Failure-finding interval
The relation holds when
One site changes every bearing at the yearly shutdown and still loses the conveyor twice a year. Another site repairs only what breaks, and on the night the mains fails its standby generator does not start, because nobody had tried it for eleven months. Both sites applied one rule to every machine, and each rule was right for some failures and wrong for the rest. A maintenance plan is a choice made failure mode by failure mode: what happens if it fails, can anything be done before it fails, and does that cost less than the failure. This lesson gives the logic of that choice and the two calculations that it needs most often. #MaintenanceStrategy #RCM #AgeReplacement
By the end of this lesson, you will be able to:
The cold store has two compressors, a borehole pump, a conveyor with a gearbox, and a standby generator. Each can fail in several ways, and the maintenance budget is one number. For each way of failing, the planner must decide whether to wait for it, replace the part before it, watch for it, or test for it.
The answer differs even inside one machine. A conveyor bearing wears out, and its failure stops the line at 12,000 currency units an hour. A control board on the same conveyor fails with no relation to its age, so a new board is no better than the old one. The generator can be dead for months and nobody knows, because nothing asks it to run.
A strategy chosen per machine (“the conveyor is on a yearly service”) cannot be right for all three. The unit of the decision is the failure mode.
There are only five answers, and every maintenance plan is a mixture of them.
| Strategy | What is done | It can work when |
|---|---|---|
| Run to failure | Nothing until the failure, then repair | The failure is evident and its consequence is acceptable |
| Scheduled restoration or replacement | Overhaul or replace at a fixed age, whatever the condition | The chance of failure rises with age, and most items reach that age |
| On-condition task | Inspect at an interval, act only when a fault is found | The failure gives a warning with a long enough P-F interval |
| Failure-finding task | Test at an interval whether a hidden function still works | The failure is hidden and a test can show it |
| Redesign | Change the machine, the process or the procedure | No task is possible or good enough |
Run to failure is a strategy, not neglect, provided it was chosen. A lamp in a corridor, a fan belt with a spare on the shelf, a board that fails at random: for these, waiting is the cheapest correct answer.
Redesign has a wide meaning here: a change to the hardware (a second pump, a larger bearing, a filter), to the way the machine is operated, or a spare kept on site.
The first question about a failure mode is not “what can we do” but “what happens if it occurs”. Reliability-centred maintenance, the method that came from the aircraft study of Nowlan and Heap, sorts consequences into four classes, and the class decides how good a task must be:
For the last two classes the test of a task is money: over time it must cost less than the failures it prevents. For a safety or environmental consequence the test is not money: the task must reduce the risk to an acceptable level, and if no task can, the design must change.
A task must pass two tests. It must be technically possible: the failure must behave in a way the task can use. And it must be worth doing: it must deal with the consequence well enough.
Scheduled replacement is technically possible only when there is an age at which the chance of failure starts to rise quickly, and most items survive to it. For an item that fails at random it does nothing; for an item with early failures it makes things worse, because every new part must again pass through its weakest period.
An on-condition task is technically possible when the failure gives a clear sign, the P-F interval is fairly consistent, and the time that remains after the sign is found is long enough to act. The interval of the task comes from the P-F interval.
A failure-finding task is technically possible when a test can show the state of the hidden function without damaging it, and when the test can be done often enough to give the availability that is needed.
The chart below gives the order of the questions, summarised in this course’s own words. Published reliability-centred maintenance diagrams are longer, and ask the task questions separately for each consequence class.
Where more than one task is possible, an on-condition task is usually considered first: it leaves the item in service for almost its whole life and acts only on the items that need it. Scheduled replacement throws away the remaining life of every item that would have lasted longer.
The logic has two default answers that surprise people. For a failure with no safety consequence and no affordable task, the correct answer is run to failure. For a hidden failure, doing nothing is not allowed: the function must at least be tested.
A standby machine has a hidden failure mode: it fails while it stands, and the failure shows only when it is called, like a smoke alarm with a dead battery that is found only by the test button or the fire. Let
Suppose each test finds any failure and a failed machine is repaired at once. A failure can occur at any moment between two tests, so on average it stays hidden for half an interval. The fraction of the time the machine is dead without anybody knowing is its unavailability
Failure-finding interval
The relation holds when
The standby does not matter by itself; the multiple failure does: the demand comes while the standby is dead. If demands arrive at
The two compressors of the cold store show a way to avoid the calculation. If duty and standby exchange roles every week, each is proved by a week of real work, and a failure of either is evident within a week: a failure-finding task with a short interval and no extra labour.
