Skip to content
You Start with one site
Amounts in Start with one site
Control, Measurement & Energy · Course

Simple Payback and Its Limits

Lesson 1 of 10 21 min read
Found this useful?

A site spends its small energy budget on a project with a three-year payback, and the equipment is worn out in the fourth year. A second project with the same payback would have earned for fifteen years, and it was refused because the two looked equal on paper. A third was approved on a supplier’s promise of a saving that nobody checked afterwards. Each payback was calculated correctly, and each decision was still poor. This lesson shows how to calculate simple payback, what it does not see, and what must be true before you trust the saving inside it. #EnergyEconomics #SimplePayback #EnergySaving

Learning Objectives

By the end of this lesson, you will be able to:

  1. Calculate the yearly saving and the simple payback of an energy project
  2. Explain why a saving is a comparison with what would have happened, and why that makes it an estimate
  3. Show what simple payback ignores: life after payback, timing, rising prices and maintenance
  4. Compare two projects with the same payback by their total net benefit
  5. Decide when simple payback is enough and when a fuller analysis is needed

Real-World System Problem: Three proposals and one budget



A site manager has three proposals: a variable speed drive for the booster pump, from a drive supplier; a capacitor bank to correct the power factor (the ratio of useful power in kW to the power the supply must carry in kVA), from an electrical contractor; and 120 new fittings for the store building, from a lighting company. Each ends with the same line: “payback under three years”.

The manager must decide which to do first, and whether to do all three. The budget is limited, the people who wrote the proposals also sell the equipment, and next year someone will ask whether the money came back. One number, payback, must carry all of this.

Payback is a good first question and a poor last one. It says how soon the cost returns if the saving is real, and nothing about what comes after or whether the saving is real.

Site manager:which one first?D: 120 newlight fittingscost 174,000B: capacitorbankcost 450,000A: drive onbooster pumpcost 95,000
Three proposals for one budget

All money in this course is in currency units, so the method works in any country. (Project C, a cold room, joins these three in the energy audit later in the course.) The energy price of 12.00 currency units per kWh and every rate are examples: use the figures from your own bills.

Fundamental Theory: What payback measures and what it leaves out



A saving is a comparison

After the drive is fitted, a meter shows how much energy the pump uses now. No meter can show what the pump would have used this year without the drive, because that year did not happen. The saving is the difference:

The second term is measured. The first is always an estimate, built from measurements before the change and adjusted to the conditions after it, however good the meters are.

Energyusebefore the changeafter the changewould havemeasuredbeen usedsaving(estimated)was used(measured)time
Only one of the two lines can be measured

A proposal adds a third number: the saving the supplier expects, a forecast made before either line exists. A payback built on it is only as good as the promise. Read every payback in a proposal as “payback, if the saving is as stated”, and ask how the saving will be checked afterwards.

Simple payback

Let be the capital cost of the project, paid at the start (year 0), in currency units. Let be the saving in one year, in currency units per year.

Simple payback

It is the time the savings need to return the cost, when the saving is the same every year and a currency unit in a later year counts the same as one today.

The yearly saving in money comes from the energy saved and the price:

where is the energy saved in kWh per year and is the energy price in currency units per kWh. For a constant load, is the reduction in power (kW) multiplied by the operating hours in a year.

What a cumulative cash flow shows

Add the cash flows year by year, starting with the cost as a negative number. The running total is the cumulative cash flow. Payback is the moment the total crosses zero.

cash+S●0●year●payback●●-C0●01234
Cumulative cash flow of a project that pays back in 3 years

Everything to the right of the crossing is the benefit of the project. Simple payback does not look there. That is its main fault.

What simple payback ignores

Life after payback. With a 3-year payback, a project that lasts 4 years earns for one more year, and one that lasts 15 years earns for twelve more. Payback gives them the same score.

Timing inside the payback period. One project returns most of its cost in year 1, another almost nothing until year 3. If both reach zero at 3 years, payback scores them equal, although the first is safer.

The time value of money. A currency unit received in five years is worth less than one today, which can earn interest or repay a loan meanwhile. Simple payback counts them as equal.

Rising prices. If the energy price rises, the same kWh saved is worth more each year, and the true payback is shorter than the simple one.

