Avoided energy at a retrofit isolation boundary
Writing a Measurement and Verification Plan
On this page
A drive is fitted to a pump, and a year later the contractor brings one power reading that shows a saving of 38 percent, while the owner brings twelve electricity bills that show nothing. Both are honest and both numbers are correct, and there is no way to choose between them, because nobody wrote down how the saving would be found. This lesson shows how to write the document that prevents this: a measurement and verification plan, agreed before the work starts. #MeasurementAndVerification #EnergySavings #MVPlan
Learning Objectives
By the end of this lesson, you will be able to:
- List what a measurement and verification plan fixes before the work starts, with the reason for each item
- Write the savings calculation of a project as a formula that a second person can apply to the same data
- Calculate the expected precision of a yearly saving from the uncertainties of the meters
- Compare the cost of measurement with the saving it verifies
- Review a plan and say what each omission would let either party argue later
Real-World System Problem: A booster pump, a drive and two signatures
A booster pump supplies water to a building for about 3,000 hours a year. Its flow is controlled by a throttling valve, and at the usual flow of about 12 m³/h it draws 2.345 kW. A contractor offers a variable speed drive for 95,000 currency units and expects the pump to draw 1.462 kW afterwards. The owner will pay in part from the saving.
A saving is a comparison with what would have happened without the project, which can never be measured. It is calculated from a baseline, and the baseline exists only if somebody recorded it before the work: once the drive is fitted, the throttled pump is gone.
So every choice that decides the number is made first: which meter, at which place, over which days, with which formula and at which price. The plan records those choices, and both parties sign it while neither knows which choice will favour them, as the finish line of a race is agreed before the start.
Fundamental Theory: What the plan fixes before work starts
A plan is a set of decisions with dates
A measurement and verification plan is a short document that states how the saving of one project will be determined. Each decision in it is made before the data it governs exist.
The plan promises a method, not a result. If the drive saves less than expected, a good plan shows that clearly, and both parties accept the number because they accepted the method.
The fourteen items
This list is the course’s own summary, a study aid. The International Performance Measurement and Verification Protocol (IPMVP) and ISO 50015 each describe what a plan must contain, and where a contract names one of them, its current edition decides.
- The measure and its intent. What is changed, and what service must stay the same. Without the intent, a saving made by giving less water or less light counts as a success.
- The measurement boundary. The closed line round what the claim covers. It decides which meter can prove the saving and which effects are outside the claim.
- The option. Retrofit isolation or whole facility, and what is measured against what is estimated. Each option gives a different number, so the choice cannot wait for the results.
- The baseline period and its data. The dates, the quantities logged, the interval and where the file is kept. This record cannot be made again after the work.
- The baseline model. The formula, its coefficients, its fit and the range of conditions in which it is valid. A model chosen after the results can be chosen to suit them.
- The independent variables and the static factors. What the model corrects for, and what must stay constant, each static factor with its baseline value. This is the only basis for a later adjustment.
- The reporting period. Its start, its length, and whether the result is avoided energy or normalised savings. A period chosen afterwards can be the best months.
- The meters and their calibration. Type, place, accuracy and calibration date of each. The same meters at the same points serve both periods.
- The calculation. The formula, with the rule for missing data. A second person must reach the same number from the same file.
- The energy price. The price per kWh for every report, and whether demand charges are claimed. A price left open moves the money without moving any energy.
- The expected precision. The uncertainty the method will give, calculated in advance. It shows whether the saving can be seen at all, before money is spent on meters.
- Responsibilities. Who reads the meters, who keeps the data, who reports a change on the site and how soon. A task with no name is done by nobody.
- The report format and frequency. What each report contains and when it is due. Both parties then know what they will receive.
- The budget for measurement. What the measurement costs, and its share of the saving. Measurement is paid for from the saving it proves.
The protocol’s own list also asks how the work will be checked (quality assurance): who checks the data file, the calculation and the report before they go out. Put that under item 12, with a name.
The calculation as a formula
A sentence such as “the saving will be measured at the pump” is not a calculation. A formula is. For a retrofit isolation with a baseline model, the avoided energy of a period is
The sum runs over the intervals in which the equipment ran. The plan also says what happens to an interval with no data: the fair rule leaves it out of both terms, and the report states how many hours were lost.
Expected precision, before any money is spent
The uncertainties of the meters pass into the saving. Write the saving as a power difference
The expanded uncertainty is
The budget for measurement
A commonly quoted guide is that measurement and verification should cost only a small share of the saving it verifies, often not more than about 10 percent of the yearly saving. Treat it as a guide, not a rule, and check what the protocol named in the contract says.
