Skip to content
You Start with one site
Amounts in Start with one site
Control, Measurement & Energy · Course

A Condition Monitoring Programme

Lesson 10 of 10 26 min read
Found this useful?

Many sites buy a vibration meter, take readings for three months, and stop. The numbers were written in a book, nobody had agreed what a high number should cause, and the first real failure came between two visits on a machine that was not on the list. The instrument was never the problem. What was missing was a programme: a short written plan that says which machines are watched, for which faults, how often, against which limits, and what happens when a limit is crossed. This lesson builds that plan for four machines and then tests it with money. #ConditionMonitoring #MaintenancePlanning #PredictiveMaintenance

Learning Objectives

By the end of this lesson, you will be able to:

  1. Rank the machines of a site by what a failure costs, with a simple stated score
  2. Choose the failure modes, the measurement and the measurement point for each machine
  3. Apply the P-F interval idea to set the measurement interval
  4. Decide in advance the action that each alarm triggers
  5. Calculate the expected yearly cost of route readings and of fitted sensors from stated assumptions

Real-World System Problem: One site, four machines, one technician



A small processing site has the four machines of this course: a 22 kW compressor motor (A), a borehole booster pump (B), a belt-driven condenser fan (C) and a conveyor gearbox (D). When the compressor stops, the product in process is lost. When the fan stops, the plant runs at reduced capacity and loses little.

The site has one maintenance technician and a small budget. It cannot measure everything every day, and need not: the four machines do not cost the same when they fail, and their faults do not develop at the same speed. A programme spends the measuring effort where a failure costs most and a warning arrives in time to be used.

D conveyorgearboxline stopsC condenser fanbelt drivereduced capacityB booster pump48.33 Hzwater supplyA compressormotor, 24.42 Hzproduct at risk
The site and what each machine carries

Fundamental Theory: From measurements to a programme



The programme in nine steps

ISO 17359 is the general guidance document for setting up condition monitoring. The steps below follow the same general order, in this course’s own words.

  1. List the machines and what each one does for the site.
  2. Rank them by what a failure costs.
  3. For each machine worth watching, list the failure modes and what each would show.
  4. Choose the measurement, the point and the operating state for each failure mode.
  5. Choose the interval from how fast the fault develops.
  6. Take baselines and set limits.
  7. Decide in advance the action that each alarm triggers, and who decides.
  8. Measure, record, and diagnose when an alarm comes.
  9. Review after every repair and every year, and correct the plan.
RepairReviewFailuremodesList &rankAlarm &actionDiagnoseBaseline& limitsMeasure-ment andinterval
The programme is a loop, not a list

Ranking by what a failure costs

The cost of a failure is the repair plus what the site loses while the machine is down. Three questions capture most of it: how large is the cost, is there a standby, and how long does the repair take. This lesson scores each from 1 to 3 and multiplies the scores: a simple method chosen for this lesson, not a standard, meant to make the site argue about the right questions.

Failure modes worth watching

A failure mode is worth watching when three things are true: it is likely enough, it costs enough, and it gives a sign that can be measured before the failure. A fault that gives no warning needs a different defence, such as a standby or a planned replacement.

The P-F interval

Point P is the moment at which a developing fault can first be detected by the chosen measurement. Point F is functional failure: the machine no longer does its work. The time between them is the P-F interval.

conditionP: fault can firstobe detectedF: functionalxfailuretimeP-Finterval
The P-F interval

The P-F interval belongs to a fault and a measurement together: envelope analysis with an industrial accelerometer detects a bearing defect early (a long P-F interval), an overall velocity reading detects it late (a short one). A better measurement buys time, as a smoke detector warns before the flames are seen.

The commonly used rule for the measurement interval

is the time between two readings and is the P-F interval. With this interval at least two readings fall between P and F. One reading raises the alert, and the second confirms the rise.

The rule is a starting point. The time to arrange the repair must also fit inside what remains after detection. P-F intervals are seldom known well and vary from one failure to the next on the same machine; the site’s own repair records are the best source.