Costs that continue. A drive needs cooling fans and filters. A capacitor bank needs new capacitors after some years. If a project adds a yearly cost , the saving that returns the capital is :

Risk. Payback has no place for the chance that the saving is smaller than promised.

When simple payback is still the right tool

Simple payback is not wrong. It is a screen, like a sieve: a quick test that sorts proposals before anyone spends time on a careful study. It serves well when all of these are true:

  • the cost is small for the site,
  • the payback is short compared with the life of the equipment,
  • the saving is steady from year to year and is easy to believe,
  • little can go wrong.

Repairing compressed air leaks, fitting a time switch, or cleaning a condenser are examples. A study of such a measure can cost more than the measure.

A rule of thumb at many sites: with a simple payback under about 2 years, do it without further study; between about 2 and 5 years, make a fuller analysis; over about 5 years, it needs a strong reason other than energy. This is a habit of practice, not a standard. Each organisation sets its own limits, and they move with the cost of borrowing.

Application 1: Payback of the drive, the capacitor bank and the lighting



Step 1: The yearly saving of each project

Click to reveal the yearly savings
  1. Project A, power and energy. The reduction in power is .

    This course rounds it to 2,650 kWh a year. ✅

  2. Project A, money.

    The drive is expected to save 31,800 a year at today’s price. ✅

  3. Project B. The saving is read from the bill, month by month.

    This saving comes from the demand charge (a charge on the highest kVA the site draws in the month) and a surcharge for low power factor. Almost no kWh are saved. It is a cost saving that is not an energy saving. ✅

  4. Project D, energy. Each fitting saves .

    The lighting change saves 18,144 kWh a year. ✅

  5. Project D, money and cost.

    The lighting saves 217,728 a year for a cost of 174,000. ✅

Step 2: Simple payback

Click to reveal the three paybacks
  1. Project A.

    About 36 months. ✅

  2. Project B.

    The bank returns its cost in the third monthly bill. ✅

  3. Project D.

    The lighting returns its cost in under 10 months. ✅

  4. Rank them. By payback the order is B, then D, then A. ✅

ProjectCostSaving a yearSimple payback
A, drive on pump95,00031,8002.99 years
B, capacitor bank450,0002,074,5600.217 years (2.6 months)
D, lighting174,000217,7280.799 years (9.6 months)

Step 3: Project A with maintenance and a rising price

When the saving changes from year to year, the formula no longer applies. Add the net saving year by year until the total reaches zero, then interpolate inside that year. With a price rise of per year, the saving in year is .

Click to reveal the effect on project A
  1. Maintenance only. The net saving is a year.

    The maintenance moves the payback from 2.99 to 3.19 years, past the “under three years” in the proposal. ✅

  2. Price rise of 5 percent a year, no maintenance. The savings are 31,800, then 33,390, then 35,060. After 2 years the total is .

    The rising price shortens the payback from 2.99 to 2.85 years. ✅

  3. Both together. The net savings are 29,800, then 31,390, then 33,060, then 34,812. After 3 years the total is .

    The two effects nearly cancel inside the payback period. ✅

  4. Look past the payback. Over the 10-year life, the net benefit (all net savings minus the cost, with no discounting) is 203,000 at a constant price with maintenance, and 284,977 with the price rise and maintenance. The payback moved by 0.17 years and the benefit over the life by 81,977. Payback hardly notices a price rise, because most of its effect comes late. ✅

  5. Check with the script. The Python script below computes the same four cases year by year and prints 2.99, 3.19, 2.85 and 3.02 years. ✅

Step 4: What each figure rests on

Click to reveal the test of each saving
  1. Project A rests on two power readings and on 3,000 hours a year at the same flow. Fewer hours or a different flow change the saving, so measure power and flow before and after. ✅

  2. Project B rests on the tariff. The saving exists because the utility charges for kVA and adds a surcharge for low power factor. If the tariff changes, the saving changes, although the bank works exactly as before. On a site with variable speed drives, such as project A, a plain bank can resonate with the drives’ harmonic currents and fail early; ask whether the bank is detuned (fitted with reactors) for this. ✅

  3. Project D rests on a power difference that is easy to measure and on 4,200 hours that must be agreed or logged. ✅

  4. A limiting case as a check. Suppose the lighting runs only half of the stated hours. The saving halves to 108,864 and the payback doubles to years. Payback is inversely proportional to the hours, so an error in hours passes into the payback at full size. ✅

  5. Check it on the bills and meters after the change. For B, put three bills before and three after side by side, for similar months. The kWh line should hardly move. The maximum demand in kVA should fall, the power factor should rise to the value the contractor promised (often 0.95 or more), and the surcharge should disappear. If the kWh line also fell a lot, something else changed at the site (fewer working days, a line stopped), and that part of the fall is not the bank’s. For D, a logger on the lighting circuit should show less while the lights are on, and it records the real hours. The proposal’s 4,200 hours are about 81 hours a week; a week of logging that shows 50 hours moves the payback in the same proportion. ✅

Application 2: Two projects with the same payback



year03 415P######==costnet benefit: 1 year of savingreturnedQ######costnet benefit: 12 years of savingreturned#saving that returns the cost=net benefit
Same cost, same saving, different lives

Step 1: Payback and net benefit

Click to reveal the comparison
  1. Payback of each.

    Both projects have a simple payback of 3.0 years. ✅

  2. Net benefit of P. Let be the life in years. The total net benefit, without discounting, is .

    Project P returns its cost and 20,000 more. ✅

  3. Net benefit of Q.

    Project Q returns its cost and 240,000 more, twelve times the net benefit of P. ✅

  4. Why payback ranks them equal. The formula contains the cost and the yearly saving, but not . Any two projects with the same cost and yearly saving get the same payback, whatever their lives. ✅

Step 2: Check a second way

Click to reveal the check
  1. Count the years after payback. P earns for year after payback: . Q earns for years: . Both agree with Step 1. ✅

  2. Money returned for each unit spent. P returns times its cost. Q returns times its cost. ✅

  3. A limiting case. A project with a life equal to its payback has a net benefit of zero. It returns the money and nothing else. Payback alone would still pass it. ✅

Verify It in Python



The script computes the yearly saving and simple payback of projects A, B and D, project A’s payback year by year in four cases, and projects P and Q. The plot shows the cumulative cash flow of P and Q.

simple_payback_screen.py
"""Simple payback of three projects, and what payback does not see."""
import numpy as np
import matplotlib.pyplot as plt
PRICE = 12.00 # currency units per kWh (example)
def payback(cost, saving):
"""Simple payback in years."""
return cost / saving
def payback_by_year(cost, first_saving, rise=0.0, upkeep=0.0, life=10):
"""Payback when the saving changes each year.
Adds the net saving year by year and interpolates inside the
year in which the running total reaches zero.
"""
total = -cost
for year in range(1, life + 1):
net = first_saving * (1.0 + rise) ** (year - 1) - upkeep
if total + net >= 0.0:
return year - 1 + (-total) / net
total += net
return float("nan")
# ---------- Part 1: the three proposals ----------
save_a = 2650 * PRICE # drive: 0.883 kW x 3,000 h = 2,650 kWh
save_b = 172_880 * 12 # power factor bank
kwh_d = 120 * (72 - 36) * 4200 / 1000.0 # lighting
save_d = kwh_d * PRICE
projects = (("A drive", 95_000, save_a),
("B bank", 450_000, save_b),
("D lights", 120 * 1450, save_d))
print("Simple payback")
for name, cost, saving in projects:
pb = payback(cost, saving)
print(f" {name:9s} cost {cost:>9,.0f} saving {saving:>11,.0f} a year "
f"payback {pb:.3f} y = {12 * pb:.1f} months")
print(f" lighting energy saved: {kwh_d:,.0f} kWh a year")
# ---------- Part 2: project A, year by year ----------
print("Project A payback, year by year")
cases = (("price constant, no upkeep", 0.00, 0.0),
("price constant, upkeep 2,000", 0.00, 2000.0),
("price +5 % a year, no upkeep", 0.05, 0.0),
("price +5 % a year, upkeep 2,000", 0.05, 2000.0))
for label, rise, upkeep in cases:
pb = payback_by_year(95_000, 31_800, rise, upkeep)
years = np.arange(1, 11)
net10 = np.sum(31_800 * (1 + rise) ** (years - 1) - upkeep) - 95_000
print(f" {label:32s} payback {pb:.2f} y, "
f"net benefit in 10 y {net10:>9,.0f}")
# ---------- Part 3: same payback, different lives ----------
COST, SAVING = 60_000, 20_000
print("Two projects, cost 60,000 and saving 20,000 a year")
for name, life in (("P", 4), ("Q", 15)):
net = SAVING * life - COST
print(f" {name}: payback {payback(COST, SAVING):.1f} y, life {life:2d} y, "
f"net benefit {net:>8,.0f}, returned {SAVING * life / COST:.2f} "
f"times the cost")
# ---------- Plot ----------
fig, ax = plt.subplots(figsize=(8, 4.5))
for name, life, style in (("P, life 4 years", 4, "o-"),
("Q, life 15 years", 15, "s--")):
t = np.arange(0, life + 1)
ax.plot(t, -COST + SAVING * t, style, label=name)
ax.axhline(0.0, color="gray", linewidth=0.8)
ax.axvline(3.0, color="gray", linewidth=0.8, linestyle=":")
ax.set_xlabel("year")
ax.set_ylabel("cumulative cash flow (currency units)")
ax.set_title("Same payback, different lives")
ax.legend()
fig.tight_layout()
fig.savefig("simple_payback_screen.png", dpi=120)
print("Saved simple_payback_screen.png")

Expected output

Simple payback
A drive cost 95,000 saving 31,800 a year payback 2.987 y = 35.8 months
B bank cost 450,000 saving 2,074,560 a year payback 0.217 y = 2.6 months
D lights cost 174,000 saving 217,728 a year payback 0.799 y = 9.6 months
lighting energy saved: 18,144 kWh a year
Project A payback, year by year
price constant, no upkeep payback 2.99 y, net benefit in 10 y 223,000
price constant, upkeep 2,000 payback 3.19 y, net benefit in 10 y 203,000
price +5 % a year, no upkeep payback 2.85 y, net benefit in 10 y 304,977
price +5 % a year, upkeep 2,000 payback 3.02 y, net benefit in 10 y 284,977
Two projects, cost 60,000 and saving 20,000 a year
P: payback 3.0 y, life 4 y, net benefit 20,000, returned 1.33 times the cost
Q: payback 3.0 y, life 15 y, net benefit 240,000, returned 5.00 times the cost
Saved simple_payback_screen.png

The two lines lie on top of each other up to year 4, and payback reads only that part of the plot.

Common Mistakes



  • Treating the supplier’s stated saving as a result. It is a forecast. Ask what will be measured, before and after, to check it.
  • Comparing projects by payback alone when their lives differ. Write the life beside every payback and compute the net benefit over the life.
  • Leaving out continuing costs. Extra maintenance and replacement parts reduce the saving that returns the capital.
  • Using nameplate power and assumed hours when a measurement is possible. Motors rarely run at nameplate load, and hours are often overstated.
  • Calling every cost saving an energy saving. A power factor bank reduces the bill and saves almost no kWh. Report the two separately.
  • Rejecting a long-lived project because its payback is over a fixed limit, without a fuller analysis.

Summary



  • A saving is the difference between what would have been used and what was used. Only the second can be measured, so every saving contains an estimate.
  • Simple payback is the cost divided by the yearly saving. It tells you how soon the cost returns if the saving is real.
  • It ignores the life after payback, the timing of the savings, the time value of money, rising prices and risk. Continuing costs must be subtracted from the saving by hand.
  • Projects A, B and D pay back in 2.99 years, 2.6 months and 9.6 months. Maintenance of 2,000 a year moves A to 3.19 years.
  • Two projects with a 3-year payback and lives of 4 and 15 years have net benefits of 20,000 and 240,000.
  • Use payback as a first screen for small, quick, low-risk measures, and state the life and the source of the saving with it.

Exercises



1. Repairing compressed air leaks costs 18,000 currency units and saves 2,400 kWh a year. The energy price is 12.00 per kWh. Find the yearly saving and the simple payback in months.

Answer

a year. Payback years, which is 7.5 months.

2. A new motor costs 240,000 and saves 60,000 a year. It needs 6,000 a year of extra maintenance. Find the simple payback with and without the maintenance.

Answer

Without: years. With: years.

3. A store replaces 60 fittings of 58 W by fittings of 24 W, at 1,200 per fitting installed. The proposal assumes 3,000 hours a year at 12.00 per kWh. Find the payback. A logger later shows the lights run 1,800 hours a year. Find the payback again.

Answer

Energy saved: kWh, worth 73,440 a year. Cost , so the payback is 0.980 years. At 1,800 hours the saving is 44,064 a year and the payback is 1.63 years.

4. Project X costs 80,000, saves 32,000 a year and lasts 5 years. Project Y costs 200,000, saves 50,000 a year and lasts 20 years. Find the simple payback and the undiscounted net benefit of each. Which does payback prefer?

Answer

X: payback 2.50 years, net benefit . Y: payback 4.00 years, net benefit . Payback prefers X, although Y returns ten times as much over its life.

5. A project costs 150,000 and saves 40,000 in its first year. The energy price rises 8 percent a year. Find the payback year by year, with interpolation inside the last year, and compare it with the simple payback at a constant price.

Answer

Savings: 40,000, then 43,200, then 46,656, total 129,856 after 3 years. The remaining 20,144 is returned in year 4, when the saving is 50,388: years. At a constant price the payback is years.

6. A supplier promises to cut a site’s energy cost of 500,000 a year by 20 percent, for 250,000. The equipment lasts 6 years. Find the payback and the undiscounted net benefit. Then repeat for a real saving of 12 percent.

Answer

Promised: saving 100,000 a year, payback 2.50 years, net benefit . At 12 percent: saving 60,000 a year, payback 4.17 years, net benefit . The saving fell by 40 percent and the net benefit fell by 69 percent.

References



  • B. L. Capehart, W. C. Turner and W. J. Kennedy, Guide to Energy Management, 8th edition, Fairmont Press, 2016.
  • A. Thumann and D. P. Mehta, Handbook of Energy Engineering, 7th edition, Fairmont Press, 2013.
  • D. G. Newnan, T. G. Eschenbach and J. P. Lavelle, Engineering Economic Analysis, 13th edition, Oxford University Press, 2017.


© 2021-2026 SiliconWit®. All rights reserved.
A: drive on booster pump cost 95,000 B: capacitor bank cost 450,000 D: 120 new light fittings cost 174,000 Site manager: which one first?
Three proposals for one budget
energy use time before the change after the change measured would have been used estimated was used measured saving
Only one of the two lines can be measured
0 3 4 15 year P net benefit: 1 year of saving, 20,000 Q net benefit: 12 years of saving, 240,000 cost returned saving that returns the cost net benefit
Same cost, same saving, different lives
Predict first

Two projects each cost 60,000 currency units and save 20,000 a year. One lasts 4 years. The other lasts 15 years. How does the simple payback of the 15-year project compare?

the change metered would have been used: estimated was used: metered saving
See it: one payback, two very different projects

Simple payback, both
Net benefit of P over its life
Net benefit of Q over its life

Both projects cost 60,000 currency units at year 0 and save 20,000 in the first year, as in Application 2. Each line adds the net saving of each year to the cost. Where a line crosses zero is the payback. Everything above zero is the benefit that payback does not look at. The price rise is applied to the saving and the maintenance stays constant. No discounting: a saving in year 15 counts the same as one in year 1.

payback: 3 years payback does not look here P: life 4 years Q: life 15 years

Check yourself

Three questions. Each wrong choice is a mistake people really make, so read the note after you answer.

1. A lighting proposal replaces 40 fittings, each saving 50 W, for 50,000 currency units. It assumes 4,000 hours a year at 12.00 per kWh and states a payback of 6.25 months. A logger later shows the lights run 2,500 hours a year. What is the payback now?

2. A project costs 120,000, saves 40,000 a year, and needs 10,000 a year of extra maintenance for as long as it runs. What is its simple payback?

3. A site has 90,000 to spend and can do only one project. X costs 30,000, saves 15,000 a year and lasts 3 years. Y costs 90,000, saves 22,500 a year and lasts 12 years. Without discounting, which gives the larger net benefit?

Watch it build: payback of the new lighting
012 years cost 174,000 What must the savingsrepay? The price, paid now. 0.80 years4.32 kW × 4,200 h× 12.00 = 217,728 a year 1.34 yearsat 2,500 h:129,600 a year 4,200 h
  1. The 120 new fittings cost 174,000, paid at the start. That is what the savings must repay.
  2. 4.32 kW less for 4,200 h is 18,144 kWh, worth 217,728 a year: payback 0.80 years.
  3. If the lamps really run 2,500 h, the saving is 40 % less and payback stretches to 1.34 years.