Skip to content
You Start with one site
Amounts in Start with one site
Control, Measurement & Energy · Course

The Time Value of Money: NPV and IRR

Lesson 2 of 10 23 min read
Found this useful?

A site borrows at 12 percent a year to fit equipment that “pays back in three years”, and the loan is still not cleared in the fourth year. Nobody made an error in arithmetic: the payback counted a saving in year three as if it arrived today, and the bank did not. The same blind spot makes a project that earns for fifteen years look no better than one that earns for four. This lesson gives money a date. You will discount future savings to today’s value and calculate net present value, internal rate of return and discounted payback for a pump drive and a capacitor bank. #EnergyEconomics #NetPresentValue #InternalRateOfReturn

Learning Objectives

By the end of this lesson, you will be able to:

  1. Explain why a currency unit next year is worth less than a currency unit today
  2. Calculate the present value of a future amount and of a uniform yearly saving
  3. Calculate the net present value and the discounted payback of a project, with and without a rising energy price
  4. Solve for the internal rate of return numerically and say what it means
  5. Test how the result changes with the discount rate, and keep real and nominal rates apart

Real-World System Problem: Is the drive worth borrowing for?



The variable speed drive for the booster pump costs 95,000 currency units, installed. It is expected to save 31,800 a year at today’s energy price, and it needs 2,000 a year of extra maintenance. The simple payback is about three years. The drive should last 10 years.

The site manager does not have 95,000 idle. The money must be borrowed, or taken from another use that also earns something. Here that cost of money is 12 percent a year, an example: each organisation has its own figure. Ask the finance office for the rate it uses to judge projects (often called the hurdle rate); it is usually above the loan rate, because it also allows for risk. The question is no longer “when does the money come back?” but “after paying 12 percent a year for the money, is anything left, and how much?”

The second proposal, a capacitor bank that removes a demand charge and a surcharge, costs 450,000 and saves 172,880 a month. It will need new capacitors in year 7 for 120,000. The manager wants one method that handles both: a steady saving and a cost that arrives late.

29,800 net saving each year (31,800 - 2,000)year1234567891095,000 cost at year 0
Cash flows of the drive, case (a)

Fundamental Theory: Giving money a date



Why a unit next year is worth less

Put 100 currency units in an account that pays 12 percent a year, and after one year you hold 112. So 100 today equals 112 in one year, and 100 received in one year is worth less than 100 today. The same holds if you borrow: a unit received sooner repays the loan sooner and saves interest.

This is not inflation, which is treated later in this section. Even with stable prices, money that arrives earlier can be put to work earlier.

Compounding and discounting

Let be the discount rate per year, written as a fraction (12 percent is ). An amount today grows to after years:

This is compounding. Discounting is the same relation read backwards. The present value of an amount received in year is

The term is the discount factor for year .

Compoundingyear 0year 1year 2100112.00125.44Discounting: what 100 received later is worth todaytodayreceived in89.29year 156.74year 532.20year 10
100 currency units at 12 percent

At 12 percent, a saving in year 10 counts for less than a third of its face value, so the late years of a long project add less than a simple sum suggests, but they still add something.

The present worth factor of a uniform yearly amount

Many energy projects save about the same amount every year for years. The present value of this series is the sum of terms: , then , and so on to . Each term is the one before multiplied by , so this geometric series has a closed form. The sum for one currency unit a year is the present worth factor, .

Present worth factor of a uniform yearly amount

The present value of a saving received at the end of each year for years is .

Two checks help you trust it. With very small, approaches : no discounting, so years count as . With very large, approaches : at 12 percent, a saving that lasts for ever is worth only 8.33 times one year’s saving.

Net present value

Let be the capital cost at year 0 and the net saving in year (saving minus any extra cost in that year).

Net present value

A positive NPV means the project repays its cost, pays the cost of money at rate , and leaves the NPV as a surplus in today’s currency units.

A positive NPV at your discount rate means the project is worth more than it costs. Between two projects that exclude each other, the larger NPV adds more value. NPV counts the whole life, the timing of every cash flow and any late cost: all that simple payback ignores.

Discounted payback

Discounted payback is the time at which the cumulative discounted cash flow first becomes positive. It is always longer than simple payback, because each saving counts for less. For a part of a year, interpolate in a straight line inside the year of the crossing: an approximation, because discounting is not linear within a year.

Discounted payback still ignores everything after the crossing. Use it as a measure of how long the money is at risk, and use NPV for the decision.