Route readings against fitted sensors

Route readingsPermanently fitted sensor
Who measuresA person with a portable analyserA sensor that stays on the machine
IntervalWeeks or monthsMinutes or hours
Depth of one readingHigh: spectrum, envelope, several points and directionsUsually lower: overall level, some bands
Operating stateWhatever the machine is doing during the visitLogged with every reading
CostEach visitOnce to fit, then small
Weak pointThe fault that develops between visitsEarly bearing defects at high frequency, with low-cost sensors
route visitsfitted sensor'''''''''''''''''''faultP ox F(3 days)timeone month
A fast fault between two monthly visits

Continuous monitoring adds two things a visit cannot: it sees the fault that begins and ends between two visits, and it records the operating context, so each reading is compared with others at the same speed and load.

The action for each alarm

An alarm with no agreed action is noise. Decide the actions before the first alarm, write the name of the person who decides, and keep the list beside the limits.

The expected yearly cost

A programme costs money every year, and a failure costs money in some years. The expected cost puts the two on one scale.

Expected yearly cost of one scheme

is the yearly cost of the scheme, the probability that the fault develops in a year, the probability that the scheme detects it in time, the cost of a planned repair and the cost of an unplanned failure.

Every term is an estimate. The value of the calculation is that it shows which estimate decides the answer.

Application 1: A programme for machines A to D



Step 1: Rank the machines

Click to reveal the ranking
  1. Failure cost. Add the repair and the lost production: A is 30,000, B is 7,000, C is 2,500 and D is 14,000 currency units. ✅

  2. Scores.

    MachineCostStandbyRepair timeCriticality
    A compressor motor33218
    D conveyor gearbox23212
    B booster pump2228
    C condenser fan1212

    The order is A, D, B, C. ✅

  3. What the ranking decides. Machines A and D get a fitted sensor and a monthly route. Pump B gets the monthly route. Fan C gets a route reading every three months. ✅

Step 2: Failure modes, measurements and points

Click to reveal the measurement plan
  1. Failure modes and the sign of each. Each sign is what the fault is consistent with, not proof of it.

    MachineFailure modes worth watchingSign to look for
    ABearing defect on the 6309Envelope lines at BPFO 74.15 Hz or BPFI 121.19 Hz, higher crest factor
    AUnbalance, misalignment, looseness1× at 24.42 Hz, 2× and axial, many harmonics
    AElectrical100 Hz, sidebands at 2.33 Hz round 1×
    BUnbalance, misalignment1× at 48.33 Hz, 2× and axial
    BImpeller wear, flow far from design, cavitationVane pass 290 Hz, broadband high-frequency level
    CBelt wear, dirt on the bladesMultiples of 4.75 Hz, fan 1× at 9.67 Hz, blade pass 67.7 Hz
    DGear wear or damageGear mesh 410.8 Hz with sidebands at 24.17 or 6.04 Hz
    B, C, DBearing defectsEnvelope lines at the bearing frequencies of each bearing

    Every machine has at least one sign that can be measured. ✅

  2. Measurement and point.

    MachineMeasurementWhereSettings that matter
    AFitted: overall velocity and band levelsA2, motor drive-end housing, radialBand 10 to 1000 Hz, state logged
    ARoute: spectrum at 8 readings, envelope at A2A1, A2, A3Record of 4 s, industrial accelerometer
    BRoute: spectrum at 10 readings, envelopeB1 to B4Range above 870 Hz
    CRoute: spectrum, overall from 2 HzFan bearing housingsRecord of about 23 s
    DFitted: overall velocity and gear mesh bandInput shaft housing, radialLoad logged
    DRoute: spectrum on both shafts, envelopeBearing housings of both shaftsRange above 1232 Hz, record of 1.6 s

    The settings come from the machines: the fan’s belt and shaft lines lie below 10 Hz, and the gearbox needs three times its gear mesh frequency. ✅

  3. Safety. Every route point is reached with the guards in place and with the site’s permission. Fitted sensors, pads and cables are installed with the machine stopped, isolated and locked out under the site’s permit. The compressor has one reachable bearing, and the plan records that gap openly. ✅

Step 3: Intervals from the P-F interval

Click to reveal the two cases
  1. Bearing defect, P-F interval of 6 weeks.