A small project cannot pay for a careful method; a large or uncertain one deserves it. When the cost is too high, the honest choices are a cheaper option with a stated estimate, a shorter period of verification, or meters that also serve the operation of the plant.
Application 1: The complete plan for the pump drive
Step 1: The baseline model from the log
Click to reveal the baseline model
-
What the log contains. 14 days at 1 minute give 20,160 rows. The pump ran in 6,842 of them: 114.0 hours, or 8.15 hours a day. Over 365 days that is 2,973 hours, within 1 percent of the 3,000 expected. ✅
-
Fit power against flow over the running minutes.
is the flow in m³/h. The RMSE is 0.030 kW. The plan fixes these rounded coefficients. ✅ -
Range. The flow in the running minutes went from 8.0 to 16.0 m³/h. The model is valid inside that range and nowhere else. ✅
-
At the usual flow.
This is the throttled power of the proposal. A plan could use this one mean value, with the flow range stated, in place of a model. The model is better here because the flow is logged in any case, and a year with more water pumped then gets a higher baseline. ✅
-
Check it before anyone signs: a dry run. Test the calculation of item 9 on the baseline log itself, where the true saving is zero. Fit the model to the first 7 days and apply the formula to the 56.7 running hours of the second 7 days: the baseline gives 133.30 kWh and the meter 133.31 kWh, a “saving” of
kWh. A result near zero shows that the formula, the units (kW times one sixtieth of an hour) and the rule for running minutes work. A clear non-zero result means an error in the method, found before it costs money. ✅
Step 2: The expected saving and its precision
Click to reveal the expected precision
-
Expected saving.
The course states this as 2,650 kWh and 31,800 currency units a year. Inside the boundary it is 37.7 percent of the baseline. ✅
-
Power readings. At 2 percent of reading,
kW before and kW after, which combine by root sum of squares to 0.055 kW (0.0553 before rounding). ✅
-
Flow reading. A drift of 2 percent at 12 m³/h is 0.24 m³/h. Through the slope of the model it moves the baseline by
kW. ✅
-
Running hours. 1 percent of 3,000 hours is 30 hours. An hour that is missed is missed from both terms, so it acts on the difference.
✅
-
Combine.
The relative precision is
percent. In money, currency units. ✅ -
The expected result as the plan will state it. 2,650 kWh a year, with a range of 2,303 to 2,997 kWh. In money, 31,800 currency units a year, with a range of 27,636 to 35,964. The saving is 15 times its standard uncertainty, far above the commonly used criterion of 2. ✅
Step 3: The cost of measurement
Click to reveal the budget
-
First year.
currency units, which is 24.5 percent of one year’s saving. ✅ -
Over the 3 years of verification.
This is a little above the commonly quoted guide of about 10 percent. After the first year the cost is 1,800 a year, 5.7 percent. ✅
-
Effect on the project. The present value of the measurement costs at 12 percent is
. The net present value falls from 73,377 to 63,054. The project still earns far more than its cost, and now its result can be proved. ✅
Step 4: The plan as a table
Click to reveal the filled plan
-
The plan. Fields with dots are filled in on site.