Internal rate of return

The NPV falls as the discount rate rises, because later savings count for less. The rate at which it reaches zero is the internal rate of return, IRR.

NPV+●●●●●IRR:NPV=00●rate i●-●
NPV against discount rate

The IRR is the highest cost of money at which the project still does not lose. If the IRR is above your discount rate, the NPV is positive, and the two tests agree.

For more than two cash flows there is no formula for the IRR. It is found numerically: write the NPV as a function of , choose a low rate where the NPV is positive and a high rate where it is negative, and let a root-finding routine (here brentq from SciPy) narrow the interval until the NPV is zero.

Some cash-flow patterns, with costs that return after savings have begun (a large replacement or a clean-up cost late in life), can have more than one IRR, and then NPV is the test to rely on.

A rising energy price

If the energy price rises by a fraction each year, the saving in year is , where is the saving at today’s price. Costs that do not follow the energy price, such as maintenance, are kept apart and not escalated. For not equal to , the present value of the rising savings has a closed form that is useful as a check:

A price rise is a forecast. Report the result with it and without it, and do not let a project depend on it.

Real and nominal rates

A nominal rate includes inflation: it is the rate a bank quotes. A real rate has inflation removed. They are linked by . A real rate of 12 percent with inflation of 5 percent is a nominal rate of percent, not 17 percent.

Use one kind throughout a calculation:

  • savings in today’s prices, with no general inflation added: discount at a real rate;
  • every cash flow in the money of its own year, inflation included: discount at a nominal rate.

Both give the same NPV when done consistently. Mixing them makes a good project look poor. For the drive below, the net saving of 29,800 in today’s prices at a real 12 percent gives an NPV of 73,377; the same savings inflated by 5 percent a year and discounted at the nominal 17.6 percent give 73,377 again; today’s prices discounted at 17.6 percent give only 40,850.

In this course is a real rate before tax. A rate quoted by a bank is nominal: a loan at 12 percent with inflation at 5 percent is a real rate of percent. So the 12 percent used below stands for a demanding real rate, and the 5 percent energy price rise is 5 percent a year above general inflation: a strong assumption, chosen to show the method.

Application 1: The pump drive over 10 years



Step 1: Case (a), net present value

Click to reveal the NPV at a constant price
  1. Net saving each year. currency units, the same in all 10 years. ✅

  2. Present worth factor. With :

    Ten years of saving count as 5.65 years’ worth today. ✅

  3. Present value of the net savings.

    The savings are worth 168,377 today, against 298,000 as a simple sum. ✅

  4. Net present value.

    After repaying the cost and paying 12 percent a year for the money, the drive leaves a surplus of 73,377 in today’s currency units. ✅

Step 2: Case (a), the year-by-year table and discounted payback

Click to reveal the table and the paybacks
  1. Build the table. Each year’s net saving is multiplied by its discount factor and added to the running total, which starts at . ✅

    YearNet savingDiscount factorPresent valueCumulative
    129,8000.892926,607-68,393
    229,8000.797223,756-44,636
    329,8000.711821,211-23,425
    429,8000.635518,938-4,487
    529,8000.567416,90912,422
    629,8000.506615,09827,520
    729,8000.452313,48041,000
    829,8000.403912,03653,036
    929,8000.360610,74663,782
    1029,8000.32209,59573,377
  2. Check the NPV. The last cumulative value is 73,377, the same as Step 1 by the factor. ✅

  3. Simple payback. years. ✅

  4. Discounted payback. The cumulative value turns positive in year 5. At the end of year 4 it is , and year 5 adds 16,909.

    The discounted payback is in year 5, about 4.27 years by straight-line interpolation. ✅

  5. Check it before anyone signs. Two quick tests catch most errors in an NPV sheet. At a rate of 0 the NPV must equal the simple sum: 10 years of 29,800 less 95,000, which is 203,000. At the IRR it must be 0. Also watch the spreadsheet function NPV(rate, range): it treats the first cell of the range as year 1. Put the year 0 cost inside the range and every flow is discounted one year too many: the result is , not 73,377. Keep the cost outside: NPV(rate, years 1 to 10) minus 95,000. ✅

Step 3: Case (a), internal rate of return

Click to reveal the IRR
  1. State the condition. The IRR is the rate at which , so for 10 years. ✅

  2. Bracket it by hand. At 28 percent, and the NPV is . At 29 percent, and the NPV is . The IRR lies between them, close to 29 percent. ✅

