IPMVP options
On this page
To test whether a new tyre saves fuel, you can measure the fuel of one car, or read the fuel bill of the whole fleet. The second hides a small change among hundreds of others. The four IPMVP options (A, B, C and D) are the standard ways to choose where to draw the line round a saving, and which meter on that line proves it.
See it
A drive saves 2,650 kWh a year on one pump. The site's utility meter records 504,000 kWh a year. Can the monthly bill show the saving?
The dashed line is the measurement boundary. Everything inside it is covered by the claim, and every energy flow that crosses it is measured or estimated with a stated reason. The same saving is a large share of a small meter and a small share of a large one.
The idea
A saving cannot be read from any instrument: it is what was used, against what would have been used without the project. So the first decision is the measurement boundary, a line round the part of the site that the claim covers.
Options A and B draw the line round the changed equipment. In Option A the quantity the project changes, such as lamp power, is measured, and one it does not change, such as the hours, is agreed. In Option B everything that decides the energy is measured. Option C uses the utility meter of the whole facility, with a baseline model for weather and work. Option D uses a simulation calibrated to real data, where there is no past to measure.
Which one fits depends first on how large the saving is against the meter you would read.
S is the saving over a period, E is the energy the boundary meter records over the same period, f is the share
A guide often quoted for Option C is a saving above about 10% of the meter. The protocol's current edition, not this page, decides what each option requires.
One worked number
A pump drew 2.345 kW before a drive was fitted, for 3,000 hours a year. The drive saves 2,650 kWh a year. The site uses 504,000 kWh a year. What share is the saving at the utility meter, and at a meter on the pump?
Show the worked solution, 3 steps
- At the utility meter
f = 2,650 ÷ 504,000 = 0.53%, less than the site's ordinary scatter.
- Energy inside the pump boundary
Before the drive the pump used 2.345 kW × 3,000 h = 7,035 kWh a year.
- The share there
f = 2,650 ÷ 7,035 = 37.7%. The same saving is now plain. Check it in the figure: compare Option B with Option C.
The mistake to avoid
A second trap is in Option A: the saving moves with the agreed value in full proportion. Write down where it came from, such as a time switch setting or a log.
Check yourself
Repairing compressed air leaks saves 30,000 kWh a year. The site uses 1,200,000 kWh a year. Which choice fits?
Under Option A a motor's power is measured as 9.8 kW before and 9.1 kW after. The parties agree 5,000 hours a year. The motor really runs 4,200 hours. What saving does the contract pay on?
A power factor correction bank lowers the demand charge on the bill and saves almost no kWh. Where should the boundary be?
Where you meet it
- A lighting change in a storeThe power of the new fittings is measured and the hours are agreed: Option A.
- A drive on a borehole pumpPower and flow are both logged, because the water demand changes: Option B.
- A whole office buildingSeveral measures together save a large share of the utility meter: Option C.
- A new buildingThere is no past year to measure, so a calibrated simulation stands in for it: Option D.
- The measurement boundary decides what the claim covers and which meter proves it.
- A and B: round the equipment. C: the whole facility. D: a calibrated simulation.
- Share = saving ÷ energy at the boundary meter. A small share needs a smaller boundary.
- In Option A, write down the source of every agreed value.
Discussion
No comments yet. Questions, results from your own build, a better way to explain it: all welcome.
My notes on this page
Kept on this device only. Nothing is sent anywhere.