Item Agreed for project A 1. Measure and intent A variable speed drive on the booster pump, in place of control by the throttling valve. Intent: the same water service (flow as demanded, the same system pressure) with less electricity 2. Boundary Pump, motor and drive. Electricity is measured on the supply upstream of the drive, so the drive’s own losses are inside. No interactive effect is claimed 3. Option Retrofit isolation with all parameters measured (Option B of the IPMVP, current edition). The saving is 0.526 percent of the site meter, which cannot show it, and 37.7 percent inside this boundary. The load varies, so nothing is estimated 4. Baseline period and data 14 days before the work, from … to …, at 1 minute intervals: power, flow, discharge pressure. 20,160 rows, 114.0 running hours. File …, a copy held by each party 5. Baseline model kW, RMSE 0.030 kW, valid for from 8.0 to 16.0 m³/h. At 12 m³/h it gives 2.345 kW 6. Independent variable and static factors Independent variable: flow in m³/h. Running hours are taken as logged. Static factors: system pressure set point … bar, read on …; pump, impeller, motor and pipework unchanged; no new user on the line; throttling valve fully open after commissioning, position recorded (a valve left half closed keeps part of the old loss) 7. Reporting period 12 months from the day the drive is commissioned, repeated for 3 years. The result is avoided energy: the baseline adjusted to the flow and hours of the reporting period 8. Meters Energy meter on the pump’s supply: 2 percent of reading, accuracy class …, serial …, calibrated on …, next due … Flow meter on the discharge: 2 percent of reading, serial …, calibrated on … The same meters at the same points in both periods. Mains work by a licensed electrician 9. Calculation kWh over the running minutes (measured power above 0.1 kW). A minute with no data is left out of both terms and counted in the report. Flow outside 8.0 to 16.0 m³/h is reported 10. Energy price 12.00 currency units per kWh for every report of the 3 years. Energy only. No saving in demand charges is claimed 11. Expected precision 2,650 kWh a year, expanded uncertainty 347 kWh (13.1 percent): 2,303 to 2,997 kWh. 31,800 currency units a year, plus or minus 4,164 12. Responsibilities Contractor: meters, calibration records, data, calculation, report. Owner: gives access, and reports any change to a static factor within 14 days. Each party may ask for the raw record at any time 13. Report One page each year, within 30 days of the end of the period: monthly hours, mean flow, baseline kWh, measured kWh, avoided kWh; the yearly saving with its range; adjustments; events; hours of missing data. The data file is attached 14. Budget for measurement 6,000 once and 1,800 a year: 11,400 over 3 years, 11.9 percent of the expected 95,400. Above the guide of about 10 percent, accepted because the meters remain in use for operation Every row can be checked by a person who was not at the meeting. ✅
-
Check a second way. The power readings give 91 percent of the variance. With them alone,
percent, close to the 13.1 percent of the full calculation. The script prints the same model, 173 and 347 kWh, 11.9 percent and 63,054. ✅
Application 2: Review a weak plan
Step 1: The review, item by item
Click to reveal the review
-
Compare with the list.
Item In the weak plan What it lets a party argue 1. Measure and intent The drive is named. The service is not Contractor: a lower pressure is part of the saving. Owner: the saving came from poor service 2. Boundary The whole site, by implication Either: any change anywhere on the site is, or is not, the drive 3. Option Not named Each chooses the method that suits the result 4. Baseline period and data Three bills Owner: those months were unusual. Nobody can test it 5. Baseline model None Contractor: the weather hid the saving. Owner: the weather made it 6. Variables and static factors None A new machine or a closed store changes the saving, with no rule to correct it 7. Reporting period ”The first year”, with no start date Each picks the twelve bills that suit it 8. Meters and calibration ”A power reading”: which meter, where, and none before the work The one reading has nothing to be compared with 9. Calculation ”Compare” Subtract the totals, the means, or the same months of each year: three answers 10. Energy price ”The electricity price” The energy rate, the average cost with demand charges, or next year’s tariff 11. Expected precision None Nobody knows whether a difference is a result or noise 12. Responsibilities The contractor reports Nobody must report a change on the site 13. Report format ”A savings report” A single number with no data is a report 14. Budget None The method costs nothing and proves nothing The weak plan fixes none of the fourteen items completely. ✅
Step 2: Three arguments with numbers
Click to reveal the numbers
-
The bills cannot show the saving. The saving is
kWh a month, which is 0.526 percent of a bill of 42,000 kWh. In the best case, a daily baseline model of the site has an expanded uncertainty of 717 kWh for one month. The weak plan has no model at all, so the owner can say “the bills show no saving” and the contractor can say “the bills cannot show it”, and both are right. ✅ -
The hours are open. The single power reading must be multiplied by hours that nobody fixed.
That is 25,430 against 38,146 currency units a year, from the same reading. ✅
-
The price is open. At 12.00 per kWh the saving is 31,800 currency units a year. At a tariff 10 percent higher, 13.20, it is 34,980. The energy is the same and the payment differs by 3,180. ✅
-
Check with the script. The script prints 221 kWh and 0.526 percent, 717 kWh, 2,119 and 3,179 kWh, and 31,800 and 34,980 currency units. ✅
Verify It in Python
The script generates the 14 day baseline log with a fixed seed, fits the baseline model, and calculates every number of the plan and of the review. It saves one plot: the logged power against flow with the baseline model, and the point expected with the drive.