  3. Solve numerically. brentq is given the NPV function and the interval from 0.1 to 2,000 percent, and returns

    The drive would still not lose money if the site paid up to 28.9 percent a year for the capital. ✅

Step 4: Case (b), the energy price rises 5 percent a year

Click to reveal the case with a rising price
  1. Net saving each year. The saving is and the maintenance stays at 2,000. The net savings are 29,800, then 31,390, then 33,060, then 34,812, and they reach 47,332 in year 10. ✅

  2. Net present value. Discount each year at 12 percent and add.

    The rising price adds 36,353 to the NPV. ✅

  3. Check with the closed form. The present value of the rising savings is

    The maintenance is worth . So . The two methods agree. ✅

  4. Internal rate of return. Solved in the same way, percent. ✅

  5. Paybacks. The simple payback is 3.02 years. The cumulative discounted value is after year 3, and year 4 adds 22,124, so the discounted payback is years. ✅

Project A at 12 percentCase (a), constant priceCase (b), price rises 5 percent a year
NPV73,377109,730
IRR28.9 percent33.8 percent
Simple payback3.19 years3.02 years
Discounted payback4.27 years3.90 years

Step 5: Sensitivity to the discount rate

Click to reveal the sensitivity table
  1. Recalculate the NPV at each rate. Only changes. ✅

    Discount rateNPV, case (a)NPV, case (b)
    6 percent124,331177,859
    8 percent104,960151,817
    10 percent88,108129,297
    12 percent73,377109,730
    14 percent60,44092,652
    16 percent49,03077,679
    18 percent38,92464,497
    20 percent29,93652,843
  2. Read the table. The NPV in case (a) falls from 124,331 at 6 percent to 29,936 at 20 percent. It is positive at every rate in the range, so the decision does not depend on the exact rate. ✅

  3. Where the NPV is zero. At higher rates the NPV reaches zero at 28.9 percent in case (a) and 33.8 percent in case (b): the IRRs of Steps 3 and 4, found from the other side. ✅

Application 2: The capacitor bank with a replacement in year 7



2,074,560 saving each year, years 1 to 12year123456789101112450,000 at year 0120,000 in year 7(new capacitors)
Cash flows of the capacitor bank

Step 1: Net present value

Click to reveal the NPV
  1. Present worth factor for 12 years.

    ✅

  2. Present value of the savings. . ✅

  3. Present value of the replacement. It is a single amount in year 7.

    A cost of 120,000 seven years away counts as 54,282 today. ✅

  4. Net present value.

    The NPV is about 12.3 million currency units, more than 27 times the cost. ✅

Step 2: IRR and discounted payback

Click to reveal the IRR and the payback
  1. Internal rate of return. brentq on the NPV function gives percent a year. ✅

  2. Check the IRR. When the saving is large and the life is long, later years add almost nothing at such a rate, and the IRR is close to , which is 461 percent. The check agrees. ✅

  3. Discounted payback from yearly cash flows. The first year’s saving has a present value of , far more than the cost. The crossing is inside year 1, at years by interpolation. ✅

  4. Discounted payback from monthly bills. The saving really arrives every month. With a monthly rate of and 172,880 a month, the cumulative discounted value turns positive in the third month, at about 2.65 months. The simple payback is 2.60 months. Discounting changes almost nothing over so short a time. ✅

Step 3: What this project needs

Click to reveal the judgement
  1. No refined analysis. The bank pays back in months. No reasonable discount rate, life or replacement cost changes the decision. The year 7 replacement, which looked like a complication, removes 0.4 percent of the NPV. ✅

  2. Proof of the saving. The whole result rests on the tariff: a demand charge per kVA and a surcharge for low power factor. The bank saves almost no kWh. If the utility changes its charges, or the site’s peak moves to another time, the saving changes although the bank works as designed. ✅

  3. What to check. Compare the maximum demand in kVA and the power factor on the bills before and after, and confirm that the surcharge line has gone. Three bills are enough to see it. ✅

Verify It in Python



The script defines the present worth factor, the NPV, the IRR (with brentq) and the payback, then applies them to project A in both cases and to project B. It prints the year-by-year table and the sensitivity table, and plots the NPV of project A against the discount rate.

