Wire-to-water efficiency
Energy per Cubic Metre: Auditing a Pump
On this page
A pump that is losing efficiency does not stop. The water still arrives, the tank still fills, and the only change is that the pump runs a little longer and the bill is a little higher each month. Nobody is told, because no instrument on site shows a loss, and after some years the owner pays for much more electricity than the water needs. This lesson joins the whole course into one method: measure four quantities, calculate the energy used for each cubic metre, compare it with what the design promised, and find where the difference comes from. #PumpAudit #SpecificEnergy #EnergyEfficiency
Learning Objectives
By the end of this lesson, you will be able to:
- Calculate the total head of a working pump from a pressure, a level and a flow
- Calculate wire-to-water efficiency and specific energy, and the ideal specific energy for the measured head
- Decide whether a gap from the design comes from the pump or from the system
- State the uncertainty of a measured efficiency and judge whether a measured drop is real
- Price a gap as a yearly cost and find the simple payback of a repair
Real-World System Problem: The borehole installation two years later
The borehole installation of this course was designed to deliver 12.14 m³/h at a head of 78.09 m, with 0.4217 kWh of electricity for each cubic metre. It has now run for two years. The owner reports that the tank takes longer to fill than it did. Nothing has tripped and nothing leaks on the surface.
The pump is 70 m down the borehole and cannot be inspected without a crane. So the question must be answered from the surface: is the installation still doing what it was designed to do, and if not, is the fault in the pump, in the pipe, or in the borehole?
Four instruments are enough.
Fundamental Theory: From four measurements to one number
Wire-to-water efficiency
Electrical energy enters at the supply cable, the wire, and useful energy leaves as water lifted and pushed through the pipe. Between them, the motor, the pump and any drive each keep a share as heat.
The borehole set was designed for
Specific energy and its ideal value
The specific energy
Lifting one cubic metre of water through a head
Check the units:
Specific energy from head and efficiency
A real installation uses the ideal energy divided by its wire-to-water efficiency. Only two things can raise
At the design point,
Why this one number, and what it hides
Specific energy is the number to follow through the life of a pumping system. It needs only two instruments, a flow meter and a power meter, and it is what the owner pays for, since the daily volume is fixed by the demand.
It also hides something: a higher
Total head from site measurements
The pump is out of reach, so its head is built from what can be measured. Apply the energy equation from the water surface in the borehole to the pressure gauge at ground level.
Total head of a borehole pump
The first two terms are measured; the last two are small and calculated from the flow. A common mistake is to convert the gauge pressure to metres and call that the pump head. In this installation the gauge shows about a third of it: the largest part is the lift from the water level to the ground, which no gauge at the surface can see.
How well the measurements must be made
Every instrument has an uncertainty, and the result cannot be better than the instruments. The efficiency is a product and a quotient of three measured quantities,
This assumes that the three errors are independent. The specific energy needs only two of the terms, flow and power.
Two points follow. The flow meter is usually the weakest of the three, and it enters both the efficiency and the specific energy. And an uncertainty stated as a percentage of span is large when the reading is a small part of the span, so choose a pressure range that fits the pressure.
Act on a measured drop only when it is clearly larger than the uncertainty. For a trend the absolute accuracy matters less: the same instruments in the same place repeat far better than their stated accuracy, so a slow rise in their record is real long before a single audit could prove it.
Common causes of a gap
Each cause leaves a different pattern in the four measurements. “Deeper” and “shallower” refer to the pumping water level in the borehole.
| Cause | Flow at the meter | Discharge pressure | Pumping level | Input power | Where the point lies |
|---|---|---|---|---|---|
| Worn impeller or wear rings (water recirculates inside the pump) | Lower | Lower | Slightly shallower | Slightly lower | Below the pump curve, on the system curve |
| Valve part closed, or scale and blockage after the gauge | Lower | Higher | Shallower | Lower | On the pump curve, above the system curve |
| Falling water table | Lower | Slightly lower | Deeper, also at rest | Lower | On the pump curve, system curve shifted up |
| Leak in the pipe inside the borehole (the water falls back) | Lower | Lower | Slightly shallower | Higher | As for wear, but the power is higher |
| Leak after the meter | Higher | Lower | Deeper | Higher | On the pump curve, below the system curve |
| Wrong pump for the system | As on the first day | As on the first day | As on the first day | As on the first day | On both curves, far from the best efficiency point |
| Motor or supply fault | Same | Same | Same | Higher | On both curves, with low efficiency |
The power column is for a pump whose shaft power rises with flow, such as the pumps of this course. The last column is the test that matters most: plot the measured flow and head on the same sheet as the pump curve and the system curve.
