a line through the night flow: slope 0.0218 m3/h a day, R2 0.72
line plus a step at day 35: slope -0.0002 +/- 0.0008, step 0.905 +/- 0.030 m3/h
a CUSUM on kWh per m3: signal day 24, 'start' day 15
Saved step_and_drift.png

Common Mistakes



  • Taking the reference mean from the whole record. The change is then inside the reference mean and inside the standard deviation, so the tabular CUSUM signals late or not at all. Use a period before the change.
  • Reading the height of a cumulative sum plot. Only the slope has meaning, and a rising line means “above the reference”, not “still getting worse”.
  • Fitting a straight line through a step and reporting a drift. Plot the series first, and look at the residuals of the line.
  • Reporting a slope with no interval. A slope from noisy data is never zero, so the interval is what shows whether the drift is real.
  • Predicting the date of a limit as one day. Give the range from the slope interval, and say that it assumes the same rate continues.
  • Changing the definition of the night, or of the day boundary, in the middle of a record. The series then has a step that the definition made.

Summary



  • A step has a date and a size. A drift has a rate. Plot the series before choosing a tool.
  • The cumulative sum of deviations from a reference mean changes its slope on the day the mean changes, and the new slope is the size of the step.
  • The tabular CUSUM with and gives the alarm by rule. The change began after the last time the statistic was zero.
  • On the borehole data the night flow dated the leak to day 35 at 0.90 m³/h, which is 21.6 m³ a day and 541 m³ in 25 days.
  • A drift is reported as a slope with its interval, . The specific energy rose by 0.00065 kWh per m³ a day (0.00060 to 0.00070) and reaches 0.50 about day 125 (118 to 132).

Exercises



1. A bearing temperature has a reference mean of 12.0 °C above ambient. Ten daily values follow: 12.1, 11.9, 12.0, 12.2, 11.8, 12.6, 12.5, 12.7, 12.4, 12.6. Calculate the cumulative sum of deviations. After which reading does the slope change, and what is the size of the step?

Answer

= 0.1, 0.0, 0.0, 0.2, 0.0, 0.6, 1.1, 1.8, 2.2, 2.8. It is level for the first five readings and rises from the sixth. The slope of the last five is °C, which is the mean of the last five readings (12.56) minus 12.0.

2. A process has and . Use a tabular CUSUM with and on the readings 51, 49, 52, 53, 54, 53, 55, 54, 56, 55. Find the reading at which it signals, the estimated start, and the estimated new mean.

Answer

and . = 0, 0, 1, 3, 6, 8, 12. It passes 10 at reading 7, with . The statistic was last zero at reading 2, so the change began at reading 3. The new mean is estimated as .

3. A night-flow CUSUM dates a leak of 0.35 m³/h to 18 days ago. The pump uses 0.45 kWh for each cubic metre. Find the water and the energy lost so far, assuming the leak flows at every hour.

Answer

of water, and kWh.

4. A motor winding temperature is recorded at the same load once a day for 30 days ( to 29, so ). A fitted line has a slope of 0.050 °C a day and °C. The t value for 28 degrees of freedom is 2.048. Find the 95 percent confidence interval of the slope. Is the drift real?

Answer

. The interval is , so 0.015 to 0.085 °C a day. It does not contain zero, so the drift is real at 95 percent confidence.

5. For the motor of exercise 4, the mean of the 30 temperatures is 62.0 °C at . The limit is 70 °C. Find the day the fitted line reaches the limit, and the range from the slope interval. What does the range tell the maintenance planner?

Answer

Best estimate: , so about day 175. With the unrounded interval of 0.01543 to 0.08457: earliest , latest . The range of day 109 to day 533 is too wide to plan from. Thirty days of this data prove that the temperature is rising but not when it will reach the limit. With the same scatter, 90 days of data make about 27 times larger and the interval about five times narrower.

References



  • D. C. Montgomery, Introduction to Statistical Quality Control, 8th edition, Wiley, 2019.
  • D. C. Montgomery and G. C. Runger, Applied Statistics and Probability for Engineers, 7th edition, Wiley, 2018.
  • E. S. Page, “Continuous inspection schemes”, Biometrika, vol. 41, 1954.


© 2021-2026 SiliconWit®. All rights reserved.
supply P power meter Pump F flow meter Estate day 4.6 m³/h night 0.6 m³/h leak (every hour) borehole
The borehole, its two meters and the leak
Step Drift example size one date and a size rate a rate, no date
Two kinds of change
Readings: night flow, m³/h 0.5 1.0 1.5 reference mean 0.598 new mean 1.499 Cumulative sum of deviations, m³/h 0 10 20 day 0 10 20 30 day 35 40 50 the turn marks the date slope = size of step, 0.90
The cumulative sum turns where the mean changes
Predict first

The night flow of a borehole is 0.60 m³/h and moves by about 0.03 m³/h from night to night. A small leak of 0.03 m³/h starts on day 35. Which method shows it first?

step: a pipe breaksdrift: an impeller wears sizerate one date and a sizea rate, no date
See it: small nightly excesses add up

CUSUM signal
Single night above mean + 3σ
Estimated start and size

The night flow of the borehole in Application 1, day by day. The reference is days 0 to 19 (mean 0.5977, s 0.0269 m³/h), with k = 0.5 s and h = 5 s. The plain cumulative sum turns where the mean changes. The tabular CUSUM subtracts k from every night, cannot fall below zero, and signals when it passes h. Its start date is the day after it was last zero.

Watch it build: a drift and its date
0.420.46 day 060120 limit 0.50 slope 0.00065 kWh/m³ a day 0.000604 to 0.000699 a day reaches 0.50 on day 125 day 118 to day 132
  1. Sixty days of pump energy per m³, with the least squares line: it rises 0.00065 a day.
  2. The scatter about the line gives the 95 % range of the slope: 0.000604 to 0.000699 a day.
  3. Continued, the line reaches the overhaul limit of 0.50 kWh/m³ on day 125.
  4. Each end of the slope range, turned about the mean point, gives day 118 to day 132.
a stepa drift line says: driftsays: began here no drift existsno start exists Plot first, then choose the tool.

Check yourself

Three questions. Each wrong choice is a mistake people really make, so read the note after you answer.

1. A tabular CUSUM has μ₀ = 20, k = 0.5 and h = 5. The readings are 20.5, 19.8, 21.6, 21.4, 21.8, 21.7, 21.9. It signals at the seventh reading. From which reading do you date the change?

2. A colleague fits a straight line to 60 days of night flow and reports: drift of 0.0218 m³/h a day, R² = 0.72. What do you do before anyone acts on it?