Non-Routine Adjustments
On this page
An energy project is promised to save 12 percent, and the first savings report shows less than 5 percent. The contractor is not paid and the owner believes the project failed. Three months later somebody remembers that production installed a new process line in the same period, and that it runs every working day. The project worked as promised: the site changed, and nobody had agreed what to do when a site changes. This lesson shows how to list what must stay the same, find a change that was not reported, and correct the saving for it in a way both parties accept. #NonRoutineAdjustments #StaticFactors #MeasurementAndVerification
Learning Objectives
By the end of this lesson, you will be able to:
- List the static factors of a site or a machine with their values in the baseline period
- Calculate the effect of an added load on the apparent saving, in kWh and in percentage points
- Make a non-routine adjustment by engineering calculation and from a sub-meter, and compare the two
- Detect an unreported change from a step in the baseline residuals
- Record an adjustment so that the owner and the contractor can both check it and agree it
Real-World System Problem: A site that changes during the project
An office and workshop building has one utility meter. A baseline model was fitted to a year of daily readings: energy against cooling degree days and a weekday term. An energy measure was installed on day 500, and the saving for days 500 to 729 is the adjusted baseline energy minus the measured energy.
The baseline model knows only two things about a day: how warm it was, and whether it was a working day. A machine added on day 600 is recorded by the utility meter but not expected by the model, so its energy is taken out of the saving, as a bag held on a scale hides part of a weight loss. The measure has not failed, and the report is still wrong. A project measured for a year or more will meet at least one such change, so the method must be agreed before it arrives.
Fundamental Theory: What must stay the same, and what to do when it does not
Two kinds of change
The energy of a site changes for two kinds of reason.
The first kind changes every day and is expected to: the weather, the production quantity, the number of working days. These are the independent variables. They are measured through both periods and placed in the baseline model, which corrects for them: the routine adjustment.
The second kind is expected not to change at all: the floor area, the number of shifts, the equipment installed, the set points. These are the static factors. They are not in the model, because in the baseline period they had one value only, and a model cannot learn the effect of something that never moved.
Static factors
A static factor is a property of the site, inside the measurement boundary, that affects energy and is expected to stay constant through the baseline period and the reporting period. Common static factors are:
| Static factor | Example of a baseline value |
|---|---|
| Conditioned floor area | 1,850 m² |
| Occupancy and shifts | One shift, 08:00 to 17:00, five days a week |
| Equipment installed | The list of loads above 1 kW, with their rated power |
| Set points | Offices 24 °C, cold room 4 °C |
| Building envelope | Glazing, insulation, shading as built |
The measurement and verification plan must list the static factors with their values in the baseline period. Names alone are not enough: “Set point” proves nothing a year later, while “Cold room set point 4 °C, read from the controller on the day the baseline ended” can be compared with what the controller shows today.
The list is written before anyone knows which party a change will favour, so the same rule applies to a change that reduces the saving and to one that increases it.
The savings equation with its third term
The course writes the saving as
The sign follows from one question: what would the baseline site have used with the same change? An added load raises the reporting period energy for a reason that is not the measure, so its energy is added to the saving (the same as adding it to the baseline). A removed load or a closed area has the opposite sign and reduces the saving.
Two ways to find the size of the adjustment
By engineering calculation. The effect is calculated from the physics of the change: power times hours for an added load, or a heat balance for a set point, with every input written down with its source. This costs little and can be done after the event. Its weakness is the inputs: a motor with 9 kW on its nameplate does not draw 9 kW at part load, and “10 hours a day” is often a plan, not a record.
By measurement. A sub-meter on the new load gives the adjustment as its reading. This is the stronger method when the load varies or will stay for years. It cannot measure the weeks before it was fitted, and fitting it is mains work for a licensed electrician.
The International Performance Measurement and Verification Protocol (IPMVP) uses the terms static factors and non-routine adjustments, and this lesson describes the idea in its own words. Where a contract names the protocol, the current edition decides how a change is identified, quantified and reported.
Finding a change that nobody reported
A residual is the measured energy of a day minus its adjusted baseline. In the reporting period the residuals are negative, because the measure saves energy, and they scatter round a steady level. A change in a static factor moves that level: a load that starts on one day gives a step.