For an item that wears out, with an operational or non-operational consequence, the question is at what age to replace it. Age replacement: replace the item when it reaches age
Two costs are needed:
Each replacement starts a new cycle, which ends in a planned replacement with probability
Cost per running hour of age replacement
The top is the mean cost of one cycle and the bottom is its mean length. For a Weibull model,
A small
The integral has no simple formula for a Weibull model, so the minimum is found numerically: compute
There is a minimum only when the hazard rate rises with age (
The model assumes a new part is as good as new and correctly fitted, the two costs are known, and the life model is right. None is exactly true. A replacement can introduce a fault (a bearing fitted with a hammer, a misaligned coupling): one more reason not to replace earlier than the calculation supports. And the life model comes from few failures, so the best age carries an uncertainty that Application 1 measures.
Planned replacement.
Unplanned failure.
Ratio.
Mean life. For a Weibull model the mean life is
✅
Cost per running hour. Every cycle ends in a failure and lasts the mean life.
✅
Cost a year.
One age by hand. Try
The area under the survival curve up to 6,000 h, from the script, is 5,778 h. ✅
Cost per hour at 6,000 h.
Less than half of the cost of run to failure. ✅
Other ages. The script gives 4.07 at 2,000 h, 2.71 at 4,000 h, 2.63 at 5,000 h, 2.70 at 6,000 h, 3.05 at 8,000 h and 4.05 at 12,000 h. The curve falls, turns, and rises again. ✅
The minimum. The numerical search gives a best replacement age of 4,942 h, with a cost of 2.63 currency units per hour, which is 22,100 a year. ✅
What happens at that age. 7.9 percent of the bearings fail before they reach 4,942 h. The mean cycle is 4,825 h, so the site uses 1.74 bearings a year at this position and has 0.137 failures a year, about one in seven years. ✅
Saving. Against run to failure the cost falls from 49,700 to 22,100 a year, a saving of 55.5 percent. ✅
The present yearly change. Replacement at every 8,400 h costs 3.14 per hour, 19 percent above the best. One bearing in four fails before its yearly change. ✅
Best age with the site’s figures. With
Movement of the best age. From 4,942 h to 4,370 h is 572 h earlier, a change of 12 percent. In calendar time it is about 3.4 weeks of running. ✅
Cost of choosing the wrong one. If the maker’s figures are the true ones and the site replaces at 4,370 h, the cost is 2.66 per hour, which is 1.0 percent above the best. If the site’s figures are the true ones and it replaces at 4,942 h, the cost is 3.31, which is 0.8 percent above the best. ✅
Why the penalty is small. The curve is flat near its minimum. With the maker’s figures, every age between 3,750 h and 6,490 h is within 5 percent of the best cost. ✅
What does move. The predicted cost is 2.63 per hour with one set of figures and 3.29 with the other, a difference of 25 percent. The two sets agree on when to replace and disagree on what the year will cost. ✅
Cost of the checks. One check costs
Cost of the bearings. Each bearing runs for about its mean life of 12,411 h. Its end is a planned replacement with a chance of 0.9 and a failure with a chance of 0.1.
✅
Total.
Sensitivity to the chance of detection. With a chance of 0.8 the cost is 2.23 per hour. The on-condition task costs the same as the best age replacement when the chance is 0.72. Below that, age replacement is cheaper. ✅
A condition that the best age must satisfy. Setting the slope of
where
A second reading of the same condition. At the best age the cost per hour equals the hazard rate times the extra cost of a failure:
Simulation. The script draws 400,000 bearing lives from the maker’s model, replaces each at 4,942 h or at failure, and divides the total cost by the total hours: 2.633 per hour, with 7.9 percent failed first. ✅
Limiting cases. With a cost ratio of 1.5 the best age is 17,753 h and the saving against run to failure is 1.1 percent. With
Allowed unavailability.
Interval.
✅
Practical choice. A test every 4 weeks is inside the limit and easy to schedule. Its unavailability is
Test every 4 weeks. The mains fails 6 times a year, and the generator is dead for 0.77 percent of the time:
Test once a year.
Test every week.