"""Measurement and verification plan for a drive on a booster pump: every number in the plan."""import numpy as npimport matplotlib.pyplot as plt
PRICE = 12.00 # currency units per kWh, fixed by the planP_DRIVE = 1.462 # kW expected with the drive at 12 m3/hHOURS = 3000.0 # expected running hours a yearQ_REF = 12.0 # m3/h, the usual flow
# ---------- Baseline log: 14 days at 1 minute, pump throttled ----------rng = np.random.default_rng(41)days, per_day = 14, 1440minute = np.arange(days * per_day)day = minute // per_dayclock = (minute % per_day) / 60.0 # hour of the dayrun_hours = np.where(day % 7 < 5, 9.0, 6.25) + rng.normal(0, 0.3, days)[day]running = (clock >= 6.0) & (clock < 6.0 + run_hours)flow = 12.0 + 1.6 * np.sin(2 * np.pi * (clock - 6.0) / 9.0) + rng.normal(0, 0.9, minute.size)flow = np.clip(flow, 8.0, 16.0) # m3/hpower = 1.625 + 0.060 * flow + rng.normal(0, 0.030, minute.size) # kW, throttled
q, p = flow[running], power[running]A = np.column_stack([np.ones(q.size), q])(a, b), *_ = np.linalg.lstsq(A, p, rcond=None)rmse = np.sqrt(np.sum((p - A @ [a, b]) ** 2) / (q.size - 2))a, b = round(a, 3), round(b, 4) # the plan fixes the rounded coefficientsp_base = a + b * Q_REFlogged_hours = running.sum() / 60.0print("Baseline log, pump throttled")print(f" rows {minute.size}, running minutes {running.sum()}, running hours {logged_hours:.1f}")print(f" hours a day {logged_hours / days:.2f}, in a year {365 * logged_hours / days:.0f}")print(f" flow while running: {q.min():.1f} to {q.max():.1f} m3/h, mean {q.mean():.2f}")print(f" baseline model: P = {a:.3f} + {b:.4f} x Q kW, RMSE {rmse:.3f} kW")print(f" at {Q_REF:.0f} m3/h: {p_base:.3f} kW; mean logged power {p.mean():.3f} kW")
# ---------- Expected saving ----------dP = p_base - P_DRIVEkwh = dP * HOURSprint("Expected saving")print(f" {p_base:.3f} - {P_DRIVE:.3f} = {dP:.3f} kW = {100 * dP / p_base:.1f} % of the baseline power")print(f" {kwh:.0f} kWh a year, stated as 2650; money {2650 * PRICE:.0f} currency units a year")
# ---------- Expected precision ----------U_METER, U_FLOW, U_HOURS = 0.02, 0.02, 0.01 # standard uncertainties, fractionsu_before = U_METER * p_baseu_after = U_METER * P_DRIVEu_power = np.hypot(u_before, u_after) # kW, the two power readingsu_flow_kw = b * U_FLOW * Q_REF # kW, flow error through the model slopeterms = { "power readings": u_power * HOURS, "flow reading": u_flow_kw * HOURS, "running hours": dP * U_HOURS * HOURS,}u_kwh = np.sqrt(sum(v ** 2 for v in terms.values()))print("Expected precision of the yearly saving")print(f" power: {u_before:.3f} and {u_after:.3f} kW combine to {u_power:.3f} kW")print(f" flow: {b:.3f} x {U_FLOW * Q_REF:.2f} m3/h = {u_flow_kw:.4f} kW")for name, v in terms.items(): print(f" {name:<15}{v:>6.1f} kWh ({100 * v ** 2 / u_kwh ** 2:.0f} % of the variance)")U = round(2 * u_kwh)print(f" combined u = {u_kwh:.0f} kWh, expanded U = {U} kWh = {U * PRICE:.0f} currency units")print(f" relative precision {100 * U / 2650:.1f} %, range {2650 - U} to {2650 + U} kWh, " f"{(2650 - U) * PRICE:.0f} to {(2650 + U) * PRICE:.0f} currency units")print(f" saving over its standard uncertainty: {2650 / u_kwh:.1f}")print(f" model fit: RMSE / sqrt(n) = {rmse / np.sqrt(q.size):.5f} kW (negligible)")
# ---------- Cost of measurement ----------ONCE = 4500.0 + 1500.0 # energy meter fitted + pulse logger on the water meterYEARLY = 1800.0 # data handling and one yearly reportYEARS = 3 # agreed length of verificationsaving = 2650 * PRICEtotal = ONCE + YEARS * YEARLYpa = lambda i, n: ((1 + i) ** n - 1) / (i * (1 + i) ** n)print("Cost of measurement")print(f" first year {ONCE + YEARLY:.0f} = {100 * (ONCE + YEARLY) / saving:.1f} % of one year's saving")print(f" {YEARS} years {total:.0f} = {100 * total / (YEARS * saving):.1f} % of {YEARS * saving:.0f}")print(f" later years {YEARLY:.0f} = {100 * YEARLY / saving:.1f} % of one year's saving")pv = ONCE + YEARLY * pa(0.12, YEARS)print(f" present