To test a step, take the mean residual of a group of days before the suspected date and of a group after it. The difference is the step. Its standard error is
where
The record also says what kind of change it was: a step on working days only points to a process or to people, a step on all days to equipment that never stops. This needs a reading for each day. Two bills, one before and one after, give two numbers, which cannot separate a new load from cooler weather or from the saving itself.
The paperwork of an adjustment
Three things make an adjustment acceptable to both parties.
Somebody is responsible for reporting changes. The plan names a person on the owner’s side (often the site or maintenance manager) who reports any change to a listed static factor within a stated time. The contractor reviews the residuals at each report and asks about any step.
Each adjustment has a record. One page is enough. The example uses the numbers of Application 1.
Both parties agree it. The adjustment enters the savings report only after both have signed the record. The report then shows three lines, not one: the saving before adjustment, each adjustment with its method, and the saving after adjustment.
A change that will stay for years, such as a building extension, is better handled once: the parties agree a new baseline that includes it and record the date from which it applies.
Application 1: A process load added during the reporting period
Step 1: The apparent saving
Click to reveal the apparent saving
-
Saving with no change on the site.
This is the reference: the avoided energy the report should show. ✅
-
Saving as the meter shows it.
The apparent saving is 4.61 percent. ✅
-
What was lost.
The new load hides 60 percent of the saving. ✅
Step 2: Adjustment by engineering calculation
Click to reveal the calculation
-
Energy on one weekday.
✅
-
Number of weekdays. Days 600 to 729 are 130 days. The remainder of 600 divided by 7 is 5, so day 600 is the first day of a weekend. Days 600 to 725 are 18 whole weeks, with
weekdays. Days 726 to 729 have remainders 5, 6, 0 and 1, which adds 2 weekdays. The total is 92. ✅ -
The adjustment.
✅
-
Adjusted saving.
The saving returns exactly to the reference, because in this data the load is exactly 9 kW for exactly 10 hours. ✅
Step 3: Adjustment by sub-meter
Click to reveal the measured adjustment
-
The adjustment. The sub-meter recorded 8,307 kWh on the new load from day 600 to day 729. This reading is the adjustment. ✅
-
Adjusted saving.
✅
-
Compare the two methods. They differ by 27 kWh, 0.3 percent of the adjustment. With a load that varies, only the sub-meter is right. On a real site the sub-meter is often fitted only after the step is found, say on day 650. Then the days before it are filled with the sub-meter’s measured kWh per working day, and the record says which days were metered and which were filled. ✅
-
Against the true figure. The data contain a true saving of 12 percent, 14,593 kWh. Both adjusted values are about 11.5 percent. The remaining difference is the uncertainty of the baseline model, which is present with or without the process load. ✅
Step 4: Detect the change in the record
Click to reveal the detection
-
Step on weekdays.
The standard error is 3.9 kWh, so the step is 28 standard errors. It is not chance. ✅
-
Step on weekend days.
With a standard error of 6.7 kWh this is 2.8 standard errors: probably real, and much smaller. ✅
-
Why the weekend days moved. The measure saves 12 percent of what the site would have used. Days 600 to 729 are cooler than days 500 to 599, so the site uses less, and 12 percent of less is fewer kWh: the residuals of all days rise by about 19 kWh. No load was added on weekend days. ✅
-
The load itself. The weekend days act as the control: days that the change did not touch, so their step shows what moved for other reasons.
The record gives a load of about 90 kWh on working days only, starting near day 600, with no information from the site at all. Check it three ways before anyone signs: the residuals give 89.9 kWh a weekday, the sub-meter
, and the nameplate calculation 90. Three routes that agree make an adjustment both parties can accept; if one disagrees, find out why first. ✅ -
Why two bills fail. As two bills, the site used 544.9 kWh a day in days 500 to 599 and 467.8 kWh a day in days 600 to 729. The second figure is lower, because the weather was cooler. A reader of the bills sees a fall and no sign of a new load. ✅
-
Check with the script. The script counts 92 weekdays and prints 5,577 kWh (4.61 percent), adjustments of 8,280 and 8,307 kWh, and steps of
and kWh, as found by hand. ✅
Application 2: A colder set point in the cold room
Step 1: The saving before any adjustment
Click to reveal the unadjusted saving
-
Adjusted baseline.
kWh. ✅ -
Measured.
kWh. This is 14.40 kWh a day in the first 60 days and 15.90 kWh a day in the last 120. ✅ -
Unadjusted saving.
✅
Step 2: The effect of the set point
Click to reveal the engineering model
-
The room at 4 °C.