    The interval must be 3 weeks or less. ✅

  2. Test the monthly route. A month is weeks, which is longer than 3 weeks. One reading always falls inside the 6 weeks. A second reading falls inside with a probability of only . The route must be walked every two weeks for this fault, or a fitted sensor must cover the time between visits. ✅

  3. Fast fault, P-F interval of 3 days. An example is a bearing that has lost its lubricant.

    No route can keep an interval of 36 hours on four machines. ✅

  4. What the monthly route sees of the fast fault. A visit falls inside the 3 days with a probability of , about one case in ten, and even then there is no time to plan. A fitted sensor that reads each hour takes 72 readings between P and F. ✅

  5. Result. Machines A and D keep their fitted sensors with hourly readings, and all route intervals stay monthly except the fan. The fitted sensor covers the gap that the half-interval rule shows in a monthly route. Pump B has no fitted sensor: its monthly route puts one reading inside a 6 week P-F interval, and the second, confirming reading must come from the action table (repeat within a week of an alert). The rule is met on pump B only if that repeat is really made. ✅

Step 4: Limits, their source and the action for each alarm

Click to reveal the alarm table
  1. Limits and source.

    LimitValue at A2HSource
    Alert 11.018 mm/s (mean plus 3 standard deviations)The point’s own first 12 readings
    Alert 21.404 mm/s (1.6 times the baseline)Common practice figure, own baseline
    Danger2.194 mm/s (2.5 times the baseline)Common practice figure, own baseline
    CeilingZone boundary for the machine classThe standard for that class, or the maker
    Band limits1.6 and 2.5 times each band’s baselineOwn baseline of each band

    The same method is used at every point of machines A to D, each with its own baseline at a stated speed and load. ✅

  2. Actions.

    AlarmActionWho
    Alert 1Inspect: repeat the reading at the same state. If it is confirmed, request a spectrum and envelope within one weekTechnician
    Alert 2, or a confirmed rising trendPlan a repair at the next stop: order parts, estimate the date, halve the intervalMaintenance planner
    Danger, or a sudden jumpStop now, in the controlled way of the site’s procedureThe responsible person named in the plan

    Each alarm has one action and one owner. ✅

  3. Check the ranking a second way. Ranking by failure cost alone gives 30,000, 14,000, 7,000 and 2,500: the order A, D, B, C again. The two methods agree here. They would differ if pump B had a full standby, which lowers its score from 8 to 4 while its failure cost stays the same. ✅

  4. Check the coverage. Read the failure modes of Step 2 against the measurements. Each has a measurement that can show it. Three gaps remain and are written in the plan: the far bearing of the compressor, early bearing defects between specialist visits, and fast faults on pump B and fan C. ✅

Application 2: Route readings or a fitted sensor for machine A



Step 1: Probability that the monthly route detects in time

Click to reveal the derivation
  1. One P-F interval. Let be the P-F interval in weeks and weeks the time between visits. Detection is in time when a visit falls in the first weeks after point P. Point P falls at a random moment between two visits, so

    For weeks this is 0.23, and for of 5.33 weeks or more it is 1. ✅

  2. Average over the P-F intervals. is uniform from 2 to 10 weeks, a range of 8 weeks. From 2 to 5.33 weeks the probability rises in a straight line, and above 5.33 weeks it is 1.

    A visit comes in time in 84.0 percent of cases. ✅

  3. Include the reading itself.

    The monthly route detects the fault in time with a probability of 0.756. ✅

Step 2: Probability that the fitted sensor detects in time

Click to reveal the result
  1. The window of the sensor. The sensor sees the fault for weeks before failure. Hourly readings make the timing of a visit irrelevant. Detection is in time when week, which means weeks. ✅

  2. Probability.

    The fitted sensor detects the fault in time with a probability of 0.844. ✅

Step 3: Expected yearly cost of each scheme

Click to reveal the three costs
  1. (a) No monitoring.

    The expected cost is 3,000 currency units a year. ✅

  2. (b) Monthly route. The scheme costs .

    The expected cost is 2,722 currency units a year. ✅

  3. (c) Fitted sensor. The scheme costs . A detected fault costs the planned repair and one specialist visit, 2,900.

    The expected cost is 1,633 currency units a year. ✅

Step 4: Sensitivity to the two weakest assumptions

Click to reveal the sensitivity
  1. The probability of failure. This is the least known figure. The script repeats the calculation.