The exact mean unavailability for a constant hidden failure rate and a perfect test is
At 5.2 weeks it gives 0.99 percent against 1.00 percent from the simple relation. At 52 weeks it gives 9.37 percent against 10.00 percent. The simple relation is close for short intervals and a little pessimistic for long ones. ✅
Repair time. If a failed test is followed by 48 hours of repair, the generator is also unavailable during repairs:
An uncertain failure rate. The rate of 0.2 a year would come from one or two events in the life of one generator. If the true rate is 0.4 a year, the interval for 99 percent is 2.6 weeks, and the 4 week test gives 98.5 percent. ✅
What a test must be. The relation assumes that the test finds every hidden failure. A start with no load proves the battery and the starter. It does not prove that the generator can take the load or that the changeover works. ✅
The script computes the cost per running hour of the bearing for run to failure, age replacement and the on-condition task, with the maker’s figures and with the site’s, checks the minimum by its condition and by simulation, and then computes the failure-finding interval of the generator. It saves one plot of the cost against the replacement age.
"""Age replacement, run to failure and on-condition cost for a bearing,and the failure-finding interval of a standby generator."""import numpy as npfrom scipy.integrate import quadfrom scipy.optimize import minimize_scalarfrom scipy.special import gammaimport matplotlib.pyplot as plt
TECH = 1500.0 # one technician hourBEARING = 4500.0 # one bearingDOWN = 12000.0 # one hour of conveyor downtimeCP = BEARING + 2 * TECH # planned replacementCF = BEARING + 6 * TECH + 5 * DOWN # unplanned failureYEAR = 8400.0 # running hours a year
def R(t, beta, eta): return np.exp(-(t / eta) ** beta)
def mean_life(beta, eta): return eta * gamma(1.0 + 1.0 / beta)
def cycle_length(T, beta, eta): """Mean running hours of one bearing when it is replaced at age T or at failure.""" return quad(R, 0.0, T, args=(beta, eta))[0]
def cost_rate(T, beta, eta, cp=CP, cf=CF): """Mean cost per running hour of replacement at age T.""" r = R(T, beta, eta) return (cp * r + cf * (1.0 - r)) / cycle_length(T, beta, eta)
def best_age(beta, eta, cp=CP, cf=CF): """Age with the lowest cost per hour: a coarse search, then a fine one.""" grid = eta * np.linspace(0.02, 10.0, 500) k = int(np.argmin([cost_rate(T, beta, eta, cp, cf) for T in grid])) lo, hi = grid[max(k - 1, 0)], grid[min(k + 1, grid.size - 1)] res = minimize_scalar(cost_rate, bounds=(lo, hi), args=(beta, eta, cp, cf), method="bounded", options={"xatol": 0.01}) return res.x, res.fun
print(f"Costs: planned {CP:.0f}, unplanned {CF:.0f}, ratio {CF / CP:.1f}")
MAKER = (2.4, 14000.0)SITE = (2.13, 12750.0)print("Application 1: conveyor bearing")for name, (beta, eta) in (("maker's figures", MAKER), ("site's 12 failures", SITE)): m = mean_life(beta, eta) rtf = CF / m T, c = best_age(beta, eta) F = 1.0 - R(T, beta, eta) L = cycle_length(T, beta, eta) print(f" {name}: beta {beta}, eta {eta:.0f} h") print(f" mean life {m:.0f} h, run to failure {rtf:.3f} per hour, " f"{rtf * YEAR:.0f} a year") print(f" best replacement age {T:.0f} h, cost {c:.3f} per hour, " f"{c * YEAR:.0f} a year") print(f" at that age: {100 * F:.1f} % fail first, mean cycle {L:.0f} h, " f"{YEAR / L:.2f} bearings a year, {YEAR / L * F:.3f} failures a year")
beta, eta = MAKERT_m, c_m = best_age(*MAKER)T_s, c_s = best_age(*SITE)print(" cost per hour at chosen ages, maker's figures taken as true:")for T in (2000.0, 3000.0, 4000.0, T_s, T_m, 5000.0, 6000.0, 8000.0, 8400.0, 12000.0): c = cost_rate(T, beta, eta) print(f" {T:6.0f} h: survive {R(T, beta, eta):.4f}, mean cycle " f"{cycle_length(T, beta, eta):5.0f} h, cost {c:.3f} " f"({100 * (c / c_m - 1):+.1f} % against the best)")print(f" ages within 5 % of the best cost: " f"{min(T for T in np.arange(1000, 12000, 10.0) if cost_rate(T, beta, eta) < 1.05 * c_m):.0f}" f" to " f"{max(T for T in np.arange(1000, 12000, 10.0) if cost_rate(T, beta, eta) < 1.05 * c_m):.0f} h")