The model gives 14.35 kWh against 14.40 measured in the first 60 days. ✅
-
The room at 2 °C with the load held. Only the machine changes.
The weaker machine alone costs 0.71 kWh a day. ✅
-
The room at 2 °C with its own loads. A colder room gains more heat.
The set point costs 1.57 kWh a day (from unrounded values), which is 11 percent of the room’s energy. ✅
Step 3: The adjustment and a check
Click to reveal the adjusted saving
-
The adjustment. The colder set point applied for 120 days.
✅
-
Adjusted saving.
(the money figure uses unrounded values). The adjustment is worth 2,255 currency units. ✅
-
Check against the measurement. The sub-meter shows a step of
kWh a day on day 61. The model predicted 1.57. With the load held, the model would have given 0.71 kWh a day, an adjustment of only 85 kWh, less than half of what the meter shows. The fuller model is the one that agrees with the measurement. ✅ -
Check the model against its source. For the room without the curtain, the sister course gives 18.23 kWh a day at 4 °C, about 19.17 kWh at 2 °C with the load held and about 20.3 kWh with the loads recalculated (36.95 and 39.53 kWh of heat). The script reproduces these with the same formula: 18.23, 19.18 and 20.31 (the 0.01 is rounding of the machine figures). ✅
Verify It in Python
The script rebuilds the site data, adds the process load from day 600, makes both adjustments, tests the step in the residuals and runs the cold room model. It saves one plot: the residuals of the reporting period, weekdays and weekend days marked apart, with the mean weekday level before and after day 600.
"""Non-routine adjustments: an added process load on the site, a set point in the cold room."""import numpy as npimport matplotlib.pyplot as plt
PRICE = 12.00 # currency units per kWh
def building_daily(seed=23, days=730): rng = np.random.default_rng(seed) d = np.arange(days) temp = 21.0 + 4.5 * np.sin(2 * np.pi * (d - 20) / 365.0) + rng.normal(0, 1.6, days) weekday = (d % 7) < 5 cdd = np.clip(temp - 18.0, 0.0, None) energy = 310.0 + 42.0 * cdd + np.where(weekday, 180.0, 0.0) + rng.normal(0, 28.0, days) energy[500:] *= 0.88 return d, temp, weekday, energy # kWh a day
# ---------- Part 1: the site, with a process load added from day 600 ----------d, temp, weekday, energy = building_daily()cdd = np.clip(temp - 18.0, 0.0, None)X = np.column_stack([np.ones(d.size), cdd, weekday.astype(float)])base = slice(0, 365)coef, *_ = np.linalg.lstsq(X[base], energy[base], rcond=None)rmse = np.sqrt(np.sum((energy[base] - X[base] @ coef) ** 2) / (365 - 3))print("Baseline fitted on days 0 to 364")print(f" energy = {coef[0]:.1f} + {coef[1]:.2f} x CDD + {coef[2]:.1f} x weekday, RMSE {rmse:.2f} kWh")
rep = (d >= 500)adj_base = (X @ coef)[rep].sum()clean = energy[rep].sum()print("Days 500 to 729 with no change on the site")print(f" adjusted baseline {adj_base:.0f}, measured {clean:.0f}, " f"avoided {adj_base - clean:.0f} kWh = {100 * (adj_base - clean) / adj_base:.2f} %")
P_LOAD, H_LOAD, START = 9.0, 10.0, 600 # kW, hours on each weekday, first dayadded = np.where((d >= START) & weekday, P_LOAD * H_LOAD, 0.0)site = energy + added # what the utility meter recordsn_wd = int(np.sum((d >= START) & weekday))measured = site[rep].sum()apparent = adj_base - measuredprint("The same days with the process load on the utility meter")print(f" weekdays from day {START} to 729: {n_wd}")print(f" measured {measured:.0f} kWh, apparent avoided energy {apparent:.0f} kWh " f"= {100 * apparent / adj_base:.2f} %")print(f" the saving appears smaller by {adj_base - clean - apparent:.0f} kWh, " f"{100 * (adj_base - clean - apparent) / adj_base:.2f} percentage points")