A simple audit method
Take the readings only when the pump has run long enough for the level and the flow to be steady, and take all four in the same minute.
Application 1: The audit of the borehole pump
Step 1: Total head
Click to reveal the head built from the measurements
-
Pressure head at the gauge.
The gauge shows 25.33 m of water. ✅
-
Velocity head. The pipe area is
and the flow is . The velocity head is 0.05 m, small but counted. ✅
-
Loss between the pump and the gauge.
, and Swamee-Jain gives . The pipe inside the borehole and its two fittings take 1.27 m. ✅
-
Total head. The gauge is at ground level, so
is the pumping water level, 49.5 m. The pump is producing 76.15 m, against 78.09 m at the design point. ✅
Step 2: Hydraulic power, efficiency and specific energy
Click to reveal the three results
-
Hydraulic power.
The water receives 2.319 kW. ✅
-
Wire-to-water efficiency.
The installation turns 46.8 percent of the electricity into useful work, against 50.4 percent by design. ✅
-
Specific energy.
Each cubic metre costs 0.4429 kWh, 5.0 percent more than the design 0.4217. ✅
-
Check a second way. The ideal energy for the measured head is
kWh/m³. Divided by the efficiency, kWh/m³, the same as step 3. ✅
Step 3: The pump or the system?
Click to reveal the comparison with the two curves
-
What the system needs at the measured flow.
The measured head is 76.15 m, only 0.03 m from the system curve. The system has not changed: no valve has been closed, the pipe has not scaled, and the water level is where the design expects it at this flow. ✅
-
What a new pump gives at the measured flow.
The pump gives 76.15 m, which is 92.1 percent of 82.67 m. It is 6.52 m short, a loss of 7.9 percent of its head. ✅
-
Pump efficiency. Taking the motor efficiency as still 0.82:
A new pump at 11.2 m³/h has
. The pump has lost 5.0 points of efficiency. ✅ -
Verdict. The point lies on the system curve and below the pump curve. This is the first row of the table of causes: the pump is worn, and the system is as designed. The level agrees: 49.5 m is slightly shallower than the design 50.1 m, as expected with less flow and a static level that has not moved. ✅
Step 4: Is the drop larger than the uncertainty?
Click to reveal the uncertainty of the result
-
Head. The pressure uncertainty is 0.5 percent of 16 bar, which is 0.08 bar, or
m. Combined with the 0.1 m of the level: The head is known to about 1.1 percent. ✅
-
Efficiency.
The measured efficiency is
. ✅ -
Compare. The drop from the design is
, about 2.8 times the uncertainty. The drop is real. ✅ -
Specific energy. Its uncertainty is
percent, or 0.011 kWh/m³. The rise is kWh/m³, about 1.9 times the uncertainty. It is real, but less clearly than the drop of efficiency. ✅ -
Head of the pump. The shortfall of 6.52 m has an uncertainty of 1.33 m, from the head measurement and from the flow at which the pump curve is read. The shortfall is five times larger. ✅
Application 2: The cost of the gap and the payback of an overhaul
Step 1: Yearly energy and cost
Click to reveal the cost of the gap
-
Yearly energy now.
The pump now uses 17,781 kWh a year. ✅
-
The gap.
The wear costs 849 kWh a year. ✅
-
In money.
The gap costs about 10,200 currency units a year at the example price. ✅
-
Running time.
hours a day, against 9.06 by design. The pump runs 0.76 hours longer each day. ✅
Step 2: Payback
Click to reveal the payback and the level at which to act
-
Simple payback.
The saving would repay the overhaul in 3.9 years at today’s wear. ✅
-
Specific energy for a payback of two years. The saving must be
currency units a year, which is kWh a year. Spread over m³: When the record reaches 0.463 kWh/m³, the overhaul pays back in two years. ✅
-
Check a second way. At 0.463 kWh/m³ the yearly energy is
kWh, which is 1,657 kWh above the design. At 12.00 a kWh that is 19,900 currency units, and years. ✅
Verify It in Python
The first part of the script is the hidden truth: it solves the worn duty point with a root finder and prints what perfect instruments would show. The second part is the audit, which starts from the four rounded readings alone. The script saves a plot of the measured point, with its uncertainty bars, against the pump and system curves.