value at 12 %: {pv:.0f}; project NPV 73377 becomes {73377 - pv:.0f}")
# ---------- What the weak plan leaves open (Application 2) ----------SITE_MONTH, CV = 42000.0, 0.0474site_day = 12 * SITE_MONTH / 365print("The weak plan: bills before and after")print(f" saving in a month {2650 / 12:.0f} kWh = {100 * 2650 / (12 * SITE_MONTH):.3f} % of the bill")print(f" best-case expanded uncertainty of a month of site energy: " f"{2 * CV * site_day * np.sqrt(30):.0f} kWh")for h in (2400.0, 3600.0): print(f" hours {h:.0f}: saving {dP * h:.0f} kWh = {dP * h * PRICE:.0f} currency units")for q_ in (10.0, 14.0): print(f" baseline at {q_:.0f} m3/h: {a + b * q_:.3f} kW")for price in (12.00, 13.20): print(f" price {price:.2f}: {2650 * price:.0f} currency units a year")
# ---------- Plot ----------fig, ax = plt.subplots(figsize=(8, 5))ax.plot(q[::5], p[::5], ".", markersize=2, label="logged minutes (every fifth)")qq = np.linspace(8.0, 16.0, 20)ax.plot(qq, a + b * qq, "k-", label="baseline model")ax.plot([Q_REF], [P_DRIVE], "s", label="expected with the drive")ax.set_xlabel("flow (m3/h)")ax.set_ylabel("electrical power (kW)")ax.set_title("Booster pump: baseline power against flow")ax.legend()fig.tight_layout()fig.savefig("mv_plan_project_a.png", dpi=120)print("Saved mv_plan_project_a.png")Expected output
Baseline log, pump throttled rows 20160, running minutes 6842, running hours 114.0 hours a day 8.15, in a year 2973 flow while running: 8.0 to 16.0 m3/h, mean 12.09 baseline model: P = 1.625 + 0.0600 x Q kW, RMSE 0.030 kW at 12 m3/h: 2.345 kW; mean logged power 2.350 kWExpected saving 2.345 - 1.462 = 0.883 kW = 37.7 % of the baseline power 2649 kWh a year, stated as 2650; money 31800 currency units a yearExpected precision of the yearly saving power: 0.047 and 0.029 kW combine to 0.055 kW flow: 0.060 x 0.24 m3/h = 0.0144 kW power readings 165.8 kWh (91 % of the variance) flow reading 43.2 kWh (6 % of the variance) running hours 26.5 kWh (2 % of the variance) combined u = 173 kWh, expanded U = 347 kWh = 4164 currency units relative precision 13.1 %, range 2303 to 2997 kWh, 27636 to 35964 currency units saving over its standard uncertainty: 15.3 model fit: RMSE / sqrt(n) = 0.00036 kW (negligible)Cost of measurement first year 7800 = 24.5 % of one year's saving 3 years 11400 = 11.9 % of 95400 later years 1800 = 5.7 % of one year's saving present value at 12 %: 10323; project NPV 73377 becomes 63054The weak plan: bills before and after saving in a month 221 kWh = 0.526 % of the bill best-case expanded uncertainty of a month of site energy: 717 kWh hours 2400: saving 2119 kWh = 25430 currency units hours 3600: saving 3179 kWh = 38146 currency units baseline at 10 m3/h: 2.225 kW baseline at 14 m3/h: 2.465 kW price 12.00: 31800 currency units a year price 13.20: 34980 currency units a yearSaved mv_plan_project_a.pngIn the plot the logged minutes lie in a narrow band round the baseline model, and the point expected with the drive is far below it.
Common Mistakes
- Writing the plan after the equipment is installed. The baseline can no longer be measured, and every choice is then made by someone who already knows the result.
- Describing the calculation in a sentence. Write the formula, with the rule for missing data, so that two people reach the same number.
- Listing static factors without their baseline values. “Pressure set point” proves nothing. The value and the date it was read do.
- Stating the meter’s accuracy and not the precision of the saving. Carry the meter’s uncertainty through the formula to the yearly kWh.
- Leaving the price open. Fix the price per kWh and say whether demand charges are claimed.
Summary
- A measurement and verification plan fixes the method before the data exist: the measure, boundary, option, baseline, model, variables and static factors, reporting period, meters, calculation, price, precision, responsibilities, report and budget.