    (a) None(b) Route(c) Fitted
    0.026001,9841,063
    0.051,5002,2611,277
    0.103,0002,7221,633
    0.206,0003,6432,347

    The order changes with . ✅

  2. Break-even. The route costs less than no monitoring only when is above . The fitted sensor costs less than no monitoring when is above . For a bearing that fails once in 50 years, neither pays on machine A alone. ✅

  3. How late the fitted sensor sees the fault. The share of 40 percent is a guess. With 50 percent, and . With 25 percent, and . With 15 percent, and , which is above the route. ✅

  4. Where the two schemes are equal. Scheme (c) costs the same as scheme (b) when . Above that value the fitted sensor is the cheaper scheme under these assumptions. ✅

  5. Check by simulation. The script draws one million P-F intervals and visit times at random. It finds a timing probability of 0.8395 for the monthly route, against 0.8397 from the formula. ✅

Verify It in Python



The script scores the four machines, applies the P-F rule, derives the detection probabilities by formula and by simulation, and prints the expected costs and both sensitivity tables. Its plot shows the expected cost of the three schemes against the assumed probability of failure.

monitoring_programme_cost.py
"""A condition monitoring programme for four machines: criticality ranking,
the P-F interval rule, and the expected yearly cost of three schemes.
Every cost and probability is a stated assumption, in currency units."""
import numpy as np
import matplotlib.pyplot as plt
# ---------- Application 1: ranking ----------
# name: (repair cost, lost production, standby score, repair time score)
MACHINES = {
"A compressor motor": (6000, 24000, 3, 2),
"B booster pump": (4000, 3000, 2, 2),
"C condenser fan": (1500, 1000, 2, 1),
"D conveyor gearbox": (8000, 6000, 3, 2),
}
def cost_score(cost):
return 1 if cost < 5000 else (2 if cost <= 20000 else 3)
print("Application 1: criticality = cost score x standby score x repair time score")
ranking = []
for name, (repair, lost, standby, rtime) in MACHINES.items():
cost = repair + lost
ranking.append((cost_score(cost) * standby * rtime, cost, name, cost_score(cost),
standby, rtime))
for score, cost, name, cs, standby, rtime in sorted(ranking, reverse=True):
print(f" {name:<19} failure cost {cost:>6} scores {cs} x {standby} x {rtime} = {score}")
WEEKS_PER_MONTH = 52.0 / 12.0
print("P-F interval rule: measure at intervals of no more than half the P-F interval")
for label, pf_weeks in (("bearing defect, P-F 6 weeks", 6.0), ("fast fault, P-F 3 days", 3.0 / 7.0)):
limit = pf_weeks / 2.0
in_window = pf_weeks / WEEKS_PER_MONTH # mean number of monthly readings
print(f" {label}: interval at most {limit:.2f} weeks ({limit * 7:.1f} days); "
f"monthly route gives {in_window:.2f} readings in the window on average; "
f"hourly sensor gives {pf_weeks * 7 * 24:.0f}")
print(f" P-F 6 weeks: chance of a second monthly reading in the window "
f"{(6.0 - WEEKS_PER_MONTH) / WEEKS_PER_MONTH:.2f}")
print(f" P-F 3 days: chance that a monthly visit falls in the window "
f"{(3.0 / 7.0) / WEEKS_PER_MONTH:.3f}")
# ---------- Application 2: expected yearly cost for machine A ----------
P_FAIL = 0.10 # chance of a bearing failure developing in a year
C_UNPLANNED = 30000 # repair 6000 + lost stock 24000
C_PLANNED = 2500 # bearing changed at a planned stop
PF_LOW, PF_HIGH = 2.0, 10.0 # P-F interval, weeks, uniform
LEAD = 1.0 # weeks needed to arrange the planned repair
Q_ACT = 0.90 # chance that a reading inside the window is recognised and acted on
ROUTE_COST = 12 * 150 # machine A's share of 12 visits a year
SENSOR_COST = 240 + 240 + 12 * 20 # sensor over 5 years + data service + monthly review