# the same two ages if the site's figures were the true onesc_ms = cost_rate(T_m, *SITE)print(f" site's figures taken as true: {T_m:.0f} h costs {c_ms:.3f}, " f"{100 * (c_ms / c_s - 1):+.1f} % against their best of {c_s:.3f}")
# the condition at the minimum: h(T) * integral of R - F(T) = CP / (CF - CP)h = beta / eta * (T_m / eta) ** (beta - 1.0)lhs = h * cycle_length(T_m, beta, eta) - (1.0 - R(T_m, beta, eta))print(f" condition at the minimum: left side {lhs:.4f}, right side {CP / (CF - CP):.4f}; " f"hazard rate there {h * 1e6:.1f} per million hours, times (CF - CP) = " f"{h * (CF - CP):.3f} per hour")
# check by simulation: many bearings in a row, replaced at the best age or at failurerng = np.random.default_rng(6)life = eta * rng.weibull(beta, 400000)planned = life > T_mhours = np.where(planned, T_m, life).sum()cost = np.where(planned, CP, CF).sum()print(f" simulation of 400000 bearings at {T_m:.0f} h: {cost / hours:.3f} per hour, " f"{100 * (1 - planned.mean()):.1f} % failed first")
# on-condition: vibration check every 4 weeks (672 h), 0.25 technician hour eachCHECK = 0.25 * TECHINTERVAL = 672.0m = mean_life(beta, eta)print(f" on-condition, check {CHECK:.0f} every {INTERVAL:.0f} h " f"({CHECK / INTERVAL:.3f} per hour for the checks):")for p in (0.9, 0.8, 0.6, 0.4): c = CHECK / INTERVAL + (p * CP + (1 - p) * CF) / m print(f" fault found in time with chance {p:.1f}: {c:.3f} per hour, " f"{c * YEAR:.0f} a year")p_even = (CHECK / INTERVAL + CF / m - c_m) / ((CF - CP) / m)print(f" equal to the best age replacement when the chance is {p_even:.2f}")
# when does age replacement stop paying? smaller cost ratios and smaller shapesprint(" best age for other cost ratios (maker's figures):")for ratio in (9.8, 5.0, 3.0, 2.0, 1.5): T, c = best_age(beta, eta, CP, ratio * CP) rtf = ratio * CP / m print(f" ratio {ratio:3.1f}: best age {T:6.0f} h, saving against run to failure " f"{round(100 * (1 - c / rtf), 1) + 0.0:.1f} %")print(" best age for other shapes (eta 14000 h, the lesson's costs):")for b in (3.5, 2.4, 1.5, 1.2, 1.0): T, c = best_age(b, eta) rtf = CF / mean_life(b, eta) print(f" beta {b:3.1f}: best age {T:6.0f} h, saving against run to failure " f"{round(100 * (1 - c / rtf), 1) + 0.0:.1f} %")
# ---------- Application 2: standby generator ----------print("Application 2: standby generator, hidden failure")LAM = 0.2 # hidden failures a yearTARGET = 0.99 # required availability on demandDEMANDS = 6.0 # mains failures a yearT_ff = 2.0 * (1.0 - TARGET) / LAMprint(f" interval from U = lambda T / 2: {T_ff:.3f} years = {T_ff * 52:.1f} weeks")for label, T in (("5.2 weeks", T_ff), ("4 weeks", 4 / 52), ("1 week", 1 / 52), ("26 weeks", 0.5), ("52 weeks", 1.0)): approx = LAM * T / 2.0 exact = 1.0 - (1.0 - np.exp(-LAM * T)) / (LAM * T) print(f" test every {label}: unavailability {100 * approx:.2f} % " f"(exact {100 * exact:.2f} %), demands not met {DEMANDS * approx:.3f} a year, " f"one in {1 / (DEMANDS * approx):.0f} years")repair = 48.0 / 8760.0 # two days to repair a fault that a test findsT4 = 4 / 52print(f" with 48 h of repair after each failed test, test every 4 weeks: " f"{100 * (LAM * T4 / 2 + LAM * repair):.2f} %")T_two = 2.0 * (1.0 - TARGET) / (2 * LAM)print(f" if the hidden failure rate is 0.4 a year: interval {T_two * 52:.1f} weeks")
# ---------- Plot ----------ages = np.linspace(1000.0, 16000.0, 151)fig, ax = plt.subplots(figsize=(8, 5))for name, (b, e) in (("maker's figures", MAKER), ("site's 12 failures", SITE)): ax.plot(ages, [cost_rate(T, b, e) for T in ages], label=f"age replacement, {name}") ax.axhline(CF / mean_life(b, e), linewidth=0.8, linestyle="--", color="gray")ax.plot([T_m, T_s], [c_m, c_s], "o", color="black")ax.set_xlabel("replacement age (running hours)")ax.set_ylabel("cost per running hour (currency units)")ax.set_title("Conveyor bearing: cost against replacement age")ax.set_ylim(0, 8)ax.legend()fig.tight_layout()fig.savefig("maintenance_strategy.png", dpi=120)print("Saved maintenance_strategy.png")Expected