- The expected saving of project A is 2,650 kWh a year with an expanded uncertainty of 347 kWh (13.1 percent), which is 31,800 plus or minus 4,164 currency units.
- Measurement costs 11,400 over 3 years, 11.9 percent of the expected saving, a little above the commonly quoted guide of about 10 percent.
- A plan that says “compare the bills” fixes none of the fourteen items completely, and leaves hours, price and method open to argument.
- Where a contract names a protocol, its current edition decides what the plan must contain.
Exercises
1. Measurement for a project costs 12,000 currency units once and 3,000 a year. The expected saving is 90,000 a year and verification runs for 3 years. Find the cost of measurement as a share of the saving over the 3 years, and in the first year alone.
Answer
Over 3 years:
2. A project reduces the power of a fan by 5.0 kW, with a standard uncertainty of 0.20 kW. The fan runs 4,000 hours a year, known to a standard uncertainty of 2 percent. Find the yearly saving, its expanded uncertainty and the relative precision.
Answer
3. Use the plan of project A. In one month the pump runs 240 hours at a mean flow of 13.0 m³/h and the energy meter records 372 kWh. Find the avoided energy and its value. What must the report say if the mean flow of a month is 17.5 m³/h?
Answer
Baseline:
4. Write five plan items for the lighting change of this course: 120 fittings of 72 W replaced by 120 of 36 W, 4,200 agreed hours a year, in a cooled building. Give the boundary, the option, what is measured, what is estimated, and the treatment of the cooling effect.
Answer
Boundary: the lighting circuits. Option: retrofit isolation with the key parameter measured (Option A). Measured: the power of the circuits before and after, a fall of 4.32 kW. Estimated and agreed: 4,200 hours a year, with the source of that figure, giving 18,144 kWh a year. Interactive effect: the cooling plant is outside the boundary, and its saving of about 5,583 kWh a year is an estimate from two stated assumptions, reported on a separate line or left out with a statement.
References
- Efficiency Valuation Organization, International Performance Measurement and Verification Protocol (IPMVP): Core Concepts, current edition.
- ASHRAE, Guideline 14-2014: Measurement of Energy, Demand, and Water Savings, ASHRAE, 2014.
- ISO 50015:2014, Energy management systems: Measurement and verification of energy performance of organizations: General principles and guidance.
- B. L. Capehart, W. C. Turner and W. J. Kennedy, Guide to Energy Management, 8th edition, Fairmont Press, 2016.
A pump draws 2.345 kW before a drive is fitted and 1.462 kW after. Both readings come from an energy meter with a standard uncertainty of 2 percent of reading. About how uncertain is the 0.883 kW saving, as a share of itself?
Project A: 2.345 kW throttled at 12 m³/h, 3,000 running hours a year, baseline slope 0.0600 kW per m³/h. The two power readings are treated as independent, as in the lesson. The three sources combine by root sum of squares, so the combined bar is shorter than the three laid end to end. Raise the power with the drive and watch the saving shrink while its uncertainty does not.
Check yourself
Three questions. Each wrong choice is a mistake people really make, so read the note after you answer.
1. Measurement for a project costs 8,000 currency units once and 2,000 a year. The expected saving is 40,000 a year, and verification runs for 2 years. What share of the saving does the measurement cost over the period of verification?
2. A project lowers the power of a fan by 3.0 kW, with a standard uncertainty of 0.30 kW. The fan runs 2,000 hours a year, known to 1 percent. What relative precision does the plan state for the yearly saving?
3. A year after a project, the contractor reports the twelve months from March to February, which happened to be the best twelve months of the record. Which item of the plan, written in full, would have prevented this choice?
- The flow meter feeds the baseline model: at 12 m³/h the throttled pump would draw 2.345 kW.
- The energy meter reads 1.462 kW with the drive. The difference is the saving: 0.883 kW.
- Over the 3,000 hours it ran: 2,649 kWh, stated as 2,650, worth 31,800 a year at 12.00.
- The meters' errors give U = 347 kWh, 13.1 %: the plan expects 2,303 to 2,997 kWh.
Discussion
No comments yet. Questions, results from your own build, a better way to explain it: all welcome.
My notes on this page
Kept on this device only. Nothing is sent anywhere.
Tip: select words in the lesson, or tap a figure or an equation, to put a note right there.
Notes on earlier wording
The lesson has changed and these words are no longer in it. Your notes are kept, with the words you chose.