"""Audit of a borehole pump from four measurements: flow, pressure, level, power."""import numpy as npfrom scipy.optimize import brentqimport matplotlib.pyplot as plt
RHO, G = 998.0, 9.81 # water at 20 degCNU, D, EPS = 1.004e-6, 0.063, 0.0015e-3AREA = np.pi * D**2 / 4STATIC, C = 42.0, 8.0 / 12.0 # m below ground, m per m3/hK_BELOW, K_AFTER = 2.9, 2.9 # fittings before and after the gaugeETA_MOTOR, PRICE, DAILY = 0.82, 12.00, 110.0DESIGN = dict(q=12.14, h=78.09, p_in=5.120, sec=0.4217, eta_ww=0.5036, year=16932.0)
def pump_new(q): return 110.0 - 0.2 * q - 0.2 * q**2
def system(q): # valid from 4 to 16 m3/h return 59.65 + 0.8948 * q + 0.05143 * q**2
def eta_new(q): return 0.62 - 0.0045 * (q - 11.0) ** 2
def pipe(q, length, k_sum): """Return velocity head and head loss (m) in the 63 mm main.""" v = q / 3600.0 / AREA re = v * D / NU f = 0.25 / np.log10(EPS / (3.7 * D) + 5.74 / re**0.9) ** 2 vh = v**2 / (2 * G) return vh, (f * length / D + k_sum) * vh
# ---------- The hidden truth: generate what the instruments would show ----------q_true = brentq(lambda q: 0.92 * pump_new(q) - system(q), 4.0, 16.0)h_true = 0.92 * pump_new(q_true)p_true = RHO * G * (q_true / 3600) * h_true / 1000 / (eta_new(q_true) - 0.05) / ETA_MOTORvh, loss_surface = pipe(q_true, 450.0, K_AFTER)bar_true = RHO * G * (18.0 + loss_surface) / 1e5print("Hidden truth (worn pump on the unchanged system curve)")print(f" Q = {q_true:.3f} m3/h, H = {h_true:.2f} m, input {p_true:.3f} kW")print(f" gauge {bar_true:.3f} bar, pumping water level {STATIC + C * q_true:.2f} m")
# ---------- The audit: start from the rounded readings ----------Q, P_BAR, LEVEL, P_IN = 11.2, 2.48, 49.5, 4.96vh, loss_riser = pipe(Q, 70.0, K_BELOW)head_gauge = P_BAR * 1e5 / (RHO * G)H = LEVEL + head_gauge + vh + loss_riserp_h = RHO * G * (Q / 3600.0) * H / 1000.0eta_ww = p_h / P_INsec = P_IN / Qk_ideal = RHO * G / 3.6e6print("Application 1: the audit")print(f" ideal energy constant = {k_ideal:.6f} kWh/m3 per metre of head")print(f" pressure head {head_gauge:.2f} m, velocity head {vh:.3f} m, " f"loss below the gauge {loss_riser:.2f} m")print(f" total head H = {H:.2f} m")print(f" hydraulic power = {p_h:.3f} kW")print(f" wire-to-water efficiency = {eta_ww:.4f} (design {DESIGN['eta_ww']:.4f})")print(f" specific energy = {sec:.4f} kWh/m3 (design {DESIGN['sec']:.4f}), " f"ideal at this head {k_ideal * H:.4f}")print(f" system curve at {Q} m3/h = {system(Q):.2f} m, " f"measured minus curve = {H - system(Q):+.2f} m")print(f" new pump at {Q} m3/h = {pump_new(Q):.2f} m, " f"measured is {100 * H / pump_new(Q):.1f} % of it " f"({pump_new(Q) - H:.2f} m short)")print(f" pump efficiency = {eta_ww / ETA_MOTOR:.4f} with the motor at {ETA_MOTOR}, " f"new pump at this flow {eta_new(Q):.4f}")
# ---------- Uncertainty ----------u_q, u_p = 2.0, 1.5 # percent of readingu_h_m = np.hypot(0.005 * 16.0 * 1e5 / (RHO * G), 0.1) # pressure span, levelu_h = 100 * u_h_m / Hu_eta = np.sqrt(u_q**2 + u_h**2 + u_p**2)u_sec = np.hypot(u_q, u_p)print("Uncertainty")print(f" head: {u_h_m:.2f} m = {u_h:.2f} %")print(f" efficiency: {u_eta:.2f} % of value = {eta_ww * u_eta / 100:.4f}; " f"drop from design = {DESIGN['eta_ww'] - eta_ww:.4f}")print(f" specific energy: {u_sec:.2f} % = {sec * u_sec / 100:.4f} kWh/m3; " f"rise from design = {sec - DESIGN['sec']:.4f}")slope = 0.2 + 0.4 * Qprint(f" pump head deficit: uncertainty {np.hypot(u_h_m, slope * Q * u_q / 100):.2f} m " f"against {pump_new(Q) - H:.2f} m")
# ---------- Application 2: cost ----------gap_kwh = sec * DAILY * 365 - DESIGN["year"]overhaul = 40000.0print("Application 2: cost of the gap")print(f" yearly energy {sec * DAILY * 365:.0f} kWh against " f"{DESIGN['year']:.0f} kWh, gap {gap_kwh:.0f} kWh")print(f" yearly cost of the gap = {gap_kwh * PRICE:.0f} currency units")print(f" hours a day {DAILY / Q:.2f} against {DAILY / DESIGN['q']:.2f}")print(f" simple payback of a {overhaul:.0f} overhaul = " f"{overhaul / (gap_kwh * PRICE):.1f} years")sec_2y = DESIGN["sec"] + overhaul / 2 / PRICE / (DAILY * 365)print(f" payback falls to 2 years when the specific energy reaches {sec_2y:.3f} kWh/m3")
# ---------- Plot ----------qq = np.linspace(4.0, 16.0, 100)fig, ax = plt.subplots(figsize=(7, 4.5))ax.plot(qq, pump_new(qq), label="pump curve, new")ax.plot(qq, 0.92 * pump_new(qq), "--", label="pump curve, 8 % less head")ax.plot(qq, system(qq), label="system curve")ax.plot(DESIGN["q"], DESIGN["h"], "s", color="grey", label="design duty point")ax.errorbar(Q, H, xerr=Q * u_q / 100, yerr=u_h_m, fmt="o", color="black", capsize=3, label="measured point")ax.set_xlabel("flow (m3/h)")ax.set_ylabel("head (m)")ax.legend()fig.tight_layout()fig.savefig("pump_audit.png", dpi=120)print("Saved pump_audit.png")Expected output
Hidden truth (worn pump on the unchanged system curve) Q = 11.190 m3/h, H = 76.10 m, input 4.956 kW gauge 2.481 bar, pumping water level 49.46 mApplication 1: the audit ideal energy constant = 0.002720 kWh/m3 per metre of head pressure head 25.33 m, velocity head 0.051 m, loss below the gauge 1.27 m total head H = 76.15 m hydraulic power = 2.319 kW wire-to-water efficiency = 0.4676 (design 0.5036) specific energy = 0.4429 kWh/m3 (design 0.4217), ideal at this head 0.2071 system curve at 11.2 m3/h = 76.12 m, measured minus curve = +0.03 m new pump at 11.2 m3/h = 82.67 m, measured is 92.1 % of it (6.52 m short) pump efficiency = 0.5703 with the motor at 0.82, new pump at this flow 0.6198Uncertainty head: 0.82 m = 1.08 % efficiency: 2.72 % of value = 0.0127; drop from design = 0.0360 specific energy: 2.50 % = 0.0111 kWh/m3; rise from design = 0.0212 pump head deficit: uncertainty 1.33 m against 6.52 mApplication 2: cost of the gap yearly energy 17781 kWh against 16932 kWh, gap 849 kWh yearly cost of the gap = 10185 currency units hours a day 9.82 against 9.06 simple payback of a 40000 overhaul = 3.9 years payback falls to 2 years when the specific energy reaches 0.463 kWh/m3Saved pump_audit.pngIn the plot, the measured point sits on the system curve and on the dashed curve of the worn pump, and its uncertainty bars do not reach the curve of the new pump.
Common Mistakes
- Taking the gauge pressure at ground level as the pump head. On a borehole the lift from the pumping water level is the larger part, so the level must be measured as well.
- Comparing the measured head with the design head only. Compare it with the pump curve at the measured flow, because a worn pump works at a different flow.
- Reading the four quantities at different times. The flow and the level change through a run, so readings from different minutes do not belong to the same point.
- Using motor current in place of power. Current does not include the power factor, which changes with load.
- Treating a low specific energy as proof of health. A leak after the meter raises the metered flow and makes the number look better while water is lost.