nra_calc = P_LOAD * H_LOAD * n_wdrng = np.random.default_rng(7)submeter = np.where((d >= START) & weekday, P_LOAD * H_LOAD + rng.normal(0, 3.0, d.size), 0.0)nra_meter = submeter.sum()for name, nra in (("engineering calculation", nra_calc), ("sub-meter", nra_meter)): s = apparent + nra print(f" adjustment by {name}: {nra:.0f} kWh, adjusted saving {s:.0f} kWh " f"= {100 * s / adj_base:.2f} %")true = 0.12 * clean / 0.88print(f" true saving in the data: {true:.0f} kWh = 12.00 % of the true unsaved energy")print(f" a nameplate error of 10 %: adjustment {1.1 * nra_calc:.0f} kWh, " f"saving {100 * (apparent + 1.1 * nra_calc) / adj_base:.2f} %")
resid = site - X @ coef # measured minus adjusted baselineprint("Detection: mean residual (measured minus adjusted baseline), kWh a day")for name, mask in (("weekdays", weekday), ("weekend days", ~weekday)): a = resid[(d >= 500) & (d < START) & mask] b = resid[(d >= START) & mask] se = np.sqrt(a.var(ddof=1) / a.size + b.var(ddof=1) / b.size) print(f" {name}: days 500 to 599 {a.mean():+.1f} (n = {a.size}), " f"days 600 to 729 {b.mean():+.1f} (n = {b.size}), " f"step {b.mean() - a.mean():+.1f}, standard error {se:.1f}")a = resid[(d >= 500) & (d < START)]b = resid[d >= START]print(f" all days: {a.mean():+.1f} and {b.mean():+.1f}, step {b.mean() - a.mean():+.1f}")print(" as two bills: days 500 to 599 " f"{site[500:600].mean():.1f} kWh a day, days 600 to 729 {site[600:].mean():.1f} kWh a day")
# ---------- Part 2: the cold room, set point lowered from 4 to 2 degC ----------FAN_C, E_EVAP = 0.090, 2.88 # condenser fan kW, evaporator fans kWh a dayMACHINE = {4: (3.000, 1.156), 2: (2.764, 1.129)} # set point: capacity kW, compressor kW
def room_day(load_kwh, setpoint): """Daily electricity (kWh) from the daily load of heat and the machine figures.""" cap, w = MACHINE[setpoint] hours = load_kwh / cap return hours, hours * (w + FAN_C) + E_EVAP
print("Cold room: check of the model against the design day")for name, load, sp in (("4 degC", 36.95, 4), ("2 degC, load held", 36.95, 2), ("2 degC, loads recalculated", 39.53, 2)): h, e = room_day(load, sp) print(f" {name}: load {load:.2f} kWh, {h:.2f} h, {e:.2f} kWh a day")print(f" system COP {3.000 / 1.156:.3f} at 4 degC, {2.764 / 1.129:.3f} at 2 degC " f"({100 * (2.764 / 1.129) / (3.000 / 1.156) - 100:+.1f} %)")
EFF = 0.85 # strip curtain effectivenessload4 = 36.95 - EFF * 10.99 # reporting period room at 4 degCextra = (10.22 - 9.45) + (1 - EFF) * (11.74 - 10.99) + (12.14 - 11.08)load2 = load4 + extrah4, e4 = room_day(load4, 4)h2h, e2h = room_day(load4, 2)h2, e2 = room_day(load2, 2)print("Cold room with the strip curtain (the reporting period)")print(f" 4 degC: load {load4:.2f} kWh, {h4:.2f} h, {e4:.2f} kWh a day")print(f" 2 degC, load held: {h2h:.2f} h, {e2h:.2f} kWh a day ({e2h - e4:+.2f})")print(f" 2 degC, loads recalculated: load {load2:.2f} kWh (+{extra:.2f}), {h2:.2f} h, " f"{e2:.2f} kWh a day ({e2 - e4:+.2f})")
BASE_DAY, DAYS, DAYS_COLD = 26.1, 180, 120E_FIRST, E_COLD = 864.0, 1908.0 # sub-meter totals, kWhbaseline = BASE_DAY * DAYSreported = E_FIRST + E_COLDunadjusted = baseline - reportedprint("Reported saving over 180 days")print(f" baseline {baseline:.0f} kWh, measured {reported:.0f} kWh " f"({E_FIRST / 60:.2f} then {E_COLD / DAYS_COLD:.2f} kWh a day)")print(f" unadjusted saving {unadjusted:.0f} kWh = {unadjusted * PRICE:.0f} currency units")for name, per_day in (("load held", e2h - e4), ("loads recalculated", e2 - e4)): nra = per_day * DAYS_COLD print(f" adjustment, {name}: {per_day:.2f} x {DAYS_COLD} = {nra:.0f} kWh, " f"adjusted saving {unadjusted + nra:.0f} kWh = {(unadjusted + nra) * PRICE:.0f} currency units")print(f" expected with no change of set point: {(BASE_DAY - 14.4) * DAYS:.0f} kWh")print(f" measured step at the sub-meter: {E_COLD / DAYS_COLD - E_FIRST / 60:+.2f} kWh a day, " f"model {e2 - e4:+.2f}")