C_SPECIALIST = 400 # one visit with an analyser when the trend rises
FALSE_CALLS = 0.5 # specialist visits a year that find nothing
K_LATE = 0.40 # share of the P-F interval in which the fitted sensor sees the fault
def p_route(interval, lead=LEAD, lo=PF_LOW, hi=PF_HIGH):
"""Mean of min(1, (T - lead)/interval) for T uniform between lo and hi."""
full = interval + lead # above this P-F interval a visit is certain
if full >= hi:
return ((hi - lead) ** 2 - (lo - lead) ** 2) / (2 * interval * (hi - lo))
part = ((full - lead) ** 2 - (lo - lead) ** 2) / (2 * interval * (hi - lo))
return part + (hi - full) / (hi - lo)
def p_sensor(k, lead=LEAD, lo=PF_LOW, hi=PF_HIGH):
"""Chance that k x T is at least the lead time, for T uniform between lo and hi."""
return float(np.clip((hi - lead / k) / (hi - lo), 0.0, 1.0))
timing_b = p_route(WEEKS_PER_MONTH)
rng = np.random.default_rng(10)
T = rng.uniform(PF_LOW, PF_HIGH, 1_000_000)
phase = rng.uniform(0.0, WEEKS_PER_MONTH, T.size) # time from point P to the next visit
timing_mc = np.mean(phase <= T - LEAD)
p_b = Q_ACT * timing_b
timing_c = p_sensor(K_LATE)
p_c = Q_ACT * timing_c
print("Application 2: machine A, expected yearly cost in currency units")
print(f" monthly interval {WEEKS_PER_MONTH:.3f} weeks")
print(f" (b) timing probability by formula {timing_b:.4f}, by simulation {timing_mc:.4f}")
print(f" (b) detected in time: {Q_ACT} x {timing_b:.4f} = {p_b:.3f}")
print(f" (c) timing probability {timing_c:.4f}; detected in time: {p_c:.3f}")
def cost_a(pf=P_FAIL):
return pf * C_UNPLANNED
def cost_b(pf=P_FAIL, pb=None):
pb = p_b if pb is None else pb
return ROUTE_COST + pf * (pb * C_PLANNED + (1 - pb) * C_UNPLANNED)
def cost_c(pf=P_FAIL, pc=None):
pc = p_c if pc is None else pc
return (SENSOR_COST + FALSE_CALLS * C_SPECIALIST
+ pf * (pc * (C_PLANNED + C_SPECIALIST) + (1 - pc) * C_UNPLANNED))
print(f" (a) no monitoring: {cost_a():8.0f}")
print(f" (b) monthly route: {cost_b():8.0f} (scheme {ROUTE_COST}, failures "
f"{cost_b() - ROUTE_COST:.0f})")
fixed_c = SENSOR_COST + FALSE_CALLS * C_SPECIALIST
print(f" (c) fitted sensor: {cost_c():8.0f} (scheme {fixed_c:.0f}, failures "
f"{cost_c() - fixed_c:.0f})")
print(" sensitivity 1: chance of a bearing failure in a year")
print(" p_fail (a) (b) (c)")
for pf in (0.02, 0.05, 0.10, 0.20):
print(f" {pf:5.2f} {cost_a(pf):7.0f} {cost_b(pf):7.0f} {cost_c(pf):7.0f}")
be_b = ROUTE_COST / (p_b * (C_UNPLANNED - C_PLANNED))
be_c = fixed_c / (p_c * (C_UNPLANNED - C_PLANNED - C_SPECIALIST))
print(f" (b) costs less than (a) only above p_fail = {be_b:.3f}; (c) above {be_c:.3f}")
print(" sensitivity 2: how late the fitted sensor sees the fault (share k of the P-F interval)")
print(" k p_c (c)")
for k in (0.50, 0.40, 0.25, 0.15, 0.10):
pc = Q_ACT * p_sensor(k)
print(f" {k:4.2f} {pc:5.3f} {cost_c(pc=pc):6.0f}")
pc_even = (fixed_c + P_FAIL * C_UNPLANNED - cost_b()) / (
P_FAIL * (C_UNPLANNED - C_PLANNED - C_SPECIALIST))
print(f" (c) equals (b) at p_c = {pc_even:.3f}")
print(f" one unplanned failure costs {C_UNPLANNED / cost_c():.0f} years of scheme (c)")
# ---------- Plot ----------
pf_axis = np.linspace(0.0, 0.25, 50)
fig, ax = plt.subplots(figsize=(8, 5))
ax.plot(pf_axis, cost_a(pf_axis), label="(a) no monitoring")
ax.plot(pf_axis, cost_b(pf_axis), label="(b) monthly route")
ax.plot(pf_axis, cost_c(pf_axis), label="(c) fitted sensor")
ax.axvline(P_FAIL, linewidth=0.8, color="grey")
ax.set_xlabel("assumed chance of a bearing failure in a year")
ax.set_ylabel("expected yearly cost (currency units)")
ax.set_title("Machine A: three schemes"); ax.legend(); fig.tight_layout()
fig.savefig("monitoring_programme_cost.png", dpi=120)
print("Saved monitoring_programme_cost.png")