output
Costs: planned 7500, unplanned 73500, ratio 9.8Application 1: conveyor bearing maker's figures: beta 2.4, eta 14000 h mean life 12411 h, run to failure 5.922 per hour, 49747 a year best replacement age 4942 h, cost 2.633 per hour, 22118 a year at that age: 7.9 % fail first, mean cycle 4825 h, 1.74 bearings a year, 0.137 failures a year site's 12 failures: beta 2.13, eta 12750 h mean life 11292 h, run to failure 6.509 per hour, 54677 a year best replacement age 4370 h, cost 3.288 per hour, 27618 a year at that age: 9.7 % fail first, mean cycle 4231 h, 1.99 bearings a year, 0.193 failures a year cost per hour at chosen ages, maker's figures taken as true: 2000 h: survive 0.9907, mean cycle 1995 h, cost 4.069 (+54.5 % against the best) 3000 h: survive 0.9755, mean cycle 2978 h, cost 3.061 (+16.2 % against the best) 4000 h: survive 0.9517, mean cycle 3943 h, cost 2.710 (+2.9 % against the best) 4370 h: survive 0.9407, mean cycle 4293 h, cost 2.659 (+1.0 % against the best) 4942 h: survive 0.9211, mean cycle 4825 h, cost 2.633 (+0.0 % against the best) 5000 h: survive 0.9190, mean cycle 4879 h, cost 2.633 (+0.0 % against the best) 6000 h: survive 0.8773, mean cycle 5778 h, cost 2.699 (+2.5 % against the best) 8000 h: survive 0.7702, mean cycle 7430 h, cost 3.050 (+15.8 % against the best) 8400 h: survive 0.7457, mean cycle 7733 h, cost 3.140 (+19.3 % against the best) 12000 h: survive 0.5012, mean cycle 9985 h, cost 4.048 (+53.7 % against the best) ages within 5 % of the best cost: 3750 to 6490 h site's figures taken as true: 4942 h costs 3.314, +0.8 % against their best of 3.288 condition at the minimum: left side 0.1136, right side 0.1136; hazard rate there 39.9 per million hours, times (CF - CP) = 2.633 per hour simulation of 400000 bearings at 4942 h: 2.633 per hour, 7.9 % failed first on-condition, check 375 every 672 h (0.558 per hour for the checks): fault found in time with chance 0.9: 1.694 per hour, 14231 a year fault found in time with chance 0.8: 2.226 per hour, 18698 a year fault found in time with chance 0.6: 3.290 per hour, 27632 a year fault found in time with chance 0.4: 4.353 per hour, 36566 a year equal to the best age replacement when the chance is 0.72 best age for other cost ratios (maker's figures): ratio 9.8: best age 4942 h, saving against run to failure 55.5 % ratio 5.0: best age 6905 h, saving against run to failure 36.7 % ratio 3.0: best age 9319 h, saving against run to failure 19.8 % ratio 2.0: best age 12720 h, saving against run to failure 7.0 % ratio 1.5: best age 17753 h, saving against run to failure 1.1 % best age for other shapes (eta 14000 h, the lesson's costs): beta 3.5: best age 5797 h, saving against run to failure 68.8 % beta 2.4: best age 4942 h, saving against run to failure 55.5 % beta 1.5: best age 5378 h, saving against run to failure 24.6 % beta 1.2: best age 9814 h, saving against run to failure 5.6 % beta 1.0: best age 140000 h, saving against run to failure 0.0 %Application 2: standby generator, hidden failure interval from U = lambda T / 2: 0.100 years = 5.2 weeks test every 5.2 weeks: unavailability 1.00 % (exact 0.99 %), demands not met 0.060 a year, one in 17 years test every 4 weeks: unavailability 0.77 % (exact 0.77 %), demands not met 0.046 a year, one in 22 years test every 1 week: unavailability 0.19 % (exact 0.19 %), demands not met 0.012 a year, one in 87 years test every 26 weeks: unavailability 5.00 % (exact 4.84 %), demands not met 0.300 a year, one in 3 years test every 52 weeks: unavailability 10.00 % (exact 9.37 %), demands not met 0.600 a year, one in 2 years with 48 h of repair after each failed test, test every 4 weeks: 0.88 % if the hidden failure rate is 0.4 a year: interval 2.6 weeksSaved maintenance_strategy.png1. A gearbox seal costs 9,000 currency units. A planned change takes 3 technician hours at 1,500 an hour with no lost production. An unplanned failure takes 8 technician hours and stops the conveyor for 4 hours at 12,000 an hour. Find the two costs and their ratio.