# ---------- Plot ----------fig, ax = plt.subplots(figsize=(8, 5))m = rep & weekdayax.plot(d[m], resid[m], ".", label="weekdays")m = rep & ~weekdayax.plot(d[m], resid[m], "x", label="weekend days")for lo, hi in ((500, START), (START, 730)): sel = (d >= lo) & (d < hi) & weekday ax.hlines(resid[sel].mean(), lo, hi, linewidth=2)ax.axvline(START, color="gray", linewidth=0.8)ax.axhline(0.0, color="gray", linewidth=0.8)ax.set_xlabel("day")ax.set_ylabel("measured minus adjusted baseline, kWh a day")ax.set_title("A step in the residuals on weekdays from day 600")ax.legend()fig.tight_layout()fig.savefig("non_routine_adjustment.png", dpi=120)print("Saved non_routine_adjustment.png")Expected output
Baseline fitted on days 0 to 364 energy = 306.6 + 41.61 x CDD + 182.1 x weekday, RMSE 27.30 kWhDays 500 to 729 with no change on the site adjusted baseline 120871, measured 107014, avoided 13857 kWh = 11.46 %The same days with the process load on the utility meter weekdays from day 600 to 729: 92 measured 115294 kWh, apparent avoided energy 5577 kWh = 4.61 % the saving appears smaller by 8280 kWh, 6.85 percentage points adjustment by engineering calculation: 8280 kWh, adjusted saving 13857 kWh = 11.46 % adjustment by sub-meter: 8307 kWh, adjusted saving 13884 kWh = 11.49 % true saving in the data: 14593 kWh = 12.00 % of the true unsaved energy a nameplate error of 10 %: adjustment 9108 kWh, saving 12.15 %Detection: mean residual (measured minus adjusted baseline), kWh a day weekdays: days 500 to 599 -77.5 (n = 72), days 600 to 729 +31.4 (n = 92), step +108.9, standard error 3.9 weekend days: days 500 to 599 -54.7 (n = 28), days 600 to 729 -35.7 (n = 38), step +19.0, standard error 6.7 all days: -71.1 and +11.8, step +82.9 as two bills: days 500 to 599 544.9 kWh a day, days 600 to 729 467.8 kWh a dayCold room: check of the model against the design day 4 degC: load 36.95 kWh, 12.32 h, 18.23 kWh a day 2 degC, load held: load 36.95 kWh, 13.37 h, 19.18 kWh a day 2 degC, loads recalculated: load 39.53 kWh, 14.30 h, 20.31 kWh a day system COP 2.595 at 4 degC, 2.448 at 2 degC (-5.7 %)Cold room with the strip curtain (the reporting period) 4 degC: load 27.61 kWh, 9.20 h, 14.35 kWh a day 2 degC, load held: 9.99 h, 15.06 kWh a day (+0.71) 2 degC, loads recalculated: load 29.55 kWh (+1.94), 10.69 h, 15.91 kWh a day (+1.57)Reported saving over 180 days baseline 4698 kWh, measured 2772 kWh (14.40 then 15.90 kWh a day) unadjusted saving 1926 kWh = 23112 currency units adjustment, load held: 0.71 x 120 = 85 kWh, adjusted saving 2011 kWh = 24134 currency units adjustment, loads recalculated: 1.57 x 120 = 188 kWh, adjusted saving 2114 kWh = 25367 currency units expected with no change of set point: 2106 kWh measured step at the sub-meter: +1.50 kWh a day, model +1.57Saved non_routine_adjustment.pngIn the plot the weekday residuals lie near
Common Mistakes
- Listing static factors by name only. Without the baseline value (4 °C, one shift, 1,850 m²) nobody can show later that a factor changed.
- Adjusting only for changes that reduce the saving. Equipment that was removed and areas that were closed must be adjusted with the opposite sign.