Expected output

Application 1: criticality = cost score x standby score x repair time score
A compressor motor failure cost 30000 scores 3 x 3 x 2 = 18
D conveyor gearbox failure cost 14000 scores 2 x 3 x 2 = 12
B booster pump failure cost 7000 scores 2 x 2 x 2 = 8
C condenser fan failure cost 2500 scores 1 x 2 x 1 = 2
P-F interval rule: measure at intervals of no more than half the P-F interval
bearing defect, P-F 6 weeks: interval at most 3.00 weeks (21.0 days); monthly route gives 1.38 readings in the window on average; hourly sensor gives 1008
fast fault, P-F 3 days: interval at most 0.21 weeks (1.5 days); monthly route gives 0.10 readings in the window on average; hourly sensor gives 72
P-F 6 weeks: chance of a second monthly reading in the window 0.38
P-F 3 days: chance that a monthly visit falls in the window 0.099
Application 2: machine A, expected yearly cost in currency units
monthly interval 4.333 weeks
(b) timing probability by formula 0.8397, by simulation 0.8395
(b) detected in time: 0.9 x 0.8397 = 0.756
(c) timing probability 0.9375; detected in time: 0.844
(a) no monitoring: 3000
(b) monthly route: 2722 (scheme 1800, failures 922)
(c) fitted sensor: 1633 (scheme 920, failures 713)
sensitivity 1: chance of a bearing failure in a year
p_fail (a) (b) (c)
0.02 600 1984 1063
0.05 1500 2261 1277
0.10 3000 2722 1633
0.20 6000 3643 2347
(b) costs less than (a) only above p_fail = 0.087; (c) above 0.040
sensitivity 2: how late the fitted sensor sees the fault (share k of the P-F interval)
k p_c (c)
0.50 0.900 1481
0.40 0.844 1633
0.25 0.675 2091
0.15 0.375 2904
0.10 0.000 3920
(c) equals (b) at p_c = 0.442
one unplanned failure costs 18 years of scheme (c)
Saved monitoring_programme_cost.png

Common Mistakes



  • Starting with the instrument and not with the list of machines. Rank the machines by what a failure costs, then decide what to measure.
  • Setting one interval for every machine. The interval follows the P-F interval of the fault, and a fault of 3 days cannot be caught by a monthly route.
  • Setting limits and leaving the action open. Write the action and the owner of each alarm before the first alarm comes.
  • Expecting a low-cost fitted sensor to name the fault. It shows that the machine has changed, and a specialist with a proper analyser finds what has changed.
  • Treating the expected cost as a fact. It is as good as its weakest assumption, so show the sensitivity with the result.
  • Keeping the programme unchanged for years. Review it after every repair: was the fault seen, how early, and was the limit right.

Summary



  • A condition monitoring programme is a written loop: list and rank the machines, choose failure modes, measurements and intervals, set baselines and limits, fix the action for each alarm, and review.
  • With the stated scoring the four machines rank A (18), D (12), B (8) and C (2), the same order as their assumed failure costs of 30,000, 14,000, 7,000 and 2,500 currency units.
  • The commonly used rule sets the measurement interval at no more than about half the P-F interval: 3 weeks for a bearing defect with 6 weeks, and 1.5 days for a fault with 3 days, which only a fitted sensor can keep.
  • For machine A, on the stated assumptions, the expected yearly cost is 3,000 with no monitoring, 2,722 with a monthly route and 1,633 with a fitted sensor, and the order changes when the probability of failure falls below about 0.09.
  • A fitted low-cost sensor and a specialist with an analyser work together: the first gives the trend and the time, and the second gives the diagnosis.

Exercises



1. A gear fault has a P-F interval of 8 weeks with the chosen measurement, and a belt fault has a P-F interval of 10 days. Find the longest measurement interval for each by the commonly used rule.

Answer

Half of the P-F interval: 4 weeks for the gear fault and 5 days for the belt fault. A monthly route of 4.33 weeks is slightly too long for the gear fault and far too long for the belt fault.

2. A machine has a repair cost of 5,000 and lost production of 7,000 currency units, a full standby, and a repair time of 3 days. Find its criticality with the scoring of this lesson, and compare it with machines A to D.

Answer

The failure cost is 12,000, so the cost score is 2. A full standby scores 1 and a repair of 3 days scores 2. Criticality is . It ranks below pump B (8) and above fan C (2), although its failure cost is higher than that of pump B.