2. A conveyor belt has a Weibull life with
The mean life is
3. For the belt of exercise 2, a planned replacement costs 20,000. The area under the survival curve up to 6,000 h is 5,695 h. Find the cost per hour of replacement at 6,000 h and the saving against run to failure.
4. A fire pump stands by and has a hidden failure rate of 0.5 a year. It must be available 97 percent of the time. (a) Find the failure-finding interval in weeks. (b) The pump is in fact tested every 8 weeks, and it is called 4 times a year. Find its unavailability and the rate of unmet demands. (c) What must be said about this example before the result is used?
(a)
5. For the conveyor bearing of Application 1, a different on-condition task costs 500 currency units a check, every 336 running hours, and finds a fault in time with a chance of 0.85. Find its cost per hour and compare it with the best age replacement at 2.63 per hour.
Checks:
6. Choose a strategy for each failure mode and give the reason. (a) A compressor contactor that fails at random, with a standby compressor that takes the load and a spare contactor in the store. (b) The low-oil-pressure trip of a compressor, which acts only if the oil pressure is lost. (c) A drive belt that wears out, on a fan whose stop costs only the belt and the repair, with a planned change costing almost the same as an unplanned one.
(a) Run to failure: the failure is evident, age does not matter, so scheduled replacement cannot help, and the consequence is small because the standby takes over. (b) A failure-finding task: the trip is a protective device with a hidden failure, so it must be tested at an interval set from its failure rate and the availability required. (c) Run to failure, or replacement when convenient: the item wears out, but with the two costs almost equal the cost curve has no useful minimum.
A conveyor bearing wears out. Its mean life is about 12,400 running hours. A failure in service costs about ten times as much as a planned change. At what age is it cheapest to change the bearing?
The curve is the cost per running hour of the lesson's conveyor bearing when it is changed at a fixed age, or at failure if that comes first. All costs are in currency units, and a year is 8,400 running hours. At the start the figure has the lesson's values: a planned change of 7,500, a failure of 73,500, and the maker's figures β = 2.4 and η = 14,000 h. The second button puts in the line fitted to the site's own twelve failures, β = 2.13 and η = 12,750 h. The horizontal line is run to failure, which the curve approaches at great ages. The thick mark on the age axis shows the ages that cost no more than 5 percent above the best: the curve is flat near its lowest point, so the exact age matters little. Lower the cost of a failure toward the cost of a planned change, or lower β toward 1, and watch the lowest point move to the right and disappear. The model takes a new part as correctly fitted and as good as new, and it gives averages over many bearings.
Three questions. Each wrong choice is a mistake people really make, so read the note after you answer.
1. A planned change costs 10,000 currency units and a failure costs 50,000. With replacement at 4,000 h, 90 percent of the parts reach that age, and the area under the survival curve up to 4,000 h is 3,800 h. What is the cost per running hour?
2. A control board fails at random: its life has β = 1. A failure costs ten times a planned change. What is the best age for a planned change?
3. For the conveyor bearing (β = 2.4, η = 14,000 h) the best age is 4,942 h when a failure costs 9.8 times a planned change. The downtime is removed by a design change, and a failure now costs only 2 times a planned change. What happens to the best age?
No comments yet. Questions, results from your own build, a better way to explain it: all welcome.
Kept on this device only. Nothing is sent anywhere.
Tip: select words in the lesson, or tap a figure or an equation, to put a note right there.
The lesson has changed and these words are no longer in it. Your notes are kept, with the words you chose.