npv_irr_projects.py
"""NPV, IRR and discounted payback of a pump drive and a power factor bank."""
import numpy as np
from scipy.optimize import brentq
import matplotlib.pyplot as plt
RATE = 0.12 # discount rate, an example
def pw_factor(i, n):
"""Present worth factor of a uniform yearly amount, P/A."""
return ((1 + i) ** n - 1) / (i * (1 + i) ** n)
def npv(i, cost, flows):
"""Net present value. flows[0] is the cash flow of year 1."""
years = np.arange(1, len(flows) + 1)
return -cost + np.sum(np.asarray(flows) / (1 + i) ** years)
def irr(cost, flows, low=0.001, high=20.0):
"""The rate at which the NPV is zero, found by Brent's method."""
return brentq(npv, low, high, args=(cost, flows))
def payback(cost, flows, i=0.0):
"""Payback in years; discounted when i > 0. Linear inside the year."""
total = -cost
for year, flow in enumerate(flows, start=1):
pv = flow / (1 + i) ** year
if total + pv >= 0.0:
return year - 1 + (-total) / pv
total += pv
return float("nan")
def report(name, cost, flows):
print(f"{name}")
print(f" NPV at {100 * RATE:.0f} %: {npv(RATE, cost, flows):,.0f}")
print(f" IRR: {100 * irr(cost, flows):.1f} %")
print(f" simple payback: {payback(cost, flows):.2f} y, "
f"discounted payback: {payback(cost, flows, RATE):.2f} y")
# ---------- Project A: drive on the booster pump ----------
COST_A, SAVE_A, UPKEEP, LIFE_A, RISE = 95_000, 31_800, 2_000, 10, 0.05
n = np.arange(1, LIFE_A + 1)
flows_a = np.full(LIFE_A, SAVE_A - UPKEEP, dtype=float)
flows_b = SAVE_A * (1 + RISE) ** (n - 1) - UPKEEP
print(f"P/A at 12 % for 10 years: {pw_factor(RATE, LIFE_A):.4f}")
print(f" check, 29,800 x P/A - 95,000 = "
f"{29_800 * pw_factor(RATE, LIFE_A) - COST_A:,.0f}")
report("Project A, case (a): constant price", COST_A, flows_a)
print(" year net flow factor present value cumulative")
total = -COST_A
for year, flow in zip(n, flows_a):
factor = 1 / (1 + RATE) ** year
total += flow * factor
print(f" {year:4d} {flow:10,.0f} {factor:8.4f} {flow * factor:15,.0f} "
f"{total:12,.0f}")
report("Project A, case (b): price rises 5 % a year", COST_A, flows_b)
# ---------- Project B: power factor correction bank ----------
COST_B, LIFE_B = 450_000, 12
flows_pf = np.full(LIFE_B, 172_880 * 12, dtype=float)
flows_pf[7 - 1] -= 120_000 # capacitors replaced in year 7
report("Project B: bank, capacitors replaced in year 7", COST_B, flows_pf)
print(f" present value of the year 7 replacement: "
f"{120_000 / (1 + RATE) ** 7:,.0f}")
monthly_rate = (1 + RATE) ** (1 / 12) - 1
months = payback(COST_B, np.full(12, 172_880.0), monthly_rate)
print(f" discounted payback from monthly bills: {months:.2f} months")
# ---------- Sensitivity of project A to the discount rate ----------
print("Project A, NPV against discount rate")
print(" rate % case (a) case (b)")
for pct in range(6, 21, 2):
print(f" {pct:6d} {npv(pct / 100, COST_A, flows_a):10,.0f} "
f"{npv(pct / 100, COST_A, flows_b):10,.0f}")
for label, flows in (("a", flows_a), ("b", flows_b)):
r = irr(COST_A, flows)
print(f" case ({label}): NPV is zero at {100 * r:.1f} %")
# ---------- Real and nominal rates ----------
print(f"Real 12 % with inflation 5 % is nominal "
f"{100 * (1.12 * 1.05 - 1):.1f} %")
# ---------- Plot ----------
rates = np.linspace(0.02, 0.45, 200)
fig, ax = plt.subplots(figsize=(8, 4.5))
ax.plot(100 * rates, [npv(r, COST_A, flows_a) for r in rates],
label="case (a): constant price")
ax.plot(100 * rates, [npv(r, COST_A, flows_b) for r in rates], "--",
label="case (b): price rises 5 % a year")
ax.axhline(0.0, color="gray", linewidth=0.8)
ax.set_xlabel("discount rate (%)")
ax.set_ylabel("NPV of project A (currency units)")
ax.set_title("NPV falls as the discount rate rises; it is zero at the IRR")
ax.legend()
fig.tight_layout()
fig.savefig("npv_irr_projects.png", dpi=120)
print("Saved npv_irr_projects.png")