- Using nameplate power and planned hours as if they were measured. Write them down as estimates, and fit a sub-meter when the load is large or varies.
- Treating a step in the residuals as proof of its cause. The step shows that something changed and when. A visit to the site must find what.
- Making an adjustment alone and showing only the adjusted saving. Show the saving before, the adjustment and the saving after, with both signatures.
Summary
- Independent variables change routinely and are handled by the baseline model. Static factors are expected to stay constant, and a change in one needs a non-routine adjustment.
- The plan lists the static factors with their baseline values and names who reports a change.
- A 9 kW load on 92 weekdays reduced the apparent saving from 13,857 to 5,577 kWh (11.46 to 4.61 percent). An adjustment of 8,280 kWh by calculation, or 8,307 kWh by sub-meter, restored it.
- The baseline residuals showed the change as a step of 108.9 kWh on weekdays against 19.0 kWh on weekend days. Two bills showed nothing.
- In the cold room a set point 2 K lower cost 1.57 kWh a day by the engineering model and 1.50 kWh by the sub-meter, and the adjustment of 188 kWh brought the saving to 2,114 kWh.
- An adjustment is valid when its cause is identified, its method and inputs are recorded, and both parties have agreed it.
Exercises
1. A site has an adjusted baseline of 310,000 kWh for the reporting period and an apparent saving of 21,300 kWh. A compressor was added during the period. A logger shows a mean power of 11 kW for 8 hours on each of 110 working days. Find the adjustment and the saving before and after it, in kWh and percent.
Answer
2. On another site the adjusted baseline is 400,000 kWh and the apparent saving is 52,000 kWh. During the last 150 days of the reporting period a server room of 4 kW, which ran 24 hours a day in the baseline period, was moved to another building. Find the adjusted saving.
Answer
The removed load would have used
3. The residuals of a reporting period have a mean of
Answer
Step:
4. A cold room of the same design as in Application 2 has a daily load of heat of 30.0 kWh, which you may hold constant. Its set point is lowered from 4 °C to 2 °C for 75 days of the reporting period. Use the machine figures of Application 2 to find the daily electricity at each set point and the adjustment. Is this adjustment too large or too small?
Answer
At 4 °C:
References
- Efficiency Valuation Organization, International Performance Measurement and Verification Protocol (IPMVP): Core Concepts, current edition.
- ASHRAE, Guideline 14-2014: Measurement of Energy, Demand, and Water Savings, ASHRAE, 2014.
- ISO 50015:2014, Energy management systems: Measurement and verification of energy performance of organizations: General principles and guidance.
- B. L. Capehart, W. C. Turner and W. J. Kennedy, Guide to Energy Management, 8th edition, Fairmont Press, 2016.
During the reporting period the owner closes one wing of the building. The reported saving goes up. What should the savings report do with the closed wing?
The lesson's own site, days 500 to 729: each mark is measured energy minus the adjusted baseline of that day, with the measure saving 12 percent. Dots are weekdays, rings are weekend days. The added load runs 10 hours on each weekday from its first day. The lines are the mean of each group before and after that day. With no load the saving is 13,857 kWh, 11.46 percent of the adjusted baseline of 120,871 kWh.
Check yourself
Three questions. Each wrong choice is a mistake people really make, so read the note after you answer.
1. On the site of Application 1, suppose the 9 kW process load had started on day 520 instead of day 600, still 10 hours on each weekday. Days 520 to 729 hold 150 weekdays. What saving would the report show before any adjustment?
2. In another reporting period the residuals rise by 40 kWh a day on all days, weekends too, with a standard error of 5 kWh. The site manager knows of no change, and a visit finds no cause. What goes into the report?
3. A pump with 7.5 kW on its nameplate is added and runs 12 hours a day for 100 days. A logger on its supply shows a mean power of 5.2 kW. Which adjustment belongs in the report?
- Adjusted baseline 120,871 kWh. A 9 kW load runs from day 600, the meter reads 115,294: only 5,577 shown.
- The load is not the measure, so its 8,307 kWh is added back: the saving is 13,884 kWh.
- Had a 9 kW load been removed, the saving shown would be 22,137; the adjustment takes 8,280 away.
Discussion
No comments yet. Questions, results from your own build, a better way to explain it: all welcome.
My notes on this page
Kept on this device only. Nothing is sent anywhere.