Summary
- Wire-to-water efficiency is the hydraulic power
divided by the electrical input. Specific energy is the electrical input divided by the flow, in kWh/m³. - The ideal specific energy is
kWh/m³ for water, and the real value is that figure divided by the wire-to-water efficiency. - The total head of a borehole pump is the depth of the pumping water level, plus the pressure head at the gauge, plus the velocity head and the small loss below the gauge.
- The audited pump gives 11.2 m³/h at 76.15 m with an efficiency of
and 0.4429 kWh/m³. The point lies on the system curve and 7.9 percent below the pump curve, so the pump is worn and the system is unchanged. - The gap costs 849 kWh and about 10,200 currency units a year. An overhaul at 40,000 currency units pays back in 3.9 years, and in two years once the record reaches 0.463 kWh/m³.
- One audit gives a verdict. A continuous record of kWh for each cubic metre gives the date on which to act.
Exercises
1. A pump lifts water through a total head of 45 m. Find the ideal specific energy, and the real specific energy if the wire-to-water efficiency is 0.55.
Answer
2. A booster pump delivers 18 m³/h at a total head of 30 m and takes 3.20 kW from the supply. Find the hydraulic power, the wire-to-water efficiency and the specific energy.
Answer
3. An audit uses a flow meter of ±1 percent, a head measurement of ±1.5 percent and a power meter of ±1 percent. Find the uncertainty of the wire-to-water efficiency. If the measured value is 0.52, can a drop from a design value of 0.53 be called real?
Answer
4. In Application 2 the overhaul is quoted at 60,000 currency units instead of 40,000. Find the simple payback at today’s gap, and the specific energy at which the payback would be two years.
Answer
Payback:
5. A second borehole installation, identical to the one of Application 1 when new, is audited. The readings are: flow 10.0 m³/h, discharge pressure 3.75 bar at the same gauge position, pumping water level 48.7 m below ground, electrical input 4.74 kW. Find the total head, the wire-to-water efficiency and the specific energy. Decide whether the pump or the system is the cause.
Answer
Pressure head
References
- I. J. Karassik, J. P. Messina, P. Cooper and C. C. Heald, Pump Handbook, 4th edition, McGraw-Hill, 2008.
- Hydraulic Institute and Europump, Pump Life Cycle Costs: A Guide to LCC Analysis for Pumping Systems, 2001.
- ISO 9906:2012, Rotodynamic pumps: Hydraulic performance acceptance tests, Grades 1, 2 and 3.
- JCGM 100:2008, Evaluation of measurement data: Guide to the expression of uncertainty in measurement.
A borehole pump runs with the water level 49.5 m below ground. A pressure gauge on the rising main at ground level reads 2.48 bar, which is about 25 m of water. About how much head is the pump giving?
The head is built from the readings as in Application 1: the depth of the pumping water level, the gauge pressure as a head, the velocity head, and the loss in the 70 m of 63 mm pipe below the gauge. The solid curve is the new pump, the coloured curve the system. A point on the system curve and below the pump curve means a worn pump; a point on the pump curve and off the system curve means the system has changed. The bar on the dot is about ±0.8 m, the head uncertainty of the lesson.
Check yourself
Three questions. Each wrong choice is a mistake people really make, so read the note after you answer.
1. A pump delivers 10 m³/h against a total head of 80 m and takes 5.0 kW from the supply. What is its wire-to-water efficiency?
2. An audit finds less flow than the design. The discharge pressure is higher than before, the pumping water level is a little shallower, and the measured point lies on the new pump curve but above the system curve. What has happened?
3. A flow meter of ±3 percent, a head of ±1 percent and a power meter of ±1.5 percent give a wire-to-water efficiency of 0.48. The design was 0.50. What should the owner do?
- Specific energy: supply power over flow. 5.12 kW ÷ 12.14 m³/h = 0.422 kWh/m³.
- Lifting one cubic metre through 78.1 m needs ρ g H = 764 kJ, whatever machine does it.
- 764 kJ is 0.212 kWh: the least energy this head allows for each cubic metre.
- Divided by the wire-to-water efficiency 0.504: 0.422 kWh/m³. Half becomes heat.
- The audit: 0.443 kWh/m³. Head and efficiency both changed, and one number cannot say which.
Discussion
No comments yet. Questions, results from your own build, a better way to explain it: all welcome.
My notes on this page
Kept on this device only. Nothing is sent anywhere.
Tip: select words in the lesson, or tap a figure or an equation, to put a note right there.
Notes on earlier wording
The lesson has changed and these words are no longer in it. Your notes are kept, with the words you chose.