Expected output

P/A at 12 % for 10 years: 5.6502
check, 29,800 x P/A - 95,000 = 73,377
Project A, case (a): constant price
NPV at 12 %: 73,377
IRR: 28.9 %
simple payback: 3.19 y, discounted payback: 4.27 y
year net flow factor present value cumulative
1 29,800 0.8929 26,607 -68,393
2 29,800 0.7972 23,756 -44,636
3 29,800 0.7118 21,211 -23,425
4 29,800 0.6355 18,938 -4,487
5 29,800 0.5674 16,909 12,422
6 29,800 0.5066 15,098 27,520
7 29,800 0.4523 13,480 41,000
8 29,800 0.4039 12,036 53,036
9 29,800 0.3606 10,746 63,782
10 29,800 0.3220 9,595 73,377
Project A, case (b): price rises 5 % a year
NPV at 12 %: 109,730
IRR: 33.8 %
simple payback: 3.02 y, discounted payback: 3.90 y
Project B: bank, capacitors replaced in year 7
NPV at 12 %: 12,346,319
IRR: 461.0 %
simple payback: 0.22 y, discounted payback: 0.24 y
present value of the year 7 replacement: 54,282
discounted payback from monthly bills: 2.65 months
Project A, NPV against discount rate
rate % case (a) case (b)
6 124,331 177,859
8 104,960 151,817
10 88,108 129,297
12 73,377 109,730
14 60,440 92,652
16 49,030 77,679
18 38,924 64,497
20 29,936 52,843
case (a): NPV is zero at 28.9 %
case (b): NPV is zero at 33.8 %
Real 12 % with inflation 5 % is nominal 17.6 %
Saved npv_irr_projects.png

In the plot both curves fall as the rate rises and cross zero at their IRR.

Common Mistakes



  • Adding savings of different years without discounting. A simple sum of 298,000 for the drive is worth 168,377 today at 12 percent.
  • Mixing real and nominal figures: savings in today’s prices discounted at a bank’s nominal rate. Use one kind throughout.
  • Escalating every cash flow with the energy price. Maintenance and replacement parts do not follow the energy tariff.
  • Ranking projects by IRR alone. A very high IRR on a small project can add less value than a modest IRR on a large one.
  • Forgetting a late cost such as a replacement. It must enter in its own year, discounted, with a minus sign.
  • Treating the discount rate as a fact. It is a choice. Show the NPV over a range of rates and see whether the decision changes.

Summary



  • Money has a date. The present value of an amount received in year is , and a uniform yearly saving is worth .
  • NPV is the present value of all savings and costs minus the capital cost. A positive NPV means the project repays its cost and the cost of money, with a surplus.
  • The IRR is the discount rate at which the NPV is zero. It is found numerically, and it does not show the size of the benefit.
  • Discounted payback is longer than simple payback: 4.27 against 3.19 years for the drive at a constant price.
  • At 12 percent over 10 years the drive has an NPV of 73,377 and an IRR of 28.9 percent. With the energy price rising 5 percent a year these become 109,730 and 33.8 percent.
  • The capacitor bank pays back in under 3 months. It needs proof of the saving on the bills, not a finer calculation.

Exercises



1. Find the present value of 50,000 currency units received in 5 years, at a discount rate of 10 percent.

Answer

.

2. Find the present worth factor for 15 years at 8 percent, and the present value of a saving of 12,000 a year over that time.

Answer

. The present value is .

3. A heat recovery unit costs 200,000 and saves 45,000 a year for 8 years. Find the NPV at 12 percent.

Answer

for 8 years at 12 percent. . The project is worth doing at 12 percent, with a small margin.

4. For the project of exercise 3, find the simple payback and the discounted payback at 12 percent.

Answer

Simple payback: years. The cumulative discounted value is after year 6, and year 7 adds , so the discounted payback is years, in year 7 of an 8-year life.

5. Find the IRR of the project of exercise 3. Bracket it between two whole-percent rates first.

Answer

At 15 percent the NPV is , and at 16 percent it is . A numerical solver gives percent. The margin over a 12 percent cost of money is small, so the saving must be well proved.