3. A fault always has a P-F interval of 4 weeks, and 1 week is needed to arrange the repair. Find the probability that a visit comes in time with a monthly route (4.33 weeks) and with a route every two weeks.

Answer

Monthly: . Every two weeks: is above 1, so the probability is 1. Halving the interval removes the timing risk for this fault.

4. A pump has a probability of failure of 0.15 in a year. An unplanned failure costs 20,000 and a planned repair 3,000 currency units. A monitoring scheme costs 1,000 a year and detects the fault in time with a probability of 0.80. Find the expected yearly cost with and without the scheme, and the probability of failure at which the two are equal.

Answer

Without: . With: . The scheme saves 1,040 a year on average. The two are equal when .

5. The P-F interval of a fault is uniform between 1 and 5 weeks. The route is walked every 2 weeks and half a week is needed to arrange the repair. Find the probability that a visit comes in time.

Answer

The probability for one interval is , which reaches 1 at weeks. The mean is .

References



  • ISO 17359:2018, Condition monitoring and diagnostics of machines. General guidelines.
  • J. Moubray, Reliability-centered Maintenance, 2nd edition, Industrial Press, 1997.
  • R. B. Randall, Vibration-based Condition Monitoring: Industrial, Automotive and Aerospace Applications, 2nd edition, Wiley, 2021.
  • C. Scheffer and P. Girdhar, Practical Machinery Vibration Analysis and Predictive Maintenance, Newnes (Elsevier), 2004.


© 2021-2026 SiliconWit®. All rights reserved.
A compressor motor 24.42 Hz if it fails: product at risk B booster pump 48.33 Hz if it fails: water supply C condenser fan belt drive if it fails: reduced capacity D conveyor gearbox if it fails: line stops
The site: four machines, four different costs of failure
List and rank Failure modes Measurement and interval Baseline and limits Review Repair Diagnose Alarm and action and again Each review corrects the plan, and the loop starts again.
The programme is a loop, not a list
route visits visit next visit fitted sensor fault P F 3 days, 72 sensor readings day 0 day 10 day 20 day 30 time one month between visits: neither visit sees this fault
A fast fault between two monthly visits
Predict first

A low-cost sensor fitted on a motor sees a bearing fault later than a monthly route reading with a proper analyser would. Can the fitted sensor still be the cheaper scheme over a year?

Watch it build: the P-F interval sets the interval
F P P: first detectable F: failure P-F interval P envelope: early P overall level: late P 6 weeks t ≤ 6 ÷ 2 = 3 weeks two readings inside monthly: 4.33 weeks a second reading inside only 38 % of the time
  1. P is where the fault can first be detected; F is failure. Between them lies the P-F interval.
  2. The interval belongs to the measurement too: envelope analysis finds P early, the overall level late.
  3. For a P-F interval of 6 weeks, read at least every 3 weeks: two readings fall inside, alert and confirm.
  4. A monthly route, 4.33 weeks apart, puts a second reading inside only 38 % of the time.
P: envelopeP: overall levelF: failure long warningshort warning
route visitroute visit fault: 3 days fitted sensor: a reading every hour one month
See it: which scheme costs least, and on which guess it turns

Route detects in time
Fitted sensor detects in time
Cheapest scheme

Every figure is the lesson's stated assumption for the drive-end bearing of machine A, in currency units: an unplanned failure 30,000, a planned repair 2,500, a P-F interval anywhere from 2 to 10 weeks, 1 week to act, and 9 readings in 10 recognised. A route visit costs 150; the fitted sensor costs 920 a year with its reviews and false calls, and 400 for the specialist each time it finds a fault. Dark part of each bar: what the scheme costs every year. Light part: the expected cost of repairs and failures.

Check yourself

Three questions. Each wrong choice is a mistake people really make, so read the note after you answer.

1. Oil analysis on a gearbox gives about 6 weeks between the first sign of wear (P) and failure (F). By the commonly used rule, what is the longest interval between samples?

2. A scheme costs 500 a year. The fault has a 0.2 chance of developing in a year, the scheme detects it in time with a chance of 0.8, a planned repair costs 2,000 and an unplanned failure 20,000. What is the expected yearly cost?

3. On a site's figures, monitoring a small pump costs slightly more each year than its expected failure cost. The manager still pays for it. Which reason can make that sound?

Found this useful?

Discussion

    Comments show your name. Be kind, stay on the topic.