A cyclist on a hill settles at one speed: the speed where the push the legs can give equals the push the hill asks for. A pump settles in the same way. Its duty point is the one flow and head at which the curve of the pump crosses the curve of the pipes it feeds.
See it
A pump runs at a fixed speed and feeds a building. Someone part closes a valve after the pump. What happens at the pump?
The pump curve is what the pump can give. The system curve is what the pipes need: 22 m of lift, plus friction that grows with the flow. The pump can run only where the two are equal. Closing the valve adds friction, which makes the system curve steeper and moves the crossing.
The idea
A pump at a fixed speed does not have one flow. It has a pump curve: much head when little water passes, less head when much water passes. The pipes have their own system curve: the head they need at each flow, which is the height of the lift plus the friction.
Q is the flow, H is the head in metres. The flow that makes the two heads equal is the duty point
The crossing holds itself in place. If the flow were a little higher, the pipes would need more head than the pump gives, and the water would slow down. If it were a little lower, the pump would give more than the pipes need, and the water would speed up.
Both curves are fixed only for one speed, one valve position and one set of water levels. Change any of them and the duty point moves.
One worked number
A booster pump has the curve H = 42 − 0.012 Q². Its pipes, with every valve open, need H = 22 + 0.0247 Q². Q is in m³/h and H in metres. Where does the pump run?
Show the worked solution, 3 steps
- Set the two heads equal
42 − 0.012 Q² = 22 + 0.0247 Q², so 20 = 0.0367 Q².
- Solve for the flow
Q² = 20 ÷ 0.0367 = 545, so Q = 23.3 m³/h.
- Find the head, and check it
Pump: 42 − 0.012 × 545 = 35.5 m. Pipes: 22 + 0.0247 × 545 = 35.5 m. The two agree. The figure opens at this point.
The mistake to avoid
No setting on the pump chooses the duty point. The lesson on pump curves and the duty point turns the crossing into power, running hours and cost.
Check yourself
A pump has the curve H = 50 − 0.05 Q². Its system needs H = 20 + 0.03 Q². Q is in m³/h. What is the duty point?
A new pump has 15 m³/h on its nameplate. On site the flow meter reads 12 m³/h. The pump is tested and matches its maker's curve. What is the most likely reason?
In the dry season the water level in a borehole falls by several metres. The pump and its speed do not change. What happens to the duty point?
Where you meet it
- A borehole pumpIts flow changes with the water level in the ground, because the level is part of the system curve.
- A booster pump with a valveEach turn of the valve moves the crossing along the pump curve, and the valve turns the extra head into heat.
- A chilled water or cooling water loopA clogged strainer makes the system curve steeper, and the flow falls with no fault in the pump.
- A fan and its ductsA fan curve and a duct curve cross in the same way, which is why a dirty filter cuts the air flow.
- The pump curve is what the pump can give. The system curve is what the pipes need.
- The pump runs at the crossing of the two: the duty point.
- The nameplate is one point of the pump curve, not the flow on site.
- A valve, a water level or a speed that changes moves the duty point.
Discussion
No comments yet. Questions, results from your own build, a better way to explain it: all welcome.
My notes on this page
Kept on this device only. Nothing is sent anywhere.
Tip: select words in the lesson, or tap a figure or an equation, to put a note right there.
Notes on earlier wording
The lesson has changed and these words are no longer in it. Your notes are kept, with the words you chose.