6. A project costs 120,000. It saves 30,000 in the first year, and the energy price rises 4 percent a year. The life is 6 years and the discount rate is 10 percent. Find the NPV with and without the price rise. Then give the nominal rate that matches a real rate of 10 percent when inflation is 6 percent.

Answer

Without the rise: , so . With the rise: , so . Nominal rate: percent.

References



  • D. G. Newnan, T. G. Eschenbach and J. P. Lavelle, Engineering Economic Analysis, 13th edition, Oxford University Press, 2017.
  • B. L. Capehart, W. C. Turner and W. J. Kennedy, Guide to Energy Management, 8th edition, Fairmont Press, 2016.
  • A. Thumann and D. P. Mehta, Handbook of Energy Engineering, 7th edition, Fairmont Press, 2013.


© 2021-2026 SiliconWit®. All rights reserved.
year 1 2 3 4 5 6 7 8 9 10 0 95,000 cost at year 0 29,800 net saving each year (31,800 − 2,000)
Cash flows of the drive, case (a)
Compounding value later of 100 today 100 year 0 112.00 year 1 125.44 year 2 Discounting 100 later, worth today 89.29 year 1 56.74 year 5 32.20 year 10 Dashed: the 100 received later. Gold: its worth today.
100 currency units at 12 percent
−50,000 0 100,000 200,000 0 % 10 % 20 % 30 % 40 % NPV rate i 73,377 at 12 % 203,000 at 0 % IRR 28.9 %: NPV = 0
NPV against discount rate
year 1 2 3 4 5 6 7 8 9 10 11 12 0 450,000 at year 0 2,074,560 saving each year, years 1 to 12 120,000 in year 7 new capacitors
Cash flows of the capacitor bank
Predict first

A project costs 95,000 currency units today and saves 29,800 net in each of the next 10 years. The discount rate rises from 12 percent to 20 percent, and nothing else changes. What happens to the net present value?

See it: every year's saving, and what it is worth today

Net present value, NPV
Internal rate of return, IRR
Present worth factor, P/A
Simple payback
Discounted payback
Present value of the net savings

Amounts are in currency units, and the chart is scaled in thousands. The cost is paid at year 0 and each saving arrives at the end of its year. The faint bar of a year is its net saving: the saving minus the maintenance. The strong bar inside it is the same amount divided by (1 + i)ⁿ. The line adds the strong bars to the cost, year by year. It ends at the NPV, and the gold mark shows where it crosses zero, which is the discounted payback. The energy price rise is applied to the saving only. The maintenance stays constant, as in the lesson. The IRR is found by bisection: the rate is narrowed between a low and a high value until the NPV is zero. Which case the numbers show: the first button is project A of this lesson, case (a), and the second is case (b). The third button keeps everything and ends the life after year 4. The discount rate is an example.

100895732 todayyear 1year 5year 10 discounting at 12 percent
at 12 percent: NPV 73,377 IRR: 28.9 percent 0 %12 %40 %NPV

Check yourself

Three questions. Each wrong choice is a mistake people really make, so read the note after you answer.

1. The drive saves 29,800 currency units net in each of 10 years. The discount rate is 12 percent. What are these savings worth today?

2. Only one of two projects can be done. The drive costs 95,000 and has an IRR of 28.9 percent and an NPV of 73,377. A small project costs 10,000 and saves 6,000 a year for 10 years: its IRR is 59.4 percent and its NPV is 23,901. The discount rate is 12 percent. Which adds more value?

3. The drive has a simple payback of 3.19 years. It fails at the end of year 4 and is not replaced. The site paid 12 percent a year for the money. What is the NPV?

Watch it build: ten yearly savings in today's money
1510year 1 a year for 10 years is worth0.893 … 0.322 today 105.65 P/A = 5.6502ten years count as 5.65 8.33 i near 0: P/A near 10for ever: 1 ÷ 0.12 = 8.33 29,800 × 5.6502 = 168,377− 95,000 = NPV 73,377
  1. One unit saved at the end of each year: at 12 %, year 1 is worth 0.893 today, year 10 only 0.322.
  2. Their sum is the present worth factor: P/A = 5.6502. Ten years of saving count as 5.65.
  3. The checks: with no discounting P/A is 10; a saving for ever is worth only 1 ÷ 0.12 = 8.33.
  4. The drive: 29,800 × 5.6502 = 168,377 today, less the cost of 95,000: NPV 73,377.
Found this useful?

Discussion

    Comments show your name. Be kind